Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP21-0316

Parcel: 140260390


Addresses:

2730 E DREXEL RD


Inspection Status: Re-inspection required

Inspection History: For trash and recycling enclosures

Permit Number - DP21-0316

Inspection Description - For trash and recycling enclosures

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
05/08/2025 For trash and recycling enclosures Re-inspection required 05/08/25, Do not pour until rebar has been set to plan spec. 1-1/2" needed from outside of wall to face of #5 bar. This also includes the ramp walls.
05/14/2025 For trash and recycling enclosures Partial Pass Okay to pour walls. inspection required when walls are stood.
05/30/2025 For trash and recycling enclosures Partial Pass 05/30/25, 2 trash enclosure's between the 2 buildings, south enclosure needs to have dirt removed in corners and I need pictures on the north one. Last warning, do not schedule inspections for the same day of a pour.
06/09/2025 For trash and recycling enclosures Partial Pass 06/06/25, bollards are set at 10'-6" and the wall will now be at 1'-6" spacing, pour as is.
06/11/2025 For trash and recycling enclosures Re-inspection required 06/11/25, DO NOT POIR THESE FOOTINGS. 3" clearance needed between ground and rebar. Footing rebar has a set amount of rebar needed exposed to each side of wall, snakes are not allowed.
06/13/2025 For trash and recycling enclosures Partial Pass Building 2: 4 trash enclosure footings are okay to pour. Remaining (all) ramp wall footings are okay to pour.
08/27/2025 For trash and recycling enclosures Partial Pass 08/17/25, refuse enclosure pads have passed compaction and rebar is within tolerance
09/04/2025 For trash and recycling enclosures Partial Pass 09/04/25, walls for last enclosure pass.
09/10/2025 For trash and recycling enclosures Partial Pass Footing for Northern most enclosure on Building 1 is correct and good to pour.
09/25/2025 For trash and recycling enclosures Partial Pass Contractors good to pour the floor for the trash enclosure. Per Josh Garcia’s instruction the rebar is laid out at 24 inch centers using number four bars.
11/26/2025 For trash and recycling enclosures Re-inspection required Contractor could not make the walk-through. So we’re going to reschedule for another time.