Permit: TD-DEV-0224-00058

Parcel: 13213120G


Addresses:

3520 S KINO PW

Inspection Status: Partial Pass

Inspection History: SITE - Sign Footer/Setback/Excavation Layout/Rebar

Date Description Inspector Results Comments
09/19/2025 SITE - Sign Footer/Setback/Excavation Layout/Rebar Partial Pass Clearance bars' (2X) footers are set up correctly. Need to be free of standing water, then okay to pour.
09/25/2025 SITE - Sign Footer/Setback/Excavation Layout/Rebar Passed Footing for both menu boards: rebar cage is good, anchor bolts are good, electrical conduit is good. Okay to pour footers.
All 13 light pole bases have ground rods installed.