Inspection Status: Passed

Inspection History: COT - HCBU - Masonry Pregrout 

Permit Number - T21CM00864

Inspection Description - COT - HCBU - Masonry Pregrout 

Inspection Status - Passed

Date Description Inspector Results Comments
03/08/2022 COT - HCBU - Masonry Pregrout  DMUNIZ Approved Entered by VVERA1 - Approved, final lift for CMU Elevator shaft complete.
03/07/2022 COT - HCBU - Masonry Pregrout  DMUNIZ Partial Approval Entered by VVERA1 - Partial, 12TH lift CMU Elevator shaft @ 48’ ok to grout.
03/04/2022 COT - HCBU - Masonry Pregrout  TGAUSP Cancelled Entered by VVERA1 - cancelled by Contractor due to wind
03/02/2022 COT - HCBU - Masonry Pregrout  DMUNIZ Partial Approval Entered by VVERA1 - No inspection required today see previous notes.
03/01/2022 COT - HCBU - Masonry Pregrout  DMUNIZ Partial Approval Entered by NGARCIA3 - Partial, 8TH LIFT CMU elevator shaft ok to grout and proceed.
02/28/2022 COT - HCBU - Masonry Pregrout  DMUNIZ Partial Approval Entered by VVERA1 - Partial, 7th lift CMU Elevator shaft ok for grout.
02/25/2022 COT - HCBU - Masonry Pregrout  DMUNIZ Partial Approval Entered by NGARCIA3 - Partial.- 5th & 6th lift of CMU @ Elevator shaft ok to grout and proceed.
02/23/2022 COT - HCBU - Masonry Pregrout  DMUNIZ Partial Approval Entered by NGARCIA3 - Partial, 4TH lift CMU @Elevator shaft ok to grout and proceed.
02/22/2022 COT - HCBU - Masonry Pregrout  DMUNIZ Partial Approval Entered by VVERA1 - Partial, 3RD LIFT for CMU ELEVATOR SHAFT WALLS OK for grout.
02/18/2022 COT - HCBU - Masonry Pregrout  TGAUSP Partial Approval Entered by NGARCIA3 - Partial for 2nd lift (10’-4” from pit) of the CMU elevator shaft, okay to grout
02/09/2022 COT - HCBU - Masonry Pregrout  DMUNIZ Not ready for Inspection Entered by RSALDAT1 - Not Ready
01/20/2022 COT - HCBU - Masonry Pregrout  DMUNIZ Partial Approval Entered by VVERA1 - Partial, first lift for elevator shaft CMU walls ok to grout and proceed.