Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/15/2026 | COT - HCBU - Preslab | Partial Pass | 1-15-26: excavation/reinforcement/pre slab on a total of 4 footers on each side of existing electrical room between grid lines E.1-F.2/ 10.4-12 verified per plans. 2 footers have an RFI and those too were verified per details of #6 @ 5" o.c. Bottom/#5 @9" o.c.top- 18" thick concrete footing & #6 @5" o.c. Bottom/#5 @9" o.c. Top-18" thick concrete footing. Okay for concrete placement at own risk pending city approval. | |
| 01/20/2026 | COT - HCBU - Preslab | Partial Pass | 1/20/2026 Grid lines 12/2 Columns D1. D2. F2. F1. E1. E2. Okay for concrete placement in footings. | |
| 02/03/2026 | COT - HCBU - Preslab | Partial Pass | 2-3-26: reinforcement/excavation for slab on grade at extension of warehouse area together with 6 columns at Gridline 13/ D.1-G approved. Okay for concrete placement at progress areas. | |
| 02/25/2026 | COT - HCBU - Preslab | Partial Pass | 2-25-26: excavation /reinforcement/preslab for 8 column footings many with RFI's verified per plans/details. Column 12/1 F3, column 12/2 F3, 10/2 F3, 10/2 F2, 10/3 F3, 11 F3, 11/1 F3, 12/1 F3, 12/2 (12/1 & 12/2 F3 will be a 2 step pour), D1-F1 slab on grade & RFI 31 (footing). Okay for concrete placement at inspected areas. | |
| 03/27/2026 | COT - HCBU - Preslab | Partial Pass | 3-27-26: reinforcement for 9 footings verified per S1.1 details F3 & F2/C1 together with 2 column pours @ GL-E1-F3/ 10-13. Okay for concrete placement. | |
| 06/17/2026 | COT - HCBU - Preslab | Re-inspection required | 6-17-26: preslab- second floor decking-add wire mesh at all edges, tie off rebar around columns/corners and add chairs throughout. | |
| 06/18/2026 | COT - HCBU - Preslab | Partial Pass | 6-18-26: reinforcement/preslab for second level decking approved. Okay for concrete placement. | |
| 07/07/2026 | COT - HCBU - Preslab | Passed | 7.7.26 Last small section on north end. |
|
| 10/24/2025 | COT - HCBU - Preslab | Partial Pass | Partial pass; Elevator pit, interior footings. Okay to pour in progress areas. | |
| 12/15/2025 | COT - HCBU - Preslab | Partial Pass | 12-15-25: reinforcement at elevator pit walls verified per detail 8, 7/S2.1... Okay for concrete placement at progress areas. |