Inspection Status: Passed
Inspection History: COT - HCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 02/22/2022 |
COT - HCBU - Preslab |
DMUNIZ |
Approved |
Entered by VVERA1 - Approved |
| 02/09/2022 |
COT - HCBU - Preslab |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - Partial, Spread footings, continuous footing, Post tension and re bar re enforcement Inspected and ok for concrete placement from (GL 1-16) |
| 02/08/2022 |
COT - HCBU - Preslab |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, Post tension and Continuous exterior footing from Grid lines (12-21, A-G) ok for concrete placement. |
| 03/16/2022 |
COT - HCBU - Preslab |
TGAUSP |
Approved |
Entered by VVERA1 - Approved |
| 03/15/2022 |
COT - HCBU - Preslab |
TGAUSP |
Not ready for Inspection |