Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/06/2026 | Partial Pass | Okay to pour west retaining wall. | ||
| 03/16/2026 | Partial Pass | contractor is good to pour the head wall footer on the north west side Contractors put in dowels in the existing head walls on the southwest side to tie into the new storm drain basin |
||
| 03/30/2026 | Not Ready | Called and left a message at 7:00 for Patrik, phone number: (520) 307-4035. per inspection note to notify that today is a City Holiday and since the system allowed the request, that would inspect as a courtesy. I received a call back stating that this was a wrong number. Request re-inspection for 03-31-26 | ||
| 04/13/2026 | Partial Pass | contract report retaining wall for the outlets of the channel and for the existing storm drain pipe on the west side | ||
| 12/17/2025 | Partial Pass | Contract is good for the footing wall on the west side of the project | ||
| 12/19/2025 | Partial Pass | Okay to pour footing #2. | ||
| 12/23/2025 | Partial Pass | East retaining wall is okay to pour. |