Permit: TC-COM-0325-00427

Parcel: 140420760

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Preslab  

Date Description Inspector Results Comments
01/15/2026 COT - HCBU - Preslab   Partial Pass 1-15-26: excavation/reinforcement/pre slab on a total of 4 footers on each side of existing electrical room between grid lines E.1-F.2/ 10.4-12 verified per plans. 2 footers have an RFI and those too were verified per details of #6 @ 5" o.c. Bottom/#5 @9" o.c.top- 18" thick concrete footing & #6 @5" o.c. Bottom/#5 @9" o.c. Top-18" thick concrete footing. Okay for concrete placement at own risk pending city approval.
01/20/2026 COT - HCBU - Preslab   Partial Pass 1/20/2026 Grid lines 12/2 Columns D1. D2. F2. F1. E1. E2. Okay for concrete placement in footings.
02/03/2026 COT - HCBU - Preslab   Partial Pass 2-3-26: reinforcement/excavation for slab on grade at extension of warehouse area together with 6 columns at Gridline 13/ D.1-G approved. Okay for concrete placement at progress areas.
02/25/2026 COT - HCBU - Preslab   Partial Pass 2-25-26: excavation /reinforcement/preslab for 8 column footings many with RFI's verified per plans/details. Column 12/1 F3, column 12/2 F3, 10/2 F3, 10/2 F2, 10/3 F3, 11 F3, 11/1 F3, 12/1 F3, 12/2 (12/1 & 12/2 F3 will be a 2 step pour), D1-F1 slab on grade & RFI 31 (footing). Okay for concrete placement at inspected areas.
03/27/2026 COT - HCBU - Preslab   Partial Pass 3-27-26: reinforcement for 9 footings verified per S1.1 details F3 & F2/C1 together with 2 column pours @ GL-E1-F3/ 10-13. Okay for concrete placement.
06/17/2026 COT - HCBU - Preslab   Re-inspection required 6-17-26: preslab- second floor decking-add wire mesh at all edges, tie off rebar around columns/corners and add chairs throughout.
06/18/2026 COT - HCBU - Preslab   Partial Pass 6-18-26: reinforcement/preslab for second level decking approved. Okay for concrete placement.
07/07/2026 COT - HCBU - Preslab   Passed 7.7.26
Last small section on north end.
10/24/2025 COT - HCBU - Preslab   Partial Pass Partial pass; Elevator pit, interior footings. Okay to pour in progress areas.
12/15/2025 COT - HCBU - Preslab   Partial Pass 12-15-25: reinforcement at elevator pit walls verified per detail 8, 7/S2.1... Okay for concrete placement at progress areas.