Parcel: 12620001C


Addresses:

3400 E ZOO CT


Inspection Status: Not Ready

Inspection History: COT - HCBU - Masonry Pregrout 

Permit Number - TC-COM-0523-01329

Inspection Description - COT - HCBU - Masonry Pregrout 

Inspection Status - Not Ready

Date Description Inspector Results Comments
01/08/2025 COT - HCBU - Masonry Pregrout  Not Ready Contractor cancelled, will reschedule.
01/09/2025 COT - HCBU - Masonry Pregrout  Partial Pass TIGER LIFE SUPPORT to 32' 8".
01/13/2025 COT - HCBU - Masonry Pregrout  Partial Pass Tiger life support area, CMU walls topped - out at 15’4”; Asian exhibit CMU walls East and West at 20’8” - 25’4”. OK to grout progress areas.
01/16/2025 COT - HCBU - Masonry Pregrout  Not Ready
03/14/2025 COT - HCBU - Masonry Pregrout  Partial Pass 8/20/24: Asia pavilion okay to grout stem wall.
10/16/24: pavilion and red panda okay to proceed to 2nd lift.
10/17/2024 partial pass 1st lift for the Tiger Life Support building.

Pavilion, grid line E to F/2, E grid lines 2-9, E to F grid line 6, grid line/6-9, G to F/9, second lift.

10-30-24: Restrooms, 2nd lift, Red Panda, 2nd lift.

Bathroom arch approved okay to fully grout.

Fishing cat building. Stem wall reinforcements per plan okay to grout progress areas.
Tiger life support. 2nd lift reinforcements per plan. Okay to grout progress areas.
Red panda building. Parapet section east end. reinforcements per plan.
Pavilion building. 8’8” - 12’8” south, east and west elevation. 11/13/2024
11/18/24:PRE GROUT FOR PAVILION TOP OUT ON CENTER BEARING WALL ok to proceed.

TIGER LIFE SUPPORT to 32' 8".
3/14/25: pregrout stem walls in otter building per detail 151. Ok to proceed.
03/27/2025 COT - HCBU - Masonry Pregrout  Partial Pass South and West CMU walls of reptile house at 64”. Ok to grout progress areas.
04/01/2025 COT - HCBU - Masonry Pregrout  Partial Pass South and West walls of reptile house at 9’4”. Ok to grout progress areas.
04/09/2025 COT - HCBU - Masonry Pregrout  Partial Pass Reptile house walls at 8’4” on North and East walls. Ok to grout progress area.
04/10/2025 COT - HCBU - Masonry Pregrout  Partial Pass CMU walls at 48” for,otter pump room. Ok to grout progress area.
04/18/2025 COT - HCBU - Masonry Pregrout  Partial Pass Exterior walls of Fishing Cat for decorative finish. Ok to stucco mesh and scratch coat.
05/01/2025 COT - HCBU - Masonry Pregrout  Partial Pass Reptile house CMU Walls: South wall at 8’8” - 11’8”, West wall at 8’4” - 12’4”. OK to grout progress areas.
05/08/2025 COT - HCBU - Masonry Pregrout  Partial Pass Otter building stem wall high and lower elevations. Okay to grout progress areas.

