Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 04/02/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
4-2-25, underground plumbing for grease interceptor approved. Okay to backfill progress areas. |
| 04/14/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Domestic water lines in pheasantry restrooms. |
| 04/16/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Gas lines for pavilion; vent lines for Fishing cat, Red Panda,Pheasantry Restrooms. Included in this inspection is stem wall footings from pheasant restrooms to,pavilion; approximately 215 feet. Ok to,place,concrete in progress areas. |
| 06/18/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Underground plumbing for tiger sleeping quarters: waste lines at 2” - 4”. Ok to cover progress areas. |
| 09/22/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Water lines and drain lines to bird pool at pheasantry. Ok to cover progress area. |
| 09/26/2024 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Brazing below grade for Red Panda building. |