Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Paving
Permit Number - TD-DEV-0224-00058
Inspection Description - ENGR Paving
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/09/2026 | ENGR Paving | Not Ready | 2 Scuppers South West part of parking lot going under sidewalk are not at grade with asphalt and pavement needs to be raised to invert. There are two puddling areas one at the north west corner at driveway area of parking lot and one in the middle of the west parking lot these will be addressed. Also in second to the east driveway to MLK there is puddling and this will also be addressed. | |
| 01/15/2026 | ENGR Paving | Not Ready | Not all areas of paving are repair yet. Asphalt paving adjacent to PCCP handicap parking is raised above PCCP it cannot be more than a quarter inch raise over PCCCP. | |
| 01/21/2026 | ENGR Paving | Not Ready | 1/21/26 Contractor wants to sand seal the asphalt patches. If this is done correctly it will be sufficient to repair the asphalt paving. |
|
| 01/30/2026 | ENGR Paving | Re-inspection required | Sand Seal on asphalt patch in front of East scupper on South side of parking lot is cracked and not sealing asphalt patch. Repair this area. | |
| ENGR Paving | Scheduled | |||
| 10/15/2025 | ENGR Paving | Partial Pass | Contractor needs to install hubs so we can get the proper grade for paving | |
| 12/01/2025 | ENGR Paving | Failed | contractor and I streamline the grade for the paving using the existing hubs. There’s areas that are high in some low contractor needs to address those areas. |