Revision 3 - Site/Grading/Swppp - Drexel Commerce Center. New industrial park. Shell buildings and associated sit
Permit Reviews
Permit Number - DP21-0316
Permit Status: Issued
Permit Description: Revision 3 - Site/Grading/Swppp - Drexel Commerce Center. New industrial park. Shell buildings and associated sit
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/18/2022 | DEV PKG - RESUBMITTAL | 04/05/2022 | COMPLETED |
| 04/28/2022 | DEV PKG - RESUBMITTAL | 05/25/2022 | COMPLETED |
| 11/24/2021 | DEV PKG - OK TO SUBMIT | 12/02/2021 | COMPLETED |
| 12/02/2021 | DEV PKG | 01/26/2022 | COMPLETED |
| 12/24/2024 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 01/17/2025 | REQUIRES RESUBMIT |
| 02/03/2025 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 02/05/2025 | APPROVED |
| 03/24/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 05/06/2025 | APPROVED |
| 11/06/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/06/2025 | APPROVED |
| 06/06/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 07/16/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - DP21-0316
Permit Status: Issued
Permit Description: Revision 3 - Site/Grading/Swppp - Drexel Commerce Center. New industrial park. Shell buildings and associated sit
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP21-0316
Permite Description: Revision 3 - Site/Grading/Swppp - Drexel Commerce Center. New industrial park. Shell buildings and associated sit
Total Outstanding Inspections - 17
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Correction Notice | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Violation Notice | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Setup and Controls | N/A | Not Ready | |
| 12/05/2024 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | No address posted. |
| 12/19/2024 | NPPO Pre-Construction | N/A | Partial Pass | Nursery still needs to be checked when established. |
| 06/04/2025 | SITE | N/A | Canceled | |
| 09/11/2025 | N/A | Partial Pass | Sub-grade North of building 2 and between buildings 1 & 2 is sloped and compacted per plans with proper depths; ready for AB. | |
| 09/17/2025 | ENGR Grading Final | N/A | Partial Pass | Paving inspection for AB between buildings 1 & 2: elevations, depth, and compaction is good, okay to pave between buildings. |
| 06/23/2025 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | No Issues |
| 11/10/2025 | Consultation SITE | N/A | Partial Pass | I gave the contractor a partial pass on building. There’s some tree staking that needs to be replaced. There’s some railing that needs to be installed on the south end of building one. There is a doorway opening that needs a set of stairs and railing on the north end of the building. |
| 09/17/2025 | N/A | Partial Pass | east side of building one: sidewalk forms are accurate to plans, slopes are good. OK to pour. | |
| 11/26/2025 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Not Ready | Superintendent not on site and should reschedule. |
| 05/08/2025 | For trash and recycling enclosures | N/A | Re-inspection required | 05/08/25, Do not pour until rebar has been set to plan spec. 1-1/2" needed from outside of wall to face of #5 bar. This also includes the ramp walls. |
| 11/26/2025 | SITE - Stormwater Final Inspection | N/A | Re-inspection required | Contractor could not make the walk-through. So we’re going to reschedule for another time. |
| 12/11/2025 | LAND Landscape Appearance & Function Final | N/A | Not Ready | Islands inside of curbs are not per plan shown in detail 9 Landscape Grading/Rainwater Harvesting page L4.1. |
| 11/26/2025 | ENGR Paving | N/A | Not Ready | Contractor unable to meet onsite. Says they will reschedule. |
Completed Inspections
Permit Status: Issued
Permit Number: DP21-0316
Permit Description: Revision 3 - Site/Grading/Swppp - Drexel Commerce Center. New industrial park. Shell buildings and associated sit
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | Present at meeting was, Ron Sarrasin, Ernie Stevens and Gustavo Armenta. Before anymore inspections will be done address board needs to be posted and as soon as possible SWPPP board. | |
| 02/03/2025 | NPPO Pre-Construction | Passed | ||
| 05/21/2025 | Passed | 5/22/25 Two additional wall footings are okay to pour. 5 total Footings are now okay to pour. See checklist items for detail. |
||
| 09/02/2025 | ENGR Engineering Final | Passed | Passed, east building southwest corner, loading dock area and ramp. Also passed was the curbs on all dumpster's | |
| 09/16/2025 | ENGR Grading Final | Passed | AB placement, North and West sides of building 2: compaction is good, elevations are good; okay to pave from E Commerce Center Pl to NE corner of building 2. | |
| 09/19/2025 | Passed | Box Culvert (2x8) on Southside: Culvert is installed per plans, slope is accurate, joints are sealed, top is installed; okay to backfill. Compact per manufacturer specifications. | ||
| 09/24/2025 | SITE - Stormwater Follow-up | Passed | contractor need to clean the streets. | |
| 10/30/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Passed | Contractors good pour the foundations for the polls one on the southwest side and one on the south side in between the two buildings | |
| 11/13/2025 | ENGR - Drainage Structures | Passed | contractors good to pour the head wall located the south east corner of the west building. | |
| 11/13/2025 | Passed | Contractors good to pour the stairs at the north end of the west building | ||
| 11/20/2025 | COT - ENGR - Signage Final | Passed | ||
| 11/20/2025 | Passed | |||
| 11/26/2025 | NPPO Final | Passed | Native plants have been successfully transplanted per NPPO plan. | |
| 12/11/2025 | Passed |