Permit: TD-DEV-0224-00058
Permit Details
Apply Date:
02/20/2024
Applicant:
David Openshaw
Description:
Revision 3 - South Fence - started 01.08.2026 ** Revision 2 - Fence Started 10.30.2025 ** Revision 1 - Chick-fil-A restaurant with 2 lane drive thru, 2 drive thru canopies, and trash enclosure
Permit Reviews
Permit Number - TD-DEV-0224-00058
Permit Status: In revision
Permit Description: Revision 3 - South Fence - started 01.08.2026 ** Revision 2 - Fence Started 10.30.2025 ** Revision 1 - Chick-fil-A restaurant with 2 lane drive thru, 2 drive thru canopies, and trash enclosure
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/11/2024 | DEVELOPMENT PACKAGE NEW v.4 | 08/09/2024 | REQUIRES RESUBMIT |
| 04/30/2024 | DEVELOPMENT PACKAGE NEW v.3 | 05/31/2024 | REQUIRES RESUBMIT |
| 02/28/2024 | DEVELOPMENT PACKAGE NEW v.2 | 04/12/2024 | REQUIRES RESUBMIT |
| 01/09/2026 | DEVELOPMENT PACKAGE NEW REVISION v.1 | N/A | IN REVIEW |
| 08/15/2024 | DEVELOPMENT PACKAGE NEW v.5 | 02/24/2025 | APPROVED |
| 11/14/2025 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 12/09/2025 | APPROVED |
| 02/23/2024 | DEVELOPMENT PACKAGE NEW v.1 | 02/28/2024 | REQUIRES RESUBMIT |
| 10/30/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 10/30/2025 | REQUIRES RESUBMIT |
| 02/21/2025 | DEVELOPMENT PACKAGE NEW v.1 | 03/13/2025 | REQUIRES RESUBMIT |
| 03/13/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 04/14/2025 | APPROVED |
Outstanding Inspections
Permit Status: In Revision
Permit Number: TD-DEV-0224-00058
Permite Description: Revision 3 - South Fence - started 01.08.2026 ** Revision 2 - Fence Started 10.30.2025 ** Revision 1 - Chick-fil-A restaurant with 2 lane drive thru, 2 drive thru canopies, and trash enclosure
Total Outstanding Inspections - 12
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2025 | SITE - SWPPP Correction Notice | N/A | Complete (Recurring) | Dirt and mud was observed in the street and adjacent parking lot yesterday, 7/9/25. Verbal notification was given to address track out issues. Metal grates were installed as of yesterday. Street has been cleaned up. Advised that area around fire hydrant in medical building parking lot needs to be cleaned up as well. |
| 10/15/2025 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | There’s no concerns at this time everything still in place |
| 12/01/2025 | ENGR Paving | N/A | Failed | contractor and I streamline the grade for the paving using the existing hubs. There’s areas that are high in some low contractor needs to address those areas. |
| 01/09/2026 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Not Ready | Bio Retention areas need to be depressed per landscape drawings. Also Landscape areas along MLK are at grade with Hardscape and need to be lowered.. This was discussed with contractor and he will be addressing these areas. |
| 01/09/2026 | N/A | Not Ready | Scuppers on SE side of parking lot are not complete. Scupper walls were not poured with the floor so rebar needs to be epoxy into the floor to make a solid connection. Sidewalk ramp at driveway on northside is not poured. Scupper at East side of building is going to be modified from a type one because there isn’t enough vertical separation for specified pipe to fit. engineer/contractor is proposing using a modified type two configuration 8 inches W by 3 inches H. Curb ramp at south east corner of building at drive-through is also not poured. At South side of West parking lot there’s a sidewalk between the parking lot and the drive-through area. There is a vertical curb from the sidewalk into the parking area. That is a tripping hazard the engineer OK RFI for the sidewalk. | |
| 01/09/2026 | SITE - Zoning Final | N/A | Not Ready | |
| 01/09/2026 | N/A | Not Ready | ||
| 08/21/2025 | For trash and recycling enclosures | N/A | Partial Pass | Contractor can grout the last 2 feet of the wall for the trash enclosure. This trash enclosure walls are 8 foot tall tall. |
| 12/29/2025 | ENGR Engineering Final | N/A | Not Ready | contractor needs to finish all his landscaping, rip rap striping handicap, parking signs and remove all construction material. That’s on site. |
| 01/09/2026 | LAND Landscape Appearance & Function Final | N/A | Not Ready | |
| 09/25/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | N/A | Partial Pass | Footing for both menu boards: rebar cage is good, anchor bolts are good, electrical conduit is good. Okay to pour footers. All 13 light pole bases have ground rods installed. |
| 01/09/2026 | N/A | Not Ready | Mostly complete. Not finished yet |
Completed Inspections
Permit Status: In Revision
Permit Number: TD-DEV-0224-00058
Permit Description: Revision 3 - South Fence - started 01.08.2026 ** Revision 2 - Fence Started 10.30.2025 ** Revision 1 - Chick-fil-A restaurant with 2 lane drive thru, 2 drive thru canopies, and trash enclosure
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/01/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Construction has started. Went over inspections and trash enclosure specs. This trash enclosure is different than our specs in several ways. 8' walls with a roofed storage area behind it. SWPPP board not installed, track pad has the wrong material. Heavy track out noticed on the TMC One parking lot needs to be cleaned up. Gates were swung in a direction that impacted traffic to the TMC site. |
|
| 09/02/2025 | Consultation SITE | Passed | Light pole footing inspection: All 13 footings are of proper diameter and depth, rebar cage is accurate to plans. Okay to pour 13 light pole footings. | |
| 12/02/2025 | ENGR Grading Final | Passed | contractors good to pave tomorrow.. |