Inspection Status: Partial Pass
Inspection History: Consultation SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 02/10/2026 |
Consultation SITE |
|
Partial Pass |
contractor is good to pour the channel on the north end of the project with GUNITE |
| 02/23/2026 |
Consultation SITE |
|
Partial Pass |
Contractors good to pour the truck ramp going into the building on the east side |
| 03/19/2026 |
Consultation SITE |
|
Partial Pass |
contractor is dialing the existing head wall to place new CMP pipe and wall southwest side |
| 03/31/2026 |
Consultation SITE |
|
Partial Pass |
contractor install 12 inch HDPE pipe at the north west corner of the building 47 lineal feet. Good to backfield. |
| 05/20/2026 |
Consultation SITE |
|
Partial Pass |
i’m in Fort Patrick did he can go ahead and start forming up for the curb islands here and the small pad on the southwest corner of the building |
| 06/08/2026 |
Consultation SITE |
|
Partial Pass |
The curb around the front of the building is good to pour |
| 08/24/2026 |
Consultation SITE |
|
Partial Pass |
Talked to contractor on phone and saw on DP that he needs a utility permit for inspections on water sewer electric etc. I cannot inspect the water lines or utilities. Contractor will apply for Utilities permit needed. |