Inspection Status: Not Ready

Inspection History: COT - HCPL - Plumbing Above Ceiling

Date Description Inspector Results Comments
10/26/2022 COT - HCPL - Plumbing Above Ceiling Not Ready
09/27/2022 COT - HCPL - Plumbing Above Ceiling JBURGE Partial Approval Entered by NGARCIA3 - Partial. Level #3 corridors, kitchen and restrooms.
09/26/2022 COT - HCPL - Plumbing Above Ceiling WGALLAGHER Partial Approval Entered by VVERA1 - Partial approval for above hard ceiling in restrooms and closets excluding 2027, 2095, 2110, and 2004
09/22/2022 COT - HCPL - Plumbing Above Ceiling TGAUSP Cancelled Entered by NGARCIA3 - Inspection canceled by contractor
09/21/2022 COT - HCPL - Plumbing Above Ceiling WGALLAGHER Partial Approval Entered by VVERA1 - Partial approval above 3rd floor corridor hard lids And rooms 2030 t0 2080 and 3rd floor storage
09/02/2022 COT - HCPL - Plumbing Above Ceiling JBURGE Not ready for Inspection Entered by VVERA1 - Not ready. Contractor cancelled
08/30/2022 COT - HCPL - Plumbing Above Ceiling WGALLAGHER Partial Approval Entered by NGARCIA3 - Partial approval for rooms 3094 through 3020, 3100, 3012, 3006, 3109, 3009 only AND 4th floor corridor above soffits
08/18/2022 COT - HCPL - Plumbing Above Ceiling WGALLAGHER Partial Approval Entered by NGARCIA3 - Partial approval rooms 2042 to 2071
08/16/2022 COT - HCPL - Plumbing Above Ceiling ESTEVENS Partial Approval Entered by NGARCIA3 - Partial. Level 2. DWV ONLY. 2039, 2077, 2036, 2033, 2080, 2027, 2030, 2086, 2083, 2089, 2092, 2095, 2098. 2018, 2010, 2013, 2101, 2104, 2004, 2007, 2107, 2110.
08/16/2022 COT - HCPL - Plumbing Above Ceiling ESTEVENS Partial Approval Entered by NGARCIA3 - Partial. Level 2. Units 2054, 2059. 2062, 2051, 2048, 2065, 2068, 2045. 2071, 2042, 2074.
07/29/2022 COT - HCPL - Plumbing Above Ceiling DMUNIZ Partial Approval Entered by NGARCIA3 - PARTIAL, DWV & water lines above ceiling for 4th floor ok to Sheetrock.
07/27/2022 COT - HCPL - Plumbing Above Ceiling DMUNIZ Partial Approval Entered by VVERA1 - Partial, 4TH Floor guest rooms East corridor, above ceiling inspection for bathroom hard lids ok to proceed with progress areas.
01/04/2023 COT - HCPL - Plumbing Above Ceiling Partial Pass partial approval for 4th floor corridor
01/09/2023 COT - HCPL - Plumbing Above Ceiling Partial Pass
01/11/2023 COT - HCPL - Plumbing Above Ceiling Partial Pass partial approval for maintenance office above ceiling
01/13/2023 COT - HCPL - Plumbing Above Ceiling Partial Pass partial approval for food prep room
01/17/2023 COT - HCPL - Plumbing Above Ceiling Not Ready
01/18/2023 COT - HCPL - Plumbing Above Ceiling Not Ready
01/27/2023 COT - HCPL - Plumbing Above Ceiling Passed All plumbing pipes and fire sprinkler pipes are properly supported to plumbing rack. Okay to install ceiling tile.
11/03/2022 COT - HCPL - Plumbing Above Ceiling Partial Pass partial approval for first floor guest rooms 149-181
11/14/2022 COT - HCPL - Plumbing Above Ceiling Partial Pass
11/18/2022 COT - HCPL - Plumbing Above Ceiling Partial Pass partial approval for elevator lobby 3rd floor.
partial approval for 1st floor lobby restrooms
11/22/2022 COT - HCPL - Plumbing Above Ceiling Partial Pass partial approval for first floor public areas hard lids
11/29/2022 COT - HCPL - Plumbing Above Ceiling Re-inspection required
11/30/2022 COT - HCPL - Plumbing Above Ceiling Not Ready
12/09/2022 COT - HCPL - Plumbing Above Ceiling Partial Pass partial approval for ice room first floor
12/13/2022 COT - HCPL - Plumbing Above Ceiling Partial Pass partial approval for meeting room first floor ok for hard lids
12/16/2022 COT - HCPL - Plumbing Above Ceiling Partial Pass first floor corridor north of meeting room