Parcel: 12620001C


Addresses:

3400 E ZOO CT


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-0523-01329

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
02/20/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Public restroom faux finish: #3 rebar with gunite finish. Ok to cover progress areas.
03/05/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
03/07/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Otter exhibit pump house.
03/10/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
03/14/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8/20/24: okay to pour footings for tiger life support area rebar mat and verticals to schedule.
8/26/24: partial pass at panda enclosure footings for CMU wall ok to pour.
8/29/24: stem wall at panda enclosure passed ok to proceed.

10:30-24: Fishing Cat Building.

12/18/24 reptile building footers no exterior columns. OK to place concrete.

3/5/25 Foundation for otter pit three sides of the footer OK for concrete placement and four side is up to an RFI

THEMATIC REBAR INSPECTION FOR RED PANDA
3/14/25: INSPECTION FOR REBAR AT RED PANDA FOR ROCK THEMING
04/10/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Footings for trash enclosure. Ok to place concrete,in progress areas.
04/14/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Northwest site wall at pavilion; approximately 75 feet of footings. Ok to place concrete in progress areas.
04/24/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Caisson footings and column footings at Red Panda exhibit; site wall footings at pavilion North to trash enclosure (approximately 125 feet). Ok to place concrete in progress areas.
04/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3-29-25, reinforcement/excavation for footing on otter building verified per plans. Okay to pour-see details 102 & 103.
08/08/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Building footings and column footings as per details; 101, 103. 107 on plans page SA2.1. OK to place concrete in progress areas.
08/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8/20/24: okay to pour footings for tiger life support area rebar mat and verticals to schedule.
08/26/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8/20/24: okay to pour footings for tiger life support area rebar mat and verticals to schedule.
8/26/24: partial pass at panda enclosure footings for CMU wall ok to pour.
08/29/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8/20/24: okay to pour footings for tiger life support area rebar mat and verticals to schedule.
8/26/24: partial pass at panda enclosure footings for CMU wall ok to pour.
8/29/24: stem wall at panda enclosure passed ok to proceed.
10/02/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Footings for public restrooms. Ok to place concrete in progress areas.
COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10:30-24: Fishing Cat Building.
12/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass