Inspection Status: Passed
Inspection History
| Date |
Description |
Inspector |
Results |
Comments |
| 02/05/2025 |
|
|
Passed |
Grading rough, all roads are roughed and cut to grade, basins are in better than rough condition with grade cut and sloped , building pads have been created and cut to grade and compaction test completed. |
| 08/13/2025 |
|
|
Partial Pass |
08/13/25, Slope and grade match the required depth and slope on the 2 loading dock ares on building A west side. Continue with the AB installation at 6" and when compaction is being completed schedule with PDSD to be on site during compaction testing. |
| 09/10/2025 |
|
|
Partial Pass |
Parking area and drive line on the West side of building 2: sub-grade is good, okay for AB. North and center not ready. |
| 09/11/2025 |
|
|
Partial Pass |
Sub-grade North of building 2 and between buildings 1 & 2 is sloped and compacted per plans with proper depths; ready for AB. |