Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 05/27/2021 |
PLUMBING - INTERMEDIATE |
|
Approved |
|
| 05/18/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial. Level #1; Lobby area, amenities area, laundry area. |
| 05/12/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, 1st floor rough Plumbing in guest rooms complete. |
| 05/11/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, no inspection today see previous notes. |
| 05/10/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, no inspection today see previous notes. |
| 04/30/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, 1st floor plumbing inspection Of guest rooms North of lobby. |
| 04/23/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, mechanical room inspected and ok to start Sheetrock. |
| 04/20/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, MAIN branch lines installed and under test mechanical room. Roof drain for back canopy installed and tested. |
| 04/15/2021 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
NOT READY CANCELLED BY CONTRACTOR |
| 04/14/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
PARTIAL APPROVAL FOR 2ND FLOOR INTERIORS |
| 04/07/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, 3rd floor tubs and traps tested. |
| 03/31/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, 4th floor tubs and traps installed and tested. |
| 03/25/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, Plumbing progress for 3rd floor ok to Sheetrock except shower and tub locations, further inspection required. |
| 03/22/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, inspection rescheduled. See previous notes for progress. |
| 03/16/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, 4th floor Guest rooms ok to Sheetrock. |
| 03/09/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, Drain, Waste, and Vent system under test for North 2/3 of Building. |
| 03/08/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, no inspection today see previous notes. |
| 03/05/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
PARTIAL NO INSPECTION TODAY, SEE PREVIOUS NOTES |
| 03/04/2021 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Partial, Drain, Waste, & Vents For south side 1/3 of building all 4 floors under test and approved. |