Permit: TC-COM-0325-00427
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
6550 S BAY COLONY DR
Address NEW:
6550 S BAY COLONY DR
Apply Date:
03/05/2025
Applicant:
Daniel Gullick
Description:
TI within existing building, expansion into neighboring vacant shell space
Permit Reviews
Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2026 | COMMERCIAL REVIEW - FULL REVISION v.2 | 01/27/2026 | REQUIRES RESUBMIT |
| 02/02/2026 | COMMERCIAL REVIEW - FULL REVISION v.3 | 02/26/2026 | APPROVED |
| 03/06/2025 | COMMERCIAL REVIEW - FULL v.1 | 04/01/2025 | REQUIRES RESUBMIT |
| 04/09/2025 | RESTAMP - COMMERCIAL v.1 | 04/15/2025 | APPROVED |
| 04/02/2025 | COMMERCIAL REVIEW - FULL v.2 | 04/09/2025 | APPROVED |
| 12/02/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 12/23/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Total Outstanding Activity Conditions - 12
| Date | Name |
|---|---|
| 04/09/2025 | AIR BALANCING REPORT IS REQUIRED. |
| 04/09/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 04/09/2025 | Elevator Designs must be submitted and approved prior to ... |
| 04/09/2025 | ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
| 04/09/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 04/09/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 04/09/2025 | Masonry Inspection Report submittal review is required. |
| 04/09/2025 | Post-Installed Anchor Inspection Report is required. |
| 04/09/2025 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 04/09/2025 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 04/09/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
| 06/05/2026 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
| Date | Description | Comments |
|---|---|---|
| 02/24/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 03/06/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 03/06/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 03/06/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0325-00427
Permite Description: TI within existing building, expansion into neighboring vacant shell space
Total Outstanding Inspections - 18
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/04/2026 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 3-4-26: reinforcement at elevator shaft approved. North cmu wall top out at 29' 2" & south wall at 28' 8"-okay to grout. |
| 12/16/2025 | COT - HCPL - Rough Soil | N/A | Partial Pass | 12-16-25: underground plumbing at 1st floor restroom & mop sink verified under test. Toilet was relocated to opposite side of what plans show and a revision to the city has been submitted for review. Okay to backfill using shading materials at own risk and continue with construction. |
| 02/11/2026 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 2-11-26: reinforcement at elevator shaft verified per plans and per revision ASI #3, 8/14/25-detail, 11 for masonry pier at elevator shaft. Okay to grout 3rd lift at 13' 4". |
| 06/25/2026 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 6-25-26: partial pass at above ceiling mechanical at new restrooms, janitor room, corridor between G/L; E1/ 10-12.1. Verified restroom fans & pookie at ducts. Okay to insulate remaining round duct at new corridor and restroom. Add supports to flex at 4' intervals and supports writhing 2' of a bend/joint. |
| 06/26/2026 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | 6-26-26: plumbing intermediate's & plumbing above ceiling inspection-corrections made at corridor, men's/woman's restroom, and janitor's room. DWV & domestic verified under test. Okay to continue with construction at progress areas. |
| 06/26/2026 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 6-26-26: plumbing intermediate's & plumbing above ceiling inspection-corrections made at corridor, men's/woman's restroom, and janitor's room. DWV & domestic verified under test. Okay to continue with construction at progress areas. |
| 07/24/2026 | COT - FCON - Alarm - Final | N/A | Partial Pass | Dewar room is approved. |
| 07/24/2026 | COT - FCON - Fire - Final | N/A | Partial Pass | Dewar room is approved. OK for TCO level 4 dewar room only. |
| 07/24/2026 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Dewar room is approved. |
| 07/24/2026 | COT - HCEL - Electrical Final | N/A | Partial Pass | 7-24-26: partial pass pending liquid nitrogen line installation at Suite 100. Okay to apply for a Level 1 TCO for STE. 100-Expansion Tank Area Only. Please install a sign at door which will be closed off stating " Not an Exit-Active Construction-No Entry Allowed." Note: this was the only section of the construction inspected. |
| 07/24/2026 | COT - HCME - Mechanical Final | N/A | Partial Pass | 7-24-26: partial pass pending liquid nitrogen line installation at Suite 100. Okay to apply for a Level 1 TCO for STE. 100-Expansion Tank Area Only. Please install a sign at door which will be closed off stating " Not an Exit-Active Construction-No Entry Allowed." Note: this was the only section of the construction inspected. |
| 07/31/2026 | COT - HCBU - Building Final | N/A | Partial Pass | 7-31-26: okay to apply for a Level 4 TCO for Suite 100. |
| 08/04/2026 | ENGR Engineering Final | N/A | Partial Pass | 8/4/26 All building materials and equipment dumpsters, etc and construction activity are behind fencing. Access to suite 100 is clear for emergency services and to public. Okay to apply for a level 4 TCO. |
| 08/07/2026 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 8-7-26: electrical above ceiling intermediates at kit ops room approved. Okay to install seismic wiring at hard lid. |
| 08/07/2026 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | 8-7-26: mechanical above ceiling at kit ops room approved. Okay to continue with construction at progress areas. |
| 08/07/2026 | COT - HCBU - Building Above Ceiling | N/A | Partial Pass | 8-7-26: kit ops above ceiling hard lid framing approved. |
| 08/11/2026 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 8/11/2026 Partial pass. Office east end of elevator in wall approved. |
| 08/11/2026 | COT - HCBU - Framing | N/A | Partial Pass | 8/11/2026 Partial pass 2nd floor west wall of clean room. East and west end walls of elevator. Outside of electrical room walls all approved for drywall screws. KITOPS drywall screw inspection at ceiling approved. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0325-00427
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2026 | COT - HCBU - Exterior Clips/Sheathing | Passed | East and west detail 1 page S41 on roof joist connection to CMU BRG wall. North and south detail 2 page S41 ledger connection. 3/19/2026 |
|
| 03/19/2026 | COT - HCBU - Roof Nailing | Passed | ||
| 07/07/2026 | COT - HCBU - Preslab | Passed | 7.7.26 Last small section on north end. |
Scheduled Inspections
Scheduled Inspections - TC-COM-0325-00427
Status: Issued
Description: TI within existing building, expansion into neighboring vacant shell space
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 08/17/2026 | COT - HCBU - Framing | Scheduled |
For information about today’s scheduled inspections please refer to the