Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Masonry Pregrout
Permit Number - TC-COM-0523-01329
Inspection Description - COT - HCBU - Masonry Pregrout
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/08/2025 | COT - HCBU - Masonry Pregrout | Not Ready | Contractor cancelled, will reschedule. | |
01/09/2025 | COT - HCBU - Masonry Pregrout | Partial Pass | TIGER LIFE SUPPORT to 32' 8". | |
01/13/2025 | COT - HCBU - Masonry Pregrout | Partial Pass | Tiger life support area, CMU walls topped - out at 15’4”; Asian exhibit CMU walls East and West at 20’8” - 25’4”. OK to grout progress areas. | |
01/16/2025 | COT - HCBU - Masonry Pregrout | Not Ready | ||
08/20/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 8/20/24: Asia pavilion okay to grout stem wall | |
10/16/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 10/16/24: pavilion and red panda okay to proceed to 2nd lift. | |
10/17/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 10/17/2024 partial pass 1st lift for the Tiger Life Support building. | |
10/25/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | ||
10/28/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | North and East CMU walls at 8’ - 12’. West interior wall at 8’ - 12’. Ok to grout progress areas of Asia Pavilion.. Public restroom CMU walls at 0’ - 4’. Ok to grout progress areas. | |
10/30/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 10-30-24: Restrooms, 2nd lift, Red Panda, 2nd lift. | |
11/04/2024 | COT - HCBU - Masonry Pregrout | Not Ready | Contractor cancelled due to inclement weather. | |
11/05/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Asian exhibit CMU walls: North, East, West walls at 8’ - 12’. Tiger support building, masonry walls at 0’ - 4’. Ok to grout progress areas. | |
11/07/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Asian pavilion exhibit; CMU walls 15’4” at East, West, and interior walls. South area; 8 CMU columns at 8’ - 12’. Asian area public restrooms; CMU walls at 17’4” at South, West, North walls. OK to grout progress areas. | |
11/13/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Fishing cat building. Stem wall reinforcements per plan okay to grout progress areas. Tiger life support. 2nd lift reinforcements per plan. Okay to grout progress areas. Red panda building. Parapet section east end. reinforcements per plan. Pavilion building. 8’8” - 12’8” south, east and west elevation. 11/13/2024 |
|
11/15/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Tiger life support CMU Walls at 12’8”. Ok to place grout in progress areas. | |
11/18/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 8/20/24: Asia pavilion okay to grout stem wall. 10/16/24: pavilion and red panda okay to proceed to 2nd lift. 10/17/2024 partial pass 1st lift for the Tiger Life Support building. Pavilion, grid line E to F/2, E grid lines 2-9, E to F grid line 6, grid line/6-9, G to F/9, second lift. 10-30-24: Restrooms, 2nd lift, Red Panda, 2nd lift. Bathroom arch approved okay to fully grout. Fishing cat building. Stem wall reinforcements per plan okay to grout progress areas. Tiger life support. 2nd lift reinforcements per plan. Okay to grout progress areas. Red panda building. Parapet section east end. reinforcements per plan. Pavilion building. 8’8” - 12’8” south, east and west elevation. 11/13/2024 11/18/24:PRE GROUT FOR PAVILION TOP OUT ON CENTER BEARING WALL ok to proceed. |
|
11/19/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Asian pavilion South CMU wall at 12’8” - 18’8” top out GL: C/2 - 9. OK to grout progress areas. | |
11/26/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Red panda exhibit walls at top - out :15’8” to top of parapet walls. Fishing cat exhibit walls at 0’ - 4’8”. OK to place grout in progress areas. | |
12/03/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Fishing cat exhibit; East masonry wall at 10’4”; West masonry wall at 9’4”. OK to grout progress areas. | |
12/05/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Fishing cat exhibit CMU walls at 9’ - 10’4” on East and West ends. | |
12/11/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Tiger life support structure: South, West and Northwest portion of North CMU walls at 4’ AFFE. Northeast portion of North wall at 2’ AFFE. OK to grout progress areas. | |
12/19/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Fishing cat exhibit; CMU walls topped-out. OK to.grout progress areas. |