Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Building Above Ceiling
Permit Number - T21CM00864
Inspection Description - COT - HCBU - Building Above Ceiling
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - HCBU - Building Above Ceiling | Not Ready | ||
09/16/2022 | COT - HCBU - Building Above Ceiling | ESTEVENS | Partial Approval | Entered by VVERA1 - Partial. Ok to cove up canopy. |
08/16/2022 | COT - HCBU - Building Above Ceiling | ESTEVENS | Partial Approval | Entered by NGARCIA3 - Partial. Level 2. Units 2054, 2059. 2062, 2051, 2048, 2065, 2068, 2045. 2071, 2042, 2074. |
01/04/2023 | COT - HCBU - Building Above Ceiling | Partial Pass | 4th floor above ceiling | |
01/09/2023 | COT - HCBU - Building Above Ceiling | Partial Pass | partial approval for fitness room and admin offices | |
01/11/2023 | COT - HCBU - Building Above Ceiling | Partial Pass | partial approval for maintenance office above ceiling | |
01/13/2023 | COT - HCBU - Building Above Ceiling | Partial Pass | partial approval for food prep room | |
01/17/2023 | COT - HCBU - Building Above Ceiling | Not Ready | ||
01/18/2023 | COT - HCBU - Building Above Ceiling | Not Ready | ||
01/27/2023 | COT - HCBU - Building Above Ceiling | Passed | First floor corridors, break rooms, and meeting rooms are complete. Okay to install ceiling tiles. | |
11/03/2022 | COT - HCBU - Building Above Ceiling | Partial Pass | partial approval for rms 149-181 above ceiling first floor | |
11/04/2022 | COT - HCBU - Building Above Ceiling | Partial Pass | partial approval for all first floor guest rooms | |
11/14/2022 | COT - HCBU - Building Above Ceiling | Partial Pass | Level #1, East side corridor above ceiling. OK ‘to cover progress areas | |
11/18/2022 | COT - HCBU - Building Above Ceiling | Partial Pass | partial approval for third floor elevator lobby partial approval for 1st floor lobby restrooms |
|
11/22/2022 | COT - HCBU - Building Above Ceiling | Partial Pass | Partial APPROVAL First FLOOR public area above hard lids | |
11/29/2022 | COT - HCBU - Building Above Ceiling | Re-inspection required | ||
11/30/2022 | COT - HCBU - Building Above Ceiling | Not Ready | ||
12/13/2022 | COT - HCBU - Building Above Ceiling | Partial Pass | partial approval for first floor meeting room above drop hard lids | |
12/16/2022 | COT - HCBU - Building Above Ceiling | Partial Pass | first floor corridor north of meeting room | |