Permit: TD-DEV-0323-00162
Permit Details
Status:
Inspections
Type:
Development Package
Address:
1501 E METRIC PL
Address NEW:
1501 E METRIC PL
Apply Date:
03/06/2023
Applicant:
Alan Lessenden
Description:
Development plans for new Citizens storage warehouse with associated site improvements including grading and drainage, on-site site paving, and private utilities.
Permit Reviews
Permit Number - TD-DEV-0323-00162
Permit Status: Inspections
Permit Description: Development plans for new Citizens storage warehouse with associated site improvements including grading and drainage, on-site site paving, and private utilities.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/20/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 07/18/2023 | REQUIRES RESUBMIT |
| 07/20/2023 | DEVELOPMENT PACKAGE NEW v.1 | 10/17/2023 | APPROVED |
| 03/07/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 04/18/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0323-00162
Permite Description: Development plans for new Citizens storage warehouse with associated site improvements including grading and drainage, on-site site paving, and private utilities.
Total Outstanding Inspections - 13
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2024 | NPPO Pre-Construction | N/A | Canceled | |
| 02/07/2025 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | All wattle needs to be properly staked. All trash needs to be cleaned up. Port A Jon’s need to be properly staked down. Dumpster should be in a location so that if anything leaks out it does not impact the integrity of the basin. Basin is being impacted by construction and should be maintained to hold what is the required amount of water. |
| 06/10/2025 | N/A | Not Ready | Site is shut down, no access. | |
| 02/09/2026 | For trash and recycling enclosures | N/A | Partial Pass | Contractor is, good to pour the floor for the trash enclosure |
| 03/26/2026 | ENGR - Drainage Structures | N/A | Partial Pass | contractor dowels into the existing head wall at 1 foot centers looks good. They’re gonna continue to form that up and pour on Monday. |
| 12/17/2025 | N/A | Partial Pass | Contractor and I had a conversation about the drainage pipe on the west side of the project. I am formed him and that is OK. Connect the two pipes and use a dot color on them. | |
| 12/23/2025 | N/A | Partial Pass | East retaining wall is okay to pour. | |
| 06/23/2026 | N/A | Partial Pass | need to backfill all the irrigation trenches around the building | |
| 06/23/2026 | N/A | Partial Pass | contractor continues to plant all the plants around the back of the building. | |
| 08/24/2026 | Consultation SITE | N/A | Partial Pass | Talked to contractor on phone and saw on DP that he needs a utility permit for inspections on water sewer electric etc. I cannot inspect the water lines or utilities. Contractor will apply for Utilities permit needed. |
| 09/11/2026 | Grading Progress ENGR | N/A | Partial Pass | Call in a Paving inspection |
| 09/18/2026 | ENGR Paving | N/A | Partial Pass | Most AB complete. Recall day prior to paving |
| 09/16/2026 | N/A | Partial Pass | Okay to pour sidewalk south of building. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0323-00162
Permit Description: Development plans for new Citizens storage warehouse with associated site improvements including grading and drainage, on-site site paving, and private utilities.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/10/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | Pre Construction meeting should be failed as it was again called in quite some time after construction was started. | |
| 01/13/2025 | SITE - Stormwater Setup and Controls | Passed | SWPPP board is in place. please stay on top of your by-weekly inspection’s and all other inspections, if help is needed call me please. | |
| 09/11/2026 | Passed |