Permit: TC-COM-0325-00427
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
6550 S BAY COLONY DR
Address NEW:
6550 S BAY COLONY DR
Apply Date:
03/05/2025
Applicant:
Daniel Gullick
Description:
TI within existing building, expansion into neighboring vacant shell space
Permit Reviews
Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2026 | COMMERCIAL REVIEW - FULL REVISION v.2 | 01/27/2026 | REQUIRES RESUBMIT |
| 02/02/2026 | COMMERCIAL REVIEW - FULL REVISION v.3 | 02/26/2026 | APPROVED |
| 03/06/2025 | COMMERCIAL REVIEW - FULL v.1 | 04/01/2025 | REQUIRES RESUBMIT |
| 04/09/2025 | RESTAMP - COMMERCIAL v.1 | 04/15/2025 | APPROVED |
| 10/23/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/12/2026 | APPROVED |
| 04/02/2025 | COMMERCIAL REVIEW - FULL v.2 | 04/09/2025 | APPROVED |
| 12/02/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 12/23/2025 | REQUIRES RESUBMIT |
| 08/18/2026 | SPECIAL INSPECTION REVIEW v.1 | 08/21/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 04/09/2025 | AIR BALANCING REPORT IS REQUIRED. |
| 04/09/2025 | ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
| 04/09/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
Conditions
Permit Number - TC-COM-0325-00427
Permit Status: Issued
Permit Description: TI within existing building, expansion into neighboring vacant shell space
| Date | Description | Comments |
|---|---|---|
| 04/09/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 02/24/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 04/09/2025 | Elevator Designs must be submitted and approved prior to ... | |
| 04/09/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/09/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 06/05/2026 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 04/09/2025 | Masonry Inspection Report submittal review is required. | |
| 04/09/2025 | Post-Installed Anchor Inspection Report is required. | |
| 03/06/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 03/06/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 04/09/2025 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 03/06/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 04/09/2025 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0325-00427
Permite Description: TI within existing building, expansion into neighboring vacant shell space
Total Outstanding Inspections - 17
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/04/2026 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 3-4-26: reinforcement at elevator shaft approved. North cmu wall top out at 29' 2" & south wall at 28' 8"-okay to grout. |
| 12/16/2025 | COT - HCPL - Rough Soil | N/A | Partial Pass | 12-16-25: underground plumbing at 1st floor restroom & mop sink verified under test. Toilet was relocated to opposite side of what plans show and a revision to the city has been submitted for review. Okay to backfill using shading materials at own risk and continue with construction. |
| 02/11/2026 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 2-11-26: reinforcement at elevator shaft verified per plans and per revision ASI #3, 8/14/25-detail, 11 for masonry pier at elevator shaft. Okay to grout 3rd lift at 13' 4". |
| 06/25/2026 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 6-25-26: partial pass at above ceiling mechanical at new restrooms, janitor room, corridor between G/L; E1/ 10-12.1. Verified restroom fans & pookie at ducts. Okay to insulate remaining round duct at new corridor and restroom. Add supports to flex at 4' intervals and supports writhing 2' of a bend/joint. |
| 07/24/2026 | COT - FCON - Alarm - Final | N/A | Partial Pass | Dewar room is approved. |
| 07/24/2026 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Dewar room is approved. |
| 09/02/2026 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | |
| 08/11/2026 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 8/11/2026 Partial pass. Office east end of elevator in wall approved. |
| 10/08/2026 | COT - HCBU - Building Above Ceiling | N/A | Partial Pass | |
| 10/08/2026 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | |
| 10/08/2026 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | |
| 10/08/2026 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | |
| 10/02/2026 | COT - HCBU - Framing | N/A | Partial Pass | 10/2/26: Framing at elevator 1st and 2nd floor south and north face per approved plans wall type H and H1. |
| 10/22/2026 | COT - HCBU - Building Final | N/A | Partial Pass | 10/22/26: pending conditions & other inspections. |
| 10/22/2026 | COT - HCPL - Plumbing Final | N/A | Partial Pass | 10/22/26: pending water sterilization approval. |
| 07/24/2026 | COT - FCON - Fire - Final | N/A | Partial Pass | Dewar room is approved. OK for TCO level 4 dewar room only. |
| 08/04/2026 | ENGR Engineering Final | N/A | Partial Pass | 8/4/26 All building materials and equipment dumpsters, etc and construction activity are behind fencing. Access to suite 100 is clear for emergency services and to public. Okay to apply for a level 4 TCO. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0325-00427
Permit Description: TI within existing building, expansion into neighboring vacant shell space
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2026 | COT - HCBU - Exterior Clips/Sheathing | Passed | East and west detail 1 page S41 on roof joist connection to CMU BRG wall. North and south detail 2 page S41 ledger connection. 3/19/2026 |
|
| 03/19/2026 | COT - HCBU - Roof Nailing | Passed | ||
| 07/07/2026 | COT - HCBU - Preslab | Passed | 7.7.26 Last small section on north end. |
|
| 10/14/2026 | COT - HCBU - Framing | Passed | 10/14/26: metal framing & drywall screw inspection at 1st floor northeast corner approved. Okay to tape & texture drywall. | |
| 10/22/2026 | COT - HCEL - Electrical Final | Passed | 10/22/26: electrical final approved. | |
| 10/22/2026 | COT - HCME - Mechanical Final | Passed | 10/22/26: mechanical final approved. |