Permit Details

Status:
Issued
Type:
Commercial Building
Address NEW:
6550 S BAY COLONY DR
Apply Date:
03/05/2025
Applicant:
Daniel Gullick
Description:
TI within existing building, expansion into neighboring vacant shell space

Permit Reviews

Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Start Date Submittal Complete Date Status  
01/06/2026 COMMERCIAL REVIEW - FULL REVISION v.2 01/27/2026 REQUIRES RESUBMIT Review Details
02/02/2026 COMMERCIAL REVIEW - FULL REVISION v.3 02/26/2026 APPROVED Review Details
03/06/2025 COMMERCIAL REVIEW - FULL v.1 04/01/2025 REQUIRES RESUBMIT Review Details
04/09/2025 RESTAMP - COMMERCIAL v.1 04/15/2025 APPROVED Review Details
10/23/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/12/2026 APPROVED Review Details
04/02/2025 COMMERCIAL REVIEW - FULL v.2 04/09/2025 APPROVED Review Details
12/02/2025 COMMERCIAL REVIEW - FULL REVISION v.1 12/23/2025 REQUIRES RESUBMIT Review Details
08/18/2026 SPECIAL INSPECTION REVIEW v.1 08/21/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Total Outstanding Activity Conditions - 3
Date Name
04/09/2025 AIR BALANCING REPORT IS REQUIRED.
04/09/2025 ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
04/09/2025 WATER STERILIZATION REPORT IS REQUIRED.

Conditions

Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Date Description Comments
04/09/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
02/24/2026 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
04/09/2025 Elevator Designs must be submitted and approved prior to ...
04/09/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/09/2025 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
06/05/2026 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
04/09/2025 Masonry Inspection Report submittal review is required.
04/09/2025 Post-Installed Anchor Inspection Report is required.
03/06/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
03/06/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
04/09/2025 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
03/06/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
04/09/2025 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0325-00427
Permite Description: TI within existing building, expansion into neighboring vacant shell space
Total Outstanding Inspections - 17
Last Inspection Date Description Inspector Results Comments
03/04/2026 COT - HCBU - Masonry Pregrout N/A Partial Pass 3-4-26: reinforcement at elevator shaft approved. North cmu wall top out at 29' 2" & south wall at 28' 8"-okay to grout.
12/16/2025 COT - HCPL - Rough Soil N/A Partial Pass 12-16-25: underground plumbing at 1st floor restroom & mop sink verified under test. Toilet was relocated to opposite side of what plans show and a revision to the city has been submitted for review. Okay to backfill using shading materials at own risk and continue with construction.
02/11/2026 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 2-11-26: reinforcement at elevator shaft verified per plans and per revision ASI #3, 8/14/25-detail, 11 for masonry pier at elevator shaft. Okay to grout 3rd lift at 13' 4".
06/25/2026 COT - HCME - Mechanical Intermediate N/A Partial Pass 6-25-26: partial pass at above ceiling mechanical at new restrooms, janitor room, corridor between G/L; E1/ 10-12.1. Verified restroom fans & pookie at ducts. Okay to insulate remaining round duct at new corridor and restroom. Add supports to flex at 4' intervals and supports writhing 2' of a bend/joint.
07/24/2026 COT - FCON - Alarm - Final N/A Partial Pass Dewar room is approved.
07/24/2026 COT - FCON - Sprinkler - Final N/A Partial Pass Dewar room is approved.
09/02/2026 COT - HCPL - Plumbing Intermediate N/A Partial Pass
08/11/2026 COT - HCEL - Electrical Intermediate N/A Partial Pass 8/11/2026 Partial pass. Office east end of elevator in wall approved.
10/08/2026 COT - HCBU - Building Above Ceiling N/A Partial Pass
10/08/2026 COT - HCEL - Electrical Above Ceiling N/A Partial Pass
10/08/2026 COT - HCME - Mechanical Above Ceiling N/A Partial Pass
10/08/2026 COT - HCPL - Plumbing Above Ceiling N/A Partial Pass
10/02/2026 COT - HCBU - Framing N/A Partial Pass 10/2/26: Framing at elevator 1st and 2nd floor south and north face per approved plans wall type H and H1.
10/22/2026 COT - HCBU - Building Final N/A Partial Pass 10/22/26: pending conditions & other inspections.
10/22/2026 COT - HCPL - Plumbing Final N/A Partial Pass 10/22/26: pending water sterilization approval.
07/24/2026 COT - FCON - Fire - Final N/A Partial Pass Dewar room is approved. OK for TCO level 4 dewar room only.
08/04/2026 ENGR Engineering Final N/A Partial Pass 8/4/26 All building materials and equipment dumpsters, etc and construction activity are behind fencing. Access to suite 100 is clear for emergency services and to public. Okay to apply for a level 4 TCO.

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0325-00427
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Total Completed Inspections - 6
Date Description Inspector Results Comments
03/19/2026 COT - HCBU - Exterior Clips/Sheathing Passed East and west detail 1 page S41 on roof joist connection to CMU BRG wall.
North and south detail 2 page S41 ledger connection. 3/19/2026
03/19/2026 COT - HCBU - Roof Nailing Passed
07/07/2026 COT - HCBU - Preslab Passed 7.7.26
Last small section on north end.
10/14/2026 COT - HCBU - Framing Passed 10/14/26: metal framing & drywall screw inspection at 1st floor northeast corner approved. Okay to tape & texture drywall.
10/22/2026 COT - HCEL - Electrical Final Passed 10/22/26: electrical final approved.
10/22/2026 COT - HCME - Mechanical Final Passed 10/22/26: mechanical final approved.

Documents

File Name Document Type  
COFO_TEMPORARYCOFO (SSRS).PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO (SSRS).PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO (SSRS).PDF DOCUMENTS VIEW
TC-COM-0325-00427_CBR DEWAR TI PHASE 2_63241153 - SIGNED (TERRACON)-2026-08-14_V1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO (SSRS).PDF DOCUMENTS VIEW
2026-01-15 (CBR PH II - CLEAN ROOM PERMIT SET - REVISION SET RESPONSE LETTER)_V3.PDF DOCUMENTS VIEW
CBR2NDFLOOR_CALCULATIONS SUPPLEMENTAL_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-2026-01-14 (CBR PH II - CLEAN ROOM PERMIT SET - RESPONSE SET)_V3.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-2025-03-31 (CBR DEWAR T.I. - PHASE 2 - DELTA 1-2 SET)_V2.PDF DOCUMENTS VIEW
CBR2NDFLOOR_CALCULATIONS_V2.PDF DOCUMENTS VIEW
SIC_V1.PDF DOCUMENTS VIEW