Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Date Description Inspector Results Comments
11/17/2020 PLUMBING - ROUGH, SOIL Approved Approved, completion of Under slab plumbing from GL1-6 ok to backfill.
11/13/2020 PLUMBING - ROUGH, SOIL Partial Approval Partial, Lint interceptor installed and tested ok to backfill.
11/12/2020 PLUMBING - ROUGH, SOIL Partial Approval Partial, Plumbing under slab from GL 4-9 ok to backfill.
11/10/2020 PLUMBING - ROUGH, SOIL Partial Approval Partial, Rough soil for Bathroom East of Elevator shaft under test & ok to backfill.
11/06/2020 PLUMBING - ROUGH, SOIL Partial Approval Partial, Underground Waste lines from GL9-12 ok to backfill progress.
10/30/2020 PLUMBING - ROUGH, SOIL Partial Approval South 1/3 of building’s rough pvc ok to backfill.
10/29/2020 PLUMBING - ROUGH, SOIL Not ready for Inspection Not ready. Contractor cancelled.