Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2026 | COT - HCBU - Framing | Partial Pass | 6-5-26: sheathing screw inspection at pop outs of building along the south and east sides. Okay to continue with construction at progress areas. Crickets were also inspected and approved . | |
| 07/01/2026 | COT - HCBU - Framing | Canceled | 7-1-26: canceled by contractor. | |
| 07/09/2026 | COT - HCBU - Framing | Partial Pass | ||
| 07/21/2026 | COT - HCBU - Framing | Re-inspection required | 7-21-26: add drywall screws to gyp board at party walls 8" o.c. throughout sill and in the field. Drywall screws cannot be closer than 3/8" from edges/joints. Add missing sections of drywall at party walls flush with decking or bottom of truss chords. | |
| 08/18/2026 | COT - HCBU - Framing | Re-inspection required | 8-18-26: Suite 163 has been divided into an additional Suite ( Suite XXX ) thus a party wall was added together with additional metal wall framing on the other side of the suite. Submit an updated framing/ site & floor plan to the city for review/approval. Add screws to the east party wall at suite xxx 8" o.c. Along the base and at joints above ceiling. Note: an updated metal wall framing plan must be submitted to the city for review/approval prior to proceeding with construction. |