Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2026 | COT - HCBU - Framing | Partial Pass | 3-11-26: framing at second floor elevator shaft verified per details S4.1 #2, S4.2 #4& 6, S3.1 keynotes # 6, 10, 12. Decking nailing at 6 o.c. & 8 in the field. Okay to continue with construction at progress areas. | |
| 03/19/2026 | COT - HCBU - Framing | Partial Pass | East and west detail 1 page S41 on roof joist connection to CMU BRG wall. North and south detail 2 page S41 ledger connection. 3/19/2026 |
|
| 06/05/2026 | COT - HCBU - Framing | Partial Pass | 6-5-26: metal framing for 1st floor Electrical & IDF Room's approved. Okay to add 5/8" drywall (one side electrical room ) and tape & texture interior walls of IDF room at progress areas. Okay to install drywall at the north exterior walls of IDF room but schedule a screw inspection prior to tape & texture. | |
| 06/11/2026 | COT - HCBU - Framing | Partial Pass | 6-11-26: warehouse-framing at door header, Suite 100-soffit areas/in wall framing and partial for one side drywall screw inspection-okay to tape & texture north wall. Framing for IDF/Electrical room approved-okay to drywall progress areas. | |
| 06/25/2026 | COT - HCBU - Framing | Partial Pass | 6-25-26: 1st floor framing along partition/demising wall, men/woman's restroom, janitor's room, and new corridor at G/L: E1-E2/10-12.1 approved. Drywall screw inspection at exterior walls of O2 monitoring room and vestibule approved for tape & texture. | |
| 06/30/2026 | COT - HCBU - Framing | Partial Pass | 6-30-26: verified drywall screws at west edge of slab wall at suite100. In wall Framing along north wall of suite 100 approved-okay to continue with TI and tape/texture progress areas. | |
| 07/01/2026 | COT - HCBU - Framing | Partial Pass | 7-1-26: interior framing for a 15' section at the north side of Suite 100 approved. Section of an approximate 15' wall framing just east of stairs approved. Okay to tape & texture both areas. | |
| 07/07/2026 | COT - HCBU - Framing | Partial Pass | 7.7.26 Progress area 1st floor and 2nd floor drywall and hard lids. |
|
| 07/09/2026 | COT - HCBU - Framing | Partial Pass | 7/9/2026 Partial pass. West wall at concrete edge 2nd floor approved. | |
| 07/22/2026 | COT - HCBU - Framing | Partial Pass | 7/22/2026 Partial pass. 2nd floor north wall framing along with in wall electrical approved at warehouse. 2nd floor north wall framing along with electrical in wall approved at kit ops room. East wall framing along with electrical approved in kit ops room. Pending soffit due to removal of drywall screws and being replaced with proper fasteners. | |
| 07/29/2026 | COT - HCBU - Framing | Partial Pass | 7-29-26: drywall screw inspection at upstairs north, west & east walls of upstairs warehouse approved to tape & texture. Kit ops room drywall screw approved for tape and texture. Framing at east wall of kit ops approved-okay to cover. Framing along south /east , north walls of warehouse approved. Framing/electrical in wall at Utility room furr out around south elevator shaft 1st floor warehouse. In wall rough electrical at all mentioned areas approved. We will verify ground screw and pigtails at each receptacle at upcoming inspection. | |
| 07/31/2026 | COT - HCBU - Framing | Partial Pass | 7-31-26: in wall framing east of electrical room at upstairs warehouse together with drywall screws at east wall of kit ops approved. Okay to cover and tape/texture progress areas. | |
| 08/05/2026 | COT - HCBU - Framing | Not Ready | 8/5/2026 drywall inspection. Not ready. Screws shall be no closer than 3/8" from edges and shall not tare through paper. Ensure all screws are flushed. | |
| 08/05/2026 | COT - HCBU - Framing | Partial Pass | 1st floor north and east perimeter wall. West and east walls of elevator. Approved for drywall screw inspection. Okay to proceed all progress areas. 8/5/2026 | |
| 08/11/2026 | COT - HCBU - Framing | Partial Pass | 8/11/2026 Partial pass 2nd floor west wall of clean room. East and west end walls of elevator. Outside of electrical room walls all approved for drywall screws. KITOPS drywall screw inspection at ceiling approved. |
|
| 08/17/2026 | COT - HCBU - Framing | Partial Pass | 8.17.26 Northside stairwell and clean room |
|
| COT - HCBU - Framing | Scheduled |