Top out at reptile building west and north walls. Bearing plates at interior south wall in place. North interior wall at top out. East wall at top out. South exterior half from door entry wall connected to the interior at top out. Wall with three windows at 3rd lift approved. 5/8/2025
05/13/2025 COT - HCBU - Masonry Pregrout  Partial Pass This inspection is for excavation/rebar for tiger support area, footings. Ok to place concrete when architect places locations of sliding doors.
05/16/2025 COT - HCBU - Masonry Pregrout  Partial Pass Reptile house interior walls at 0’ - 4’; trash enclosure walls (South and East) at 0’ - 4’, West stem wall, North columns (5) at first lift. Ok to grout progress areas.
05/28/2025 COT - HCBU - Masonry Pregrout  Partial Pass Reptile house North exterior wall at 13’4”; interior walls at 11’6” - 13’4”. Ok to grout progress areas.
06/24/2025 COT - HCBU - Masonry Pregrout  Partial Pass Otter house; CMU Walls at 4’ AFFE. OK to place grout in progress areas.
06/27/2025 COT - HCBU - Masonry Pregrout  Canceled Contractor cancelled.
07/01/2025 COT - HCBU - Masonry Pregrout  Partial Pass Column footings for new main entry area. Otter house; second lift at 4’ - 8’ AFFE. Reptile House; interior section walls at 4’ AFFE, exterior walls at 4’ AFFE on North side of building. Ok to grout progress areas.
07/08/2025 COT - HCBU - Masonry Pregrout  Partial Pass Otter house CMU walls at 8’ - 10’ AFFE (exterior). Ok to place grout in progress areas.
07/09/2025 COT - HCBU - Masonry Pregrout  Partial Pass Reptile house interior walls at 10’4”. Tiger enclosure East wall at 4’ AFFE. OK to place grout in progress areas.
07/15/2025 COT - HCBU - Masonry Pregrout  Partial Pass Northeast wall of Tiger exhibit, approximately 45 feet. Ok to grout progress area.
07/18/2025 COT - HCBU - Masonry Pregrout  Partial Pass Tiger house at interior walls at 6’ AFFE on North, South, East walls. Reptile,house exterior walls North and South at 12’ - 16’. Ok to grout progress areas.
07/22/2025 COT - HCBU - Masonry Pregrout  Partial Pass Reptile exhibit exterior walls (North and Northeast) at 14’6”. Ok to grout progress areas. Otter house roof; rebar in place, Ok to place concrete in progress areas.
07/28/2025 COT - HCBU - Masonry Pregrout  Partial Pass Siamang tiger exhibit CMU walls at 54” AFFE. Panda exhibit East portion stem walls at 12”. OK to place concrete in progress areas.
08/05/2025 COT - HCBU - Masonry Pregrout  Partial Pass 8-5-25: reinforcement verified per plans for top out at Otter exhibit parapet-Okay to pour grout.
08/06/2025 COT - HCBU - Masonry Pregrout  Partial Pass otter yard: 1st lift. Reptile: exterior wall by bat exhibit, up to 8’, interior walls of bird holding.
08/08/2025 COT - HCBU - Masonry Pregrout  Partial Pass 8/8/2025 2nd lift at otter building LSS equipment room.
Top out at shear wall and visitors center room. Okay to grout all progress areas.
08/13/2025 COT - HCBU - Masonry Pregrout  Partial Pass Reptile house at electric room, mechanical room, break room: masonry walls at 48” above AFF. OK to continue at eight foot lifts with clean-outs.
08/20/2024 COT - HCBU - Masonry Pregrout  Partial Pass 8/20/24: Asia pavilion okay to grout stem wall
08/20/2025 COT - HCBU - Masonry Pregrout  Partial Pass Kimono dragon exhibit are walls at 8’ 8”. Ok to grout progress areas.
09/04/2025 COT - HCBU - Masonry Pregrout  Partial Pass Reptile house East wall at 12’8”, interior East wall at 14’ - 18’; West interior walls at 18’8” (top out). Ok to.grout progress areas.
09/05/2025 COT - HCBU - Masonry Pregrout  Partial Pass Reptile house - bat exhibit CMU walls at 12’ 8”; Tiger night house stem wall at 24” AFFE. OK to grout progress areas.
09/10/2025 COT - HCBU - Masonry Pregrout  Partial Pass Bat exhibit and visitor walls, topped out at 12’8”. Columns at main entry at 12’8”. Ok to grout progress areas.
09/15/2025 COT - HCBU - Masonry Pregrout  Partial Pass Siamang building at 4’ - 8’ masonry lift. Ok to grout progress areas.
09/25/2025 COT - HCBU - Masonry Pregrout  Partial Pass 9/25/2025 Siamang building. Sterile and interior cmu walls at deck elevation and tiger off holding wall at top out. Tiger exhibit wall from siamang night house to tiger exhibit gate. 1st lift. Approved per third party report. Okay to grout all progress areas.
10/01/2025 COT - HCBU - Masonry Pregrout  Partial Pass 10/1/2025 Tiger night house building all walls approved per third party report.
10/03/2025 COT - HCBU - Masonry Pregrout  Partial Pass North CMU wall of Tiger Enclosure at 10’; entry area lintels of reptile house. Ok to place grout in progress areas.
10/07/2025 COT - HCBU - Masonry Pregrout  Partial Pass Tiger night house interior walls at 4’ - 8’. Ok to grout -regress areas. Reptile house exterior walls topped out. Ok to grout,progress areas.
10/08/2025 COT - HCBU - Masonry Pregrout  Partial Pass 10/8/2025 Saimang house. Parapet wall all sides approved.
10/10/2025 COT - HCBU - Masonry Pregrout  Not Ready
10/16/2024 COT - HCBU - Masonry Pregrout  Partial Pass 10/16/24: pavilion and red panda okay to proceed to 2nd lift.
10/16/2025 COT - HCBU - Masonry Pregrout  Canceled 10/16/2025 canceled per contractor.
10/17/2024 COT - HCBU - Masonry Pregrout  Partial Pass 10/17/2024 partial pass 1st lift for the Tiger Life Support building.
10/21/2025 COT - HCBU - Masonry Pregrout  Partial Pass Tiger LSS buildings, 1st lift complete. Aviary stem wall.
10/25/2024 COT - HCBU - Masonry Pregrout  Partial Pass
10/27/2025 COT - HCBU - Masonry Pregrout  Partial Pass Second lift (4’ - 8’) South and Southeast portion of Tiger LSS building. Ok to place grout in progress areas.
10/28/2024 COT - HCBU - Masonry Pregrout  Partial Pass North and East CMU walls at 8’ - 12’. West interior wall at 8’ - 12’. Ok to grout progress areas of Asia Pavilion.. Public restroom CMU walls at 0’ - 4’. Ok to grout progress areas.
10/30/2024 COT - HCBU - Masonry Pregrout  Partial Pass 10-30-24: Restrooms, 2nd lift, Red Panda, 2nd lift.
10/30/2025 COT - HCBU - Masonry Pregrout  Not Ready Contractor cancelled, will reschedule for 31 October.
11/04/2024 COT - HCBU - Masonry Pregrout  Not Ready Contractor cancelled due to inclement weather.
11/05/2024 COT - HCBU - Masonry Pregrout  Partial Pass Asian exhibit CMU walls: North, East, West walls at 8’ - 12’. Tiger support building, masonry walls at 0’ - 4’. Ok to grout progress areas.
11/05/2025 COT - HCBU - Masonry Pregrout  Partial Pass Masonry pre-grout at Tiger night house: North and West walls at 16’ - 18’, crossover to Tiger life support building. Ok to grout progress areas. Tiger pavilion #2, North footing in place. Ok to place concrete in progress area. Aviary slabs (2) and generator pad. Ok to,place concrete in progress areas. Plumbing underground: water lines for heating rocks at Reptile house. Ok to insulate and cover progress areas.
11/07/2024 COT - HCBU - Masonry Pregrout  Partial Pass Asian pavilion exhibit; CMU walls 15’4” at East, West, and interior walls. South area; 8 CMU columns at 8’ - 12’. Asian area public restrooms; CMU walls at 17’4” at South, West, North walls. OK to grout progress areas.
11/10/2025 COT - HCBU - Masonry Pregrout  Partial Pass Tiger night house, West and Southwest CMU walls at 16’ - 18’ top-out. OK to grout progress areas.
11/13/2024 COT - HCBU - Masonry Pregrout  Partial Pass Fishing cat building. Stem wall reinforcements per plan okay to grout progress areas.
Tiger life support. 2nd lift reinforcements per plan. Okay to grout progress areas.
Red panda building. Parapet section east end. reinforcements per plan.
Pavilion building. 8’8” - 12’8” south, east and west elevation. 11/13/2024
11/15/2024 COT - HCBU - Masonry Pregrout  Partial Pass Tiger life support CMU Walls at 12’8”. Ok to place grout in progress areas.
11/18/2024 COT - HCBU - Masonry Pregrout  Partial Pass 8/20/24: Asia pavilion okay to grout stem wall.
10/16/24: pavilion and red panda okay to proceed to 2nd lift.
10/17/2024 partial pass 1st lift for the Tiger Life Support building.

