Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 08/18/2025 |
ENGR Grading Final |
|
Passed |
Grading is for the east building and the 2 flat dock areas, both have met compaction and grade hubs are in. |
| 08/20/2025 |
ENGR Grading Final |
|
Partial Pass |
Grading compaction testing passed on the 3 north areas on building 2. The 2 south areas need to be re-compacted and tested. |
| 08/27/2025 |
ENGR Grading Final |
|
Partial Pass |
The last 2 dock loading areas on building 2 have passed compaction. |
| 09/16/2025 |
ENGR Grading Final |
|
Passed |
AB placement, North and West sides of building 2: compaction is good, elevations are good; okay to pave from E Commerce Center Pl to NE corner of building 2. |
| 09/17/2025 |
ENGR Grading Final |
|
Partial Pass |
Paving inspection for AB between buildings 1 & 2: elevations, depth, and compaction is good, okay to pave between buildings. |