Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
Permit Number - T20CM02530
Inspection Description - ELECTRIC - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/11/2021 | ELECTRIC - INTERMEDIATE | Approved | Approved | |
06/30/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, 1st and 2nd floor sub panels in guest suites inspected and ok to energize. | |
06/16/2021 | ELECTRIC - INTERMEDIATE | Correction Required | Corrections required, 2nd floor sub panel inspection. Multiple main breakers have loose connections, missing knockouts on dead fronts require blank spacers. | |
06/10/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, electrical room 1st floor ok to start fire assembly. | |
06/03/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, 3red floor guest room panels inspected and ok to install dead fronts. | |
06/01/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, inspection of Electrical panels ok for clearance. | |
05/27/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, 4th floor room panels inspected (419-435). | |
05/18/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Level #1; Lobby area, amenities area, laundry area. Level #4; Room Units 402-414 Room panels. | |
05/12/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, 1st floor rough Electrical in guest rooms complete. | |
05/11/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, no inspection today see previous notes. | |
05/10/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, no inspection today see previous notes. | |
04/30/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, 1st floor electrical inspection Of guest rooms North of lobby. | |
04/28/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, Electrical for East side canopy installed. Fire putty for Electrical boxes in stairwell fire assembly installed. | |
04/23/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, mechanical room inspected and ok to start Sheetrock. Note: Stairwell Electrical boxes to be Fire rated in ceiling. | |
04/20/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, staple and fire caulk Romex where needed in mechanical room. | |
04/15/2021 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | NOT READY CANCELLED BY CONTRACTOR | |
04/14/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | PARTIAL APPROVAL FOR 2ND FLOOR ROOM INTERIORS EXCLUDING SUB PANELS | |
04/07/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, 3rd and 4th floor stair wells electrical ok. | |
03/25/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, Electrical progress for 3rd floor ok to proceed. | |
03/24/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, inspection rescheduled see previous notes. | |
03/15/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, 4th Floor North Guest rooms ok to Sheetrock. | |
03/10/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial, 4th floor electrical progress. | |
01/28/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Level,#1 Mechanical Room; East and South Electric in walls. Ok to cover. |