Inspection Status: Canceled
Inspection History: COT - HCPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 01/21/2026 |
COT - HCPL - Rough Soil |
|
Canceled |
1-21-26: cancelled by contractor. |
| 04/08/2026 |
COT - HCPL - Rough Soil |
|
Partial Pass |
4-8-26: verified 4" underground plumbing to column which will extend up to 2nd floor at G/L: 12/ E-E.2...10' stack verified under test- okay to backfill progress areas using shading materials. |
| 12/16/2025 |
COT - HCPL - Rough Soil |
|
Partial Pass |
12-16-25: underground plumbing at 1st floor restroom & mop sink verified under test. Toilet was relocated to opposite side of what plans show and a revision to the city has been submitted for review. Okay to backfill using shading materials at own risk and continue with construction. |