Permit: T01CM03462
Permit Details
Apply Date:
07/13/2001
Applicant:
TUCSON UNIFIED SCHOOL DISTRICT
Description:
ELEMENTARY SCHOOL:TD#15-16-62
Contractors:
- LAMBERT LTD , RICHARD E
- TUCSON UNIFIED SCHOOL DIST #1
Permit Reviews
Permit Number - T01CM03462
Permit Status: C of o
Permit Description: ELEMENTARY SCHOOL:TD#15-16-62
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/13/2003 | REVISION | 01/13/2003 | COMPLETED |
07/13/2001 | COMMERCIAL-BLDG/FIRE ONLY | 07/31/2001 | COMPLETED |
11/29/2002 | REVISION | 12/10/2002 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T01CM03462
Permit Status: C of o
Permit Description: ELEMENTARY SCHOOL:TD#15-16-62
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/13/2001 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T01CM03462
Permit Description: ELEMENTARY SCHOOL:TD#15-16-62
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/07/2001 | ELECTRIC - CABLE DROP | JORTA | Approved | IVRS - Inspection 0000* |
09/05/2001 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | 1.) THE NO HUB UNDERGROUND IS NOW COMPLETE 2.) ALL AREAS HIGHLIGHTED. 3.) ALL AREAS OK TO COVER. |
09/28/2001 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection 0000* |
10/05/2001 | ELECTRIC - UFER | JORTA | Approved | IVRS - Inspection 0000*FROM REBAR UFER SYSTEM TO WATER TO GAS TO SES ATTACHMENT 3 AND STUB OUT APPROVED. |
11/28/2001 | ELECTRIC - UNDERGROUND | JORTA | Approved | IVRS - Inspection 0000*APPROVED ELECTRIC ROOM UNDER GROUND APPROVED. MECH. ROOM MCC UNDERGROUND APPROVED |
12/07/2001 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection 0000*F-4 FOOTERS OK PROVIDING FINISHED STEM GRADE IS LOWERED TO ACCOUNT FOR PLACEMENT OF #3 TIES. |
12/19/2001 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection 0000*PARTIAL WEST ROOM 1.) DIAPHRAGM BLOCKING IN OTHER AREAS MUST BE CORRECTED 2.) DO NAILS NEED TO BE BENT OVER ON STRAPPING. |
12/19/2001 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection 0000* |
12/27/2001 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | IVRS - Inspection 0000*PARTIAL 4'-12' SOUTH CLASSROOMS. |
12/27/2001 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection 0000*181,182,184 |
03/26/2002 | STUCCO MESH | LHANLY | Approved | IVRS - Inspection 0000* |
06/18/2002 | MECHANICAL - TEMP PWR FOR TEST | RSUBA | Approved | |
06/25/2002 | ELECTRIC - TEMP POWER FOR TEST | JORTA | Approved | IVRS - Inspection 0000*RECEIVED TORQUE LETTER AND BEFORE C OF O WILL NEED GFI PERFORMANCE TEST. ALL OTHER INSPECTION SIGNED OFF. ADJUSTMENT FOR MAX AMP SETTING OF MAIN BREAKER 1500AMPS TO BE VERIFIED. |
07/29/2002 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection 0000* |
07/29/2002 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection 0000* |
08/15/2002 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection 0000* |
08/15/2002 | FRAMING | LHANLY | Approved | IVRS - Inspection 0000* |
09/13/2002 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | |
09/13/2002 | PLUMBING - ABOVE CEILING | RMYERS | Approved | |
10/01/2002 | PLUMBING - PROGRESS | RMYERS | Approved | 1.) PLUMBING PROGRESS OK 2.) CONTRACTOR POSTED BOND FOR TEMP POWER/ENERGY/FUEL GAS CARD LEFT AT METER SET. |
10/15/2002 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000* |
11/14/2002 | FIRE - FINAL | LTHOMAS | Approved | |
11/14/2002 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
11/24/2002 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection 0000*1.) NOT READY FOR INSPECTION 2.) CALL IN ALL REQUIRED INSPECTION BEFORE CALLING IN FINAL STILL NEED |
11/25/2002 | ELECTRIC - FINAL | JORTA | Approved | IVRS - Inspection 0999*IRREGATION CONTROLLER NOT READY ON SEWAGE SUMP SYSTEM: NEED A COMPLETE APPROVED (CITY) PLAN I.D. PUMP 1 & 2 CONTROLLER, NEED DISCONNECT FOR COMPRESSOR, BOTH PUMPS FROM PANEL AA? NEED GROUND BUSH. & BOND JUMPER FOR ALL RACEWAYS. |
11/26/2002 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0999*1.) ACCESS STILL PROBLEM FAN COILS #46/45, RM. #116 EXHAUST BLOWER EF23, 2.) A. GREASE COLLECTION CUP ON BLOWER & HOOD. B.) EXHAUST BLWS ON ROOF. COVER FLEX DUCT COM. W/RAIN SHIELD 3.) ELIMINATE MOVEMENT ON COOKING LINE FLEX GAS CONNECTORS OR USE PROPER APPROVED FLEX GAS LINES. 4.) CHILLER PERM. LABELS/NUMBER INK IS ALREADY FADDING |
12/18/2002 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection 0999*1.) NO APPROVAL SITE UTILITY PLAN ON SITE 2.) YARDWATER COVERED BEFORE INSPECTION. 3.) SEWER COVERED BEFORE INSPECTION. |
12/27/2002 | PLUMBING - YARD WTR LINE/TEST | SLONG | Approved | YARD WATER LINE COVERED W/O INSP. SITE VISIT ON 12-26-02 TO DETERMINE IF POTHOLING WOULD BE ADEQUATE FOR INSPECTION. IT WAS DETERMINED THAT THE ENTIRE LINE SHOULD BE EXPOSED IN ORDER TO BE CERTAIN THAT NO NON-POTABLE LINES IRRIGATION ARE CONNECTED TO THE POTABLE WATER. |
01/30/2003 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
09/15/2005 | ENGINEERING - FINAL | DROBERTS | Approved | THIS SITE WAS CHECKED AND FOUND TO BE SUBSTANTIALLY COMPLETE, WITH MINOR DRAINAGE ISSUES TO BE RESOLVED UNDER THE NEW CONTRACT. THE SCHOOL WILL BE INSTALLING ADDITIONAL SIDEWALK SCUPPERS AS NEEDED DURING THE CONSTRUCTION PHASE OF THE NEW CLASSROOMS. ALSO IT WAS NOTED THAT THE ON-SITE DETENTION/RETENTION BASINS ARE NOT OPERATING PER OUR DEVELOPMENT STANDARDS AND STORMWATER RET./DET. MANUAL IN REGARDS TO THE PERCOLATION RATES. THE NEW CONTRACTOR WILL WORK ON REMOVING THE SEDIMENT FROM THE BASINS TO HELP RE-ESTABLISH THE PERCOLATION RATES. THE SCHOOL WILL INVESTIGATE THE INSTALLATION OF A LOW FLOW PIPE TO ALLOW FOR CONTINOUS DISCHARGE OF THE WATERS OVER TIME. |
09/15/2005 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | CLEARED FOR C OF O BY PHONE 9:58AM |
10/31/2006 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | |
10/31/2006 | BUILDING - FINAL | LHANLY | Approved | ALL TRADES DONE. SPECIAL INSPECTION FORMS SHOULD ALREADY BE TURNED IN. |
11/01/2006 | PERMIT FINALED | GBONILLA | Approved | |
11/01/2006 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | |
11/01/2006 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | |
11/01/2006 | MECHANICAL - HOODS | CWILLIAM | Approved |