Permit: TD-DEV-0323-00162

Parcel: 132130260


Addresses:

1501 E METRIC PL

Inspection Status: Partial Pass

Inspection History: Consultation SITE

Date Description Inspector Results Comments
02/10/2026 Consultation SITE Partial Pass contractor is good to pour the channel on the north end of the project with GUNITE
02/23/2026 Consultation SITE Partial Pass Contractors good to pour the truck ramp going into the building on the east side
03/19/2026 Consultation SITE Partial Pass contractor is dialing the existing head wall to place new CMP pipe and wall southwest side
03/31/2026 Consultation SITE Partial Pass contractor install 12 inch HDPE pipe at the north west corner of the building 47 lineal feet. Good to backfield.
05/20/2026 Consultation SITE Partial Pass i’m in Fort Patrick did he can go ahead and start forming up for the curb islands here and the small pad on the southwest corner of the building
06/08/2026 Consultation SITE Partial Pass The curb around the front of the building is good to pour
08/24/2026 Consultation SITE Partial Pass Talked to contractor on phone and saw on DP that he needs a utility permit for inspections on water sewer electric etc. I cannot inspect the water lines or utilities. Contractor will apply for Utilities permit needed.
09/23/2026 Consultation SITE Passed This is a paving inspection. AB is compact and reveals look good at curbs for both heavy duty and light duty paving.Some areas need to be cleaned up with plate tamper prior to paving (around drain grate) Drainage is correct to plan. Submit compaction tests of AB and subgrade to the permit. Okay to Place Asphalt.