Inspection Status: Partial Pass
Inspection History: COT - HCBU - Stem Wall/Retaining Wall
| Date |
Description |
Inspector |
Results |
Comments |
| 01/31/2025 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
24” stem wall on west side of reptile house. East side is missing rebar for bond beam. Ok to grout progress areas. |
| 04/01/2026 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
Tiger compound wall second lift. |
| 04/17/2025 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
Stem wall footing from pheasant restrooms to pavilion at approximately 215 feet. Ok to place concrete in progress areas. |
| 07/31/2025 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
Stem wall/retaining wall at Northeast corner of reptile house at 4’ x 45’. Ok to -lace concrete in progress area. |
| 08/05/2025 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Not Ready |
8-5-25: not ready-contractor will reschedule. |
| 08/19/2024 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
Stem wall at GL: C - F.5; 6 - 9. Ok to place grout in progress areas. |
| 10/01/2025 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
10/1/2025 tiger life building all walls @ stem wall, tiger off holding wall and entry wall @ NWC os saimung cat Roth at 0'-5'4. |
| 10/16/2024 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
10/16/24; stem walls for restroom okay to pour grout. |