Inspection Status: Passed
Inspection History: For trash and recycling enclosures
| Date |
Description |
Inspector |
Results |
Comments |
| 01/12/2026 |
For trash and recycling enclosures |
|
Passed |
|
| 05/08/2025 |
For trash and recycling enclosures |
|
Re-inspection required |
05/08/25, Do not pour until rebar has been set to plan spec. 1-1/2" needed from outside of wall to face of #5 bar. This also includes the ramp walls. |
| 05/14/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Okay to pour walls. inspection required when walls are stood. |
| 05/30/2025 |
For trash and recycling enclosures |
|
Partial Pass |
05/30/25, 2 trash enclosure's between the 2 buildings, south enclosure needs to have dirt removed in corners and I need pictures on the north one. Last warning, do not schedule inspections for the same day of a pour. |
| 06/09/2025 |
For trash and recycling enclosures |
|
Partial Pass |
06/06/25, bollards are set at 10'-6" and the wall will now be at 1'-6" spacing, pour as is. |
| 06/11/2025 |
For trash and recycling enclosures |
|
Re-inspection required |
06/11/25, DO NOT POIR THESE FOOTINGS. 3" clearance needed between ground and rebar. Footing rebar has a set amount of rebar needed exposed to each side of wall, snakes are not allowed. |
| 06/13/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Building 2: 4 trash enclosure footings are okay to pour. Remaining (all) ramp wall footings are okay to pour. |
| 08/27/2025 |
For trash and recycling enclosures |
|
Partial Pass |
08/17/25, refuse enclosure pads have passed compaction and rebar is within tolerance |
| 09/04/2025 |
For trash and recycling enclosures |
|
Partial Pass |
09/04/25, walls for last enclosure pass. |
| 09/10/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Footing for Northern most enclosure on Building 1 is correct and good to pour. |
| 09/25/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Contractors good to pour the floor for the trash enclosure. Per Josh Garcia’s instruction the rebar is laid out at 24 inch centers using number four bars. |
| 11/26/2025 |
For trash and recycling enclosures |
|
Re-inspection required |
Contractor could not make the walk-through. So we’re going to reschedule for another time. |