Permit: TC-COM-0523-01329
Permit Details
Apply Date:
05/19/2023
Applicant:
Rebecca Roubion
Description:
N/A
Permit Reviews
Permit Number - TC-COM-0523-01329
Permit Status: Issued
Permit Description:
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/18/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/06/2023 | REQUIRES RESUBMIT |
04/22/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/25/2024 | APPROVED |
11/06/2024 | COMMERCIAL REVIEW - FULL REVISION v.1 | 12/02/2024 | APPROVED |
05/25/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/27/2023 | REQUIRES RESUBMIT |
03/08/2024 | COMMERCIAL REVIEW - FULL v.4 | 03/26/2024 | APPROVED |
03/26/2024 | RESTAMP - COMMERCIAL v.1 | 03/28/2024 | APPROVED |
12/05/2023 | COMMERCIAL REVIEW - FULL v.3 | 01/02/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0523-01329
Permit Status: Issued
Permit Description:
Total Outstanding Activity Conditions - 11
Date | Name |
---|---|
11/06/2024 | AIR BALANCING REPORT IS REQUIRED. |
11/06/2024 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
11/06/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
11/06/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
11/06/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
11/06/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
11/06/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
11/06/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
11/06/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
11/06/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
11/06/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0523-01329
Permit Status: Issued
Permit Description:
Date | Description | Comments |
---|---|---|
04/25/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0523-01329
Permite Description:
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/11/2024 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 9/11/24: red panda okay to cover underground feeder |
09/26/2024 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | Brazing below grade for Red Panda building. |
10/16/2024 | COT - HCBU - Stem Wall/Retaining Wall | N/A | Partial Pass | 10/16/24; stem walls for restroom okay to pour grout. |
10/29/2024 | COT - HCPL - Sewer | N/A | Partial Pass | Private man hole #1; 4” sewer line, approximately 50’ at tiger exhibitions. Ok to cover progress areas. |
11/06/2024 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | Plumbing underground at Fishing cat exhibit. Ok to cover progress areas. |
11/14/2024 | COT - HCPL - Yard Water Line | N/A | Partial Pass | Partial pass. Refer to highlight on plan. Okay to backfill progress areas. Shading required. 11/14/2024 |
12/10/2024 | COT - HCBU - Roof Nailing | N/A | Partial Pass | Roof system for pleasantry restroom. Ok to cover roof system |
11/18/2024 | COT - LCBU - Preslab | N/A | Partial Pass | 11/18/24: PRE SLAB FOR CONCRETE ROOF SLAB AT RED PANDA UPPER NORTH HALF passed ok to proceed. |
10/30/2024 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 10:30-24: Fishing Cat Building. |
12/19/2024 | COT - HCPL - Rough Soil | N/A | Partial Pass | Domestic water line (3”) for restrooms and fishing cat exhibit: approximately 40’. Ok to cover and compact progress areas. |
10/30/2024 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 10-30-24: Restrooms, 2nd lift, Red Panda, 2nd lift. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0523-01329
Permit Description:
Total Completed Inspections - 2
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/08/2024 | COT - HCEL - Grounding/Bonding | Passed | Grounding system (2 each,copper ufer lines) located in Northeast corner of building. | |
09/26/2024 | COT - HCBU - Preslab | Passed |