Inspection Status: Complete (Recurring)
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 03/14/2023 |
ENGR Engineering Final
|
|
Complete (Recurring) |
Contractor formed storm drain from existing to new one on the northside and one on the southside. Remove the pile of spoils that’s on the northside of the building and the trash bin container needs to be removed. |
| 03/14/2023 |
ENGR Engineering Final
|
|
Partial Pass |
OK FOR TCO LEVEL 4 FOR ALL FLOORS |
| 04/07/2023 |
ENGR Engineering Final
|
|
Partial Pass |
|
| 04/13/2023 |
ENGR Engineering Final
|
|
Passed |
|