Inspection Status: Approved

Inspection History: PLUMBING - GAS PRESSURE TEST

Date Description Inspector Results Comments
04/23/2021 PLUMBING - GAS PRESSURE TEST Approved
04/20/2021 PLUMBING - GAS PRESSURE TEST Not ready for Inspection
04/15/2021 PLUMBING - GAS PRESSURE TEST Not ready for Inspection NOT READY CANCELLED BY CONTRACTOR
04/14/2021 PLUMBING - GAS PRESSURE TEST Not ready for Inspection
12/30/2020 PLUMBING - GAS PRESSURE TEST Partial Approval Partial, Gas line installed and tested from Service entrance to Mechanical room and halfway through Ground level corridor to Room 105.