Pavilion, grid line E to F/2, E grid lines 2-9, E to F grid line 6, grid line/6-9, G to F/9, second lift.

10-30-24: Restrooms, 2nd lift, Red Panda, 2nd lift.

Bathroom arch approved okay to fully grout.

Fishing cat building. Stem wall reinforcements per plan okay to grout progress areas.
Tiger life support. 2nd lift reinforcements per plan. Okay to grout progress areas.
Red panda building. Parapet section east end. reinforcements per plan.
Pavilion building. 8’8” - 12’8” south, east and west elevation. 11/13/2024
11/18/24:PRE GROUT FOR PAVILION TOP OUT ON CENTER BEARING WALL ok to proceed.
11/19/2024 COT - HCBU - Masonry Pregrout  Partial Pass Asian pavilion South CMU wall at 12’8” - 18’8” top out GL: C/2 - 9. OK to grout progress areas.
11/26/2024 COT - HCBU - Masonry Pregrout  Partial Pass Red panda exhibit walls at top - out :15’8” to top of parapet walls. Fishing cat exhibit walls at 0’ - 4’8”. OK to place grout in progress areas.
12/03/2024 COT - HCBU - Masonry Pregrout  Partial Pass Fishing cat exhibit; East masonry wall at 10’4”; West masonry wall at 9’4”. OK to grout progress areas.
12/05/2024 COT - HCBU - Masonry Pregrout  Partial Pass Fishing cat exhibit CMU walls at 9’ - 10’4” on East and West ends.
12/11/2024 COT - HCBU - Masonry Pregrout  Partial Pass Tiger life support structure: South, West and Northwest portion of North CMU walls at 4’ AFFE. Northeast portion of North wall at 2’ AFFE. OK to grout progress areas.
12/19/2024 COT - HCBU - Masonry Pregrout  Partial Pass Fishing cat exhibit; CMU walls topped-out. OK to.grout progress areas.