Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 01/15/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
1-15-26: excavation/reinforcement on a total of 4 footers on each side of existing electrical room between grid lines E.1-F.2/ 10.4-12 verified per plans. 2 footers have an RFI and those too were verified per details of #6 @ 5" o.c. Bottom/#5 @9" o.c.top- 18" thick concrete footing & #6 @5" o.c. Bottom/#5 @9" o.c. Top-18" thick concrete footing. Okay for concrete placement at own risk pending city approval. |
| 01/20/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
1/20/2026 Grid lines 12/2 Columns D1. D2. F2. F1. E1. E2. Okay for concrete placement in footings. |
| 02/03/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2-3-26: reinforcement/excavation for slab on grade at extension of warehouse area together with 6 columns at Gridline 13/ D.1-G approved. Okay for concrete placement at progress areas. |
| 02/10/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2-11-26: reinforcement at elevator shaft verified per plans and per revision ASI #3, 8/14/25-detail, 11 for masonry pier at elevator shaft. Okay to grout 3rd lift at 13' 4". |
| 02/12/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2-12-26: reinforcement at elevator shaft walls verified per S2.1 Detail's 8,9,10. Okay to grout 4th lift at 18'. |
| 02/13/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2-13-26: reinforcement at elevator shaft verified per plans-0kay to grout 5th lift @ 22' 8". |
| 02/23/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Canceled |
2/23/2026 canceled per contractor. |
| 02/26/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2/26/26 partial pass for 6th lift |
| 03/03/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Canceled |
3-3-26: canceled by contractor. |
| 03/04/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
3-4-26: reinforcement at elevator shaft approved. North cmu wall top out at 29' 2" & south wall at 28' 8"-okay to grout. |
| 04/16/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
4-16-26: reinforcement for pad from GL/E.1-G/10-13 verified per S1.1/keynote 1. Okay for concrete placement. |
| 12/09/2025 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
12-9-25: reinforcement at elevator pit verified per plans. Okay for concrete placement at progress areas. |