Permit Details

Status:
Issued
Type:
Commercial Building
Address NEW:
6550 S BAY COLONY DR
Apply Date:
03/05/2025
Applicant:
Daniel Gullick
Description:
TI within existing building, expansion into neighboring vacant shell space

Permit Reviews

Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Start Date Submittal Complete Date Status  
01/06/2026 COMMERCIAL REVIEW - FULL REVISION v.2 01/27/2026 REQUIRES RESUBMIT Review Details
02/02/2026 COMMERCIAL REVIEW - FULL REVISION v.3 02/26/2026 APPROVED Review Details
03/06/2025 COMMERCIAL REVIEW - FULL v.1 04/01/2025 REQUIRES RESUBMIT Review Details
04/09/2025 RESTAMP - COMMERCIAL v.1 04/15/2025 APPROVED Review Details
04/02/2025 COMMERCIAL REVIEW - FULL v.2 04/09/2025 APPROVED Review Details
12/02/2025 COMMERCIAL REVIEW - FULL REVISION v.1 12/23/2025 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Total Outstanding Activity Conditions - 12
Date Name
04/09/2025 AIR BALANCING REPORT IS REQUIRED.
04/09/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/09/2025 Elevator Designs must be submitted and approved prior to ...
04/09/2025 ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
04/09/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/09/2025 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
04/09/2025 Masonry Inspection Report submittal review is required.
04/09/2025 Post-Installed Anchor Inspection Report is required.
04/09/2025 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
04/09/2025 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
04/09/2025 WATER STERILIZATION REPORT IS REQUIRED.
06/05/2026 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.

Conditions

Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Date Description Comments
02/24/2026 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
03/06/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
03/06/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
03/06/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0325-00427
Permite Description: TI within existing building, expansion into neighboring vacant shell space
Total Outstanding Inspections - 18
Last Inspection Date Description Inspector Results Comments
03/04/2026 COT - HCBU - Masonry Pregrout N/A Partial Pass 3-4-26: reinforcement at elevator shaft approved. North cmu wall top out at 29' 2" & south wall at 28' 8"-okay to grout.
12/16/2025 COT - HCPL - Rough Soil N/A Partial Pass 12-16-25: underground plumbing at 1st floor restroom & mop sink verified under test. Toilet was relocated to opposite side of what plans show and a revision to the city has been submitted for review. Okay to backfill using shading materials at own risk and continue with construction.
02/11/2026 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 2-11-26: reinforcement at elevator shaft verified per plans and per revision ASI #3, 8/14/25-detail, 11 for masonry pier at elevator shaft. Okay to grout 3rd lift at 13' 4".
06/25/2026 COT - HCME - Mechanical Intermediate N/A Partial Pass 6-25-26: partial pass at above ceiling mechanical at new restrooms, janitor room, corridor between G/L; E1/ 10-12.1. Verified restroom fans & pookie at ducts. Okay to insulate remaining round duct at new corridor and restroom. Add supports to flex at 4' intervals and supports writhing 2' of a bend/joint.
06/26/2026 COT - HCPL - Plumbing Above Ceiling N/A Partial Pass 6-26-26: plumbing intermediate's & plumbing above ceiling inspection-corrections made at corridor, men's/woman's restroom, and janitor's room. DWV & domestic verified under test. Okay to continue with construction at progress areas.
06/26/2026 COT - HCPL - Plumbing Intermediate N/A Partial Pass 6-26-26: plumbing intermediate's & plumbing above ceiling inspection-corrections made at corridor, men's/woman's restroom, and janitor's room. DWV & domestic verified under test. Okay to continue with construction at progress areas.
07/24/2026 COT - FCON - Alarm - Final N/A Partial Pass Dewar room is approved.
07/24/2026 COT - FCON - Fire - Final N/A Partial Pass Dewar room is approved. OK for TCO level 4 dewar room only.
07/24/2026 COT - FCON - Sprinkler - Final N/A Partial Pass Dewar room is approved.
07/24/2026 COT - HCEL - Electrical Final N/A Partial Pass 7-24-26: partial pass pending liquid nitrogen line installation at Suite 100. Okay to apply for a Level 1 TCO for STE. 100-Expansion Tank Area Only. Please install a sign at door which will be closed off stating " Not an Exit-Active Construction-No Entry Allowed."
Note: this was the only section of the construction inspected.
07/24/2026 COT - HCME - Mechanical Final N/A Partial Pass 7-24-26: partial pass pending liquid nitrogen line installation at Suite 100. Okay to apply for a Level 1 TCO for STE. 100-Expansion Tank Area Only. Please install a sign at door which will be closed off stating " Not an Exit-Active Construction-No Entry Allowed."
Note: this was the only section of the construction inspected.
07/31/2026 COT - HCBU - Building Final N/A Partial Pass 7-31-26: okay to apply for a Level 4 TCO for Suite 100.
08/04/2026 ENGR Engineering Final N/A Partial Pass 8/4/26 All building materials and equipment dumpsters, etc and construction activity are behind fencing. Access to suite 100 is clear for emergency services and to public. Okay to apply for a level 4 TCO.
08/07/2026 COT - HCEL - Electrical Above Ceiling N/A Partial Pass 8-7-26: electrical above ceiling intermediates at kit ops room approved. Okay to install seismic wiring at hard lid.
08/07/2026 COT - HCME - Mechanical Above Ceiling N/A Partial Pass 8-7-26: mechanical above ceiling at kit ops room approved. Okay to continue with construction at progress areas.
08/07/2026 COT - HCBU - Building Above Ceiling N/A Partial Pass 8-7-26: kit ops above ceiling hard lid framing approved.
08/11/2026 COT - HCEL - Electrical Intermediate N/A Partial Pass 8/11/2026 Partial pass. Office east end of elevator in wall approved.
08/11/2026 COT - HCBU - Framing N/A Partial Pass 8/11/2026 Partial pass 2nd floor west wall of clean room.
East and west end walls of elevator. Outside of electrical room walls all approved for drywall screws.
KITOPS drywall screw inspection at ceiling approved.

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0325-00427
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Total Completed Inspections - 3
Date Description Inspector Results Comments
03/19/2026 COT - HCBU - Exterior Clips/Sheathing Passed East and west detail 1 page S41 on roof joist connection to CMU BRG wall.
North and south detail 2 page S41 ledger connection. 3/19/2026
03/19/2026 COT - HCBU - Roof Nailing Passed
07/07/2026 COT - HCBU - Preslab Passed 7.7.26
Last small section on north end.

Scheduled Inspections

Scheduled Inspections - TC-COM-0325-00427
Status: Issued
Description: TI within existing building, expansion into neighboring vacant shell space
Scheduled Date Description Entered By Entered Date
08/17/2026 COT - HCBU - Framing Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .

Documents

File Name Document Type  
COFO_TEMPORARYCOFO (SSRS).PDF DOCUMENTS VIEW
2026-01-15 (CBR PH II - CLEAN ROOM PERMIT SET - REVISION SET RESPONSE LETTER)_V3.PDF DOCUMENTS VIEW
CBR2NDFLOOR_CALCULATIONS SUPPLEMENTAL_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-2026-01-14 (CBR PH II - CLEAN ROOM PERMIT SET - RESPONSE SET)_V3.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-2025-03-31 (CBR DEWAR T.I. - PHASE 2 - DELTA 1-2 SET)_V2.PDF DOCUMENTS VIEW
CBR2NDFLOOR_CALCULATIONS_V2.PDF DOCUMENTS VIEW