Inspection History Details
Inspection Status: Partial Pass
Inspection History
Permit Number - DP21-0316
Inspection Description -
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/01/2025 | Partial Pass | 07/01/25, drainage pipes on the east side of the west building have passed inspection for backfill to be started. | ||
| 07/10/2025 | Partial Pass | 42" drain pipe on the east side of the west building, from previous fill to south end of building, is installed correctly and is okay to backfill. Manholes are not in place for the intersections yet. | ||
| 07/15/2025 | Passed | All pipe inspected on 07/14/25, backfill can be completed up to structures which need to be seen grouted. | ||
| 07/22/2025 | Partial Pass | Backfill all drainage pipe looked at on the 22 of July | ||
| 08/07/2025 | Partial Pass | 08/07/25, Compaction is meeting and exceeding the geo report on drive lines and parking at 97s +, called for according to the geo is 95% | ||
| 08/13/2025 | Not Ready | 08/13/25, HTPE Pipe being used as an equalizer between the 2 north basins needs to be level. Found was a pitch coming from east to middle and then a pitch coming from west to middle creating a belly in the middle of the run. Also on the southeast basin, please have the engineer on record ensure the 12" pipe installed to drain the basin will be large enough to handle the 4 pipes coming into the basin. This inspection will be listed as not ready until the time we have the information from the engineer. |
||
| 08/18/2025 | Partial Pass | Storm drain on the south end middle basin has been cleared by the engineer to be a large enough pipe for drainage. Equalizer pipe on the north end still not right. |
||
| 09/19/2025 | Passed | Box Culvert (2x8) on Southside: Culvert is installed per plans, slope is accurate, joints are sealed, top is installed; okay to backfill. Compact per manufacturer specifications. |