Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Apply Date:
04/23/2020
Applicant:
KIM PRESSGROVE
Description:
NEW HOTEL
Architects:
  • DAVID RICHARD SCHUKAI
Contractors:
  • CHASSE BUILDING TEAM INC
  • CHASSE BUILDING TEAM INC***APA***

Permit Reviews

Permit Number - T20CM02530
Permit Status: C of o
Permit Description: NEW HOTEL
Start Date Submittal Complete Date Status  
01/25/2021 REVISION - - 1ST 12/17/2021 COMPLETED Review Details
04/23/2020 PLANS OK TO SUBMIT - COMM 06/01/2020 COMPLETED Review Details
06/01/2020 COMMERCIAL - NEW 08/20/2020 COMPLETED Review Details
08/25/2020 RESUBMITTAL 09/14/2020 COMPLETED Review Details
09/14/2020 RESUBMITTAL 09/16/2020 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T20CM02530
Permit Description: NEW HOTEL
Total Completed Inspections - 41
Date Description Inspector Results Comments
10/27/2020 ELECTRIC - UFER DMUNIZ Approved partial, uffers in footings.
11/06/2020 ELECTRIC - UNDERGROUND DMUNIZ Approved Partial, Secondary conduits from Switchgear to interior Electrical room (Gl12- Elevator shaft.) ok to backfill progress.
11/17/2020 PLUMBING - ROUGH, SOIL DMUNIZ Approved Approved, completion of Under slab plumbing from GL1-6 ok to backfill.
11/25/2020 BUILDING PRE-SLAB DMUNIZ Approved Partial, ok for concrete placement GL 1-7.
12/01/2020 EXCAVATION/LAYOUT REBAR & ZON ESTEVENS Approved Not ready.
12/03/2020 SHEET ROCK NAILING JBURGE Approved Partial. Level #1 corridor ceiling from South stairway to room#102. Two layers of sheet rock for two hour rating..
12/07/2020 EXT METAL CLIPS/EXT SHEATHING TGAUSP Approved Partial, North end Stairwell shear wall on ground level, ok to start Sheetrock for fire assembly.
12/10/2020 PLUMBING - YARD WTR LINE/TEST DMUNIZ Approved
12/11/2020 REINFORCED MASONRY PRE-GROUT RBOOHER Approved Approved, Elevator shaft complete.
12/15/2020 SITE - SEWER DMUNIZ Approved Partial, Private sewer lines tested and in compliance.
12/21/2020 BUILDING - PROGRESS DMUNIZ Approved Partial, South Corridor 2nd floor framing ok to start Fire barrier installation.
12/21/2020 ROOF NAILING DMUNIZ Approved Partial, Deck nailing for 3rd floor South End ok to proceed with frame.
12/23/2020 MECHANICAL - FINAL DMUNIZ Approved Partial, Four Exterior footings for Canopy Columns West Entrance. Isolated Laundry pad with Gutter trench all ok for concrete placement.
12/23/2020 FIREWALL/FIREBARRIER/FIRESTOP DMUNIZ Approved Partial, South Corridor 2nd Floor. Fire barrier for upper walls ok to Proceed on ceiling.
12/30/2020 PLUMBING - GAS PRESSURE TEST DMUNIZ Approved Partial, Gas line installed and tested from Service entrance to Mechanical room and halfway through Ground level corridor to Room 105.
01/08/2021 PLUMBING - SEWER HCS CONNECT ESTEVENS Approved
04/09/2021 ELECTRIC - OUTDOOR LIGHTING DMUNIZ Approved Approved, light piers installed and ok for concrete placement.
04/23/2021 GAS CLEARANCE DMUNIZ Approved CODE
05/10/2021 PLUMBING - ROOF DRAINS DMUNIZ Approved
05/10/2021 U VALUE FOR WINDOW DMUNIZ Approved
05/10/2021 STUCCO MESH DMUNIZ Approved
05/27/2021 MECHANICAL - INTERMEDIATE DMUNIZ Approved
05/27/2021 PLUMBING - INTERMEDIATE DMUNIZ Approved
05/27/2021 PLUMBING - ABOVE CEILING DMUNIZ Approved
05/27/2021 ELECTRIC - ABOVE CEILING DMUNIZ Approved
06/01/2021 ELECTRIC - PROGRESS DMUNIZ Approved Inspection of 1600AMP CT, MDP, DP1, DP2 OK to clear TEP ECO
06/01/2021 TEP CLEARANCE - PM DMUNIZ Approved CODE ECO/1600 AMP, CT, MDP, DP1, DP2
08/11/2021 FRAMING DMUNIZ Approved Approved
08/11/2021 ELECTRIC - INTERMEDIATE DMUNIZ Approved Approved
08/11/2021 ELECTRIC - TEMPORARY SERVICE DMUNIZ Approved - Not Applicable
08/11/2021 ELECTRIC - CONSTRUCTION POWER DMUNIZ Approved - Not Applicable
09/07/2021 FIRE - FINAL CBASALDUA Approved
09/07/2021 FIRE - ALARM FINAL CBASALDUA Approved
09/07/2021 FIRE SPKLR - FINAL CBASALDUA Approved
09/09/2021 ENGINEERING - FINAL MHERENANDEZ Approved OK FOR TCO
09/09/2021 BUILDING - FINAL DMUNIZ Approved Approved

All conditions have been met & ok to apply for CofO.
09/09/2021 BUILDING ABOVE CEILING DMUNIZ Approved 1080
09/09/2021 OUTDOOR LIGHTING FINAL DMUNIZ Approved 2090
09/09/2021 ELECTRIC - FINAL DMUNIZ Approved Approved

All conditions have been met & ok to apply for CofO.
09/09/2021 PLUMBING - FINAL DMUNIZ Approved Approved

All conditions have been met & ok to apply for CofO.
09/09/2021 CERTIFICATE OF OCCUPANCY DMUNIZ Approved Approved

All conditions have been met & ok to apply for CofO.