Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: Consultation SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 02/05/2025 |
Consultation SITE |
|
Passed |
Consultation with Rash construction on sewer and drainage requirements. They will be calling building on their needs for inspections needed. |
| 04/10/2025 |
Consultation SITE |
|
Passed |
Question was on Commerce Avenue and who is doing the inspections. We went over the PAG standards being used. |
| 06/18/2025 |
Consultation SITE |
|
Partial Pass |
This was to look at his laptop and the inspection portal but have found out they just submitted a review. |
| 10/23/2025 |
Consultation SITE |
|
Partial Pass |
Contractor called in for consultation at the manhole number 11. Contractor wants to add two more rings and two more ladder steps to access the bottom of the box covert. |
| 11/10/2025 |
Consultation SITE |
|
Partial Pass |
I gave the contractor a partial pass on building. There’s some tree staking that needs to be replaced. There’s some railing that needs to be installed on the south end of building one. There is a doorway opening that needs a set of stairs and railing on the north end of the building. |