Permit: DP21-0316

Parcel: 140260390


Addresses:

2730 E DREXEL RD


Inspection Status: Partial Pass

Inspection History: ENGR - Drainage Structures

Permit Number - DP21-0316

Inspection Description - ENGR - Drainage Structures

Inspection Status - Partial Pass

Date Description Inspector Results Comments
07/01/2025 ENGR - Drainage Structures Partial Pass 07/01/25, 4 structures on the east side of the west building have all, been placed correctly
07/10/2025 ENGR - Drainage Structures Partial Pass Single precast catch basin at the south end of the site, in the middle, is placed according to plans and drain pipe connection and slope is good. Okay to backfill.
07/16/2025 ENGR - Drainage Structures Partial Pass 07/17/25, two manhole drainage structures on the west side of the property are good to backfill.
Manhole drainage structures using the PAG 301 on the north side between the buildings is good to pour.
Drainage pipe on the north side of building 1 is good or backfill.
Drainage pipe on the southeast side of the project going into the basin is good to backfill.
07/22/2025 ENGR - Drainage Structures Partial Pass 07/22/25, backfill two drainage structures on the east side of building 1 and the 1 on the north side between the two buildings. Also good to backfill the one in front of the office and the one at the south end of building 2.
07/29/2025 ENGR - Drainage Structures Partial Pass 07/29/25, Drainage pipe on the southeast side of the project going into the basin is good to backfill.
07/31/2025 ENGR - Drainage Structures Partial Pass 07/30/25, Drainage structure between blds 1 and 2 is good to pour.
08/07/2025 ENGR - Drainage Structures Partial Pass 08/07/25, Drainage structure on the southeast side of building 1 is good to pour.
09/05/2025 ENGR - Drainage Structures Partial Pass Partial pass on bedding for box culvert
11/03/2025 ENGR - Drainage Structures Partial Pass Contractor can pour the footer for the head wall on the east end of the building 180’ x 23’ wings using number five bars doubled 1 foot center
11/05/2025 ENGR - Drainage Structures Not Ready contractor still has to form up the walls for the retaining walls. They’re not ready yet in process. Also need to dial into the box culvert and lay out the number five bars on the box culvert.
11/06/2025 ENGR - Drainage Structures Partial Pass contractors forming up the head walls and wing walls on the east end of the project. I was there at 8 o’clock this morning to inspect the dowels on the box. Culvert was good. I had to come back at 12 to reinspect the head walls so they could pour at 1 PM. Contractor was not completed forming the walls until 1:30 PM. Concrete truck shows up at 12:30 PM. Did not start pouring the walls until 1:45 PM.
11/13/2025 ENGR - Drainage Structures Passed contractors good to pour the head wall located the south east corner of the west building.