Permit Details

Status:
In Revision
Type:
Commercial Building
Address NEW:
10023 E OLD VAIL RD
Apply Date:
11/13/2025
Applicant:
Andrea Leonard
Description:
New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181

Permit Reviews

Permit Number - TC-COM-1125-02102
Permit Status: In revision
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Start Date Submittal Complete Date Status  
03/18/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/26/2026 APPROVED Review Details
11/14/2025 COMMERCIAL REVIEW - FULL v.1 12/08/2025 REQUIRES RESUBMIT Review Details
08/03/2026 COMMERCIAL REVIEW - FULL REVISION v.1 N/A IN REVIEW Review Details
01/20/2026 COMMERCIAL REVIEW - FULL v.3 02/04/2026 APPROVED Review Details
02/04/2026 RESTAMP - COMMERCIAL v.1 02/09/2026 APPROVED Review Details
12/19/2025 COMMERCIAL REVIEW - FULL v.2 01/06/2026 REQUIRES RESUBMIT Review Details
04/03/2026 COMMERCIAL REVIEW - FULL REVISION v.1 04/28/2026 APPROVED Review Details

Conditions

Permit Number - TC-COM-1125-02102
Permit Status: In revision
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Date Description Comments
11/14/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
11/14/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
11/14/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: In Revision
Permit Number: TC-COM-1125-02102
Permite Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Total Outstanding Inspections - 10
Last Inspection Date Description Inspector Results Comments
02/27/2026 COT - HCBU - Preslab N/A Canceled
03/16/2026 COT - HCEL - Electrical Underground N/A Partial Pass X4 2” schedule 40 at 24” depth all for communication purposes. Building 2. Okay to backfill. Shading required. 3/16/2026
05/28/2026 COT - HCBU - Roof Nailing N/A Partial Pass 5-28-26: nailing at roof decking only approved. Please schedule another nailing inspection to verify crickets & parapet walls.
06/26/2026 COT - HCPL - Plumbing Progress N/A Partial Pass 6-26-26: gas pressure test previously inspected.
06/26/2026 COT - HCPL - Rough Soil N/A Partial Pass 6-26-26: verified dry pack on 3 interior steel columns-okay for concrete placement.
03/02/2026 COT - HCEL - Electrical Progress N/A Partial Pass 3/2/26: UFER approved
06/05/2026 COT - HCBU - Exterior Clips/Sheathing N/A Partial Pass 6-5-26: sheathing screw inspection at pop outs of building along the south and east sides. Okay to continue with construction at progress areas. Crickets were also inspected and approved .
06/05/2026 COT - HCBU - Framing N/A Partial Pass 6-5-26: sheathing screw inspection at pop outs of building along the south and east sides. Okay to continue with construction at progress areas. Crickets were also inspected and approved .
COT - HCBU - Interior Shear Bracing N/A Scheduled
BULD - Electrical Clearance N/A Requested

Completed Inspections

Permit Status: In Revision
Permit Number: TC-COM-1125-02102
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Total Completed Inspections - 1
Date Description Inspector Results Comments
07/10/2026 COT - HCBU - Exterior Clips/Sheathing Passed 7.10.26
Holdowns installed along with anchor bolts.

Scheduled Inspections

Scheduled Inspections - TC-COM-1125-02102
Status: In Revision
Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Scheduled Date Description Entered By Entered Date
08/20/2026 COT - HCBU - Interior Shear Bracing Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-4_PLAN SET_V1.PDF DOCUMENTS VIEW
BUILDING 2 TRUSS DEFERRED SUBMITTAL_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-3_PLAN SET_V3.PDF DOCUMENTS VIEW
OVID - BLDGS 2 SI CERTS 2026-01-19-2026-01-19_V1.PDF DOCUMENTS VIEW
2_MECHANICAL COMCHECK_V1.PDF DOCUMENTS VIEW
2_STRUCTURAL ADDENDUM CALCULATIONS_V1.PDF DOCUMENTS VIEW