Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 11/17/2020 |
PLUMBING - ROUGH, SOIL |
|
Approved |
Approved, completion of Under slab plumbing from GL1-6 ok to backfill. |
| 11/13/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Partial, Lint interceptor installed and tested ok to backfill. |
| 11/12/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Partial, Plumbing under slab from GL 4-9 ok to backfill. |
| 11/10/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Partial, Rough soil for Bathroom East of Elevator shaft under test & ok to backfill. |
| 11/06/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Partial, Underground Waste lines from GL9-12 ok to backfill progress. |
| 10/30/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
South 1/3 of building’s rough pvc ok to backfill. |
| 10/29/2020 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |