Inspection Status: Approved
Inspection History: BUILDING ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 09/09/2021 |
BUILDING ABOVE CEILING |
|
Approved |
1080 |
| 08/04/2021 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Level#1 corridor. Ok to set ceiling tiles. |
| 08/03/2021 |
BUILDING ABOVE CEILING |
|
Cancelled |
IVRS - AP canceled |
| 06/29/2021 |
BUILDING ABOVE CEILING |
|
Cancelled |
IVRS - AP canceled |
| 06/16/2021 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial, 3rd floor above ceiling ok to drop ceiling tiles. |
| 06/14/2021 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial, 4th floor above ceiling inspection approved ok to install ceiling tiles. 3rd floor corrections required install KO seals and cover plates at Electrical boxes, fire stop all penetrations. |
| 05/27/2021 |
BUILDING ABOVE CEILING |
|
Approved |
|
| 03/24/2021 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial, inspection rescheduled see previous notes. |
| 03/15/2021 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial, ok to Sheetrock ceiling on 4th floor North Guest rooms. |