Permit: T22CM06674
Permit Details
Apply Date:
08/29/2022
Applicant:
Andrew Suby
Description:
This project consists of replacing the main lab located on the basement and first floors of the exis
Permit Reviews
Permit Number - T22CM06674
Permit Status: Inspections complete
Permit Description: This project consists of replacing the main lab located on the basement and first floors of the exis
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/29/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/03/2022 | COMPLETED |
10/18/2022 | RESUBMITTAL | 10/18/2022 | ACTIVE |
06/13/2024 | COMMERCIAL REVIEW - FULL v.1 | 07/16/2024 | APPROVED |
03/18/2024 | COMMERCIAL REVIEW - FULL v.1 | 04/18/2024 | REQUIRES RESUBMIT |
10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/01/2022 | REQUIRES RESUBMIT |
01/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/05/2024 | REQUIRES RESUBMIT |
12/26/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/27/2023 | APPROVED |
11/07/2023 | RESTAMP - COMMERCIAL v.1 | 11/07/2023 | APPROVED |
11/02/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/07/2023 | APPROVED |
11/25/2022 | COMMERCIAL REVIEW - FULL v.2 | 01/04/2023 | APPROVED |
08/31/2023 | COMMERCIAL REVIEW - FULL v.1 | 10/03/2023 | REQUIRES RESUBMIT |
10/09/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/09/2024 | REQUIRES RESUBMIT |
04/30/2024 | RESTAMP - COMMERCIAL v.1 | 05/01/2024 | APPROVED |
04/26/2024 | COMMERCIAL REVIEW - FULL v.2 | 04/30/2024 | APPROVED |
10/24/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 10/28/2024 | APPROVED |
Conditions
Permit Number - T22CM06674
Permit Status: Inspections complete
Permit Description: This project consists of replacing the main lab located on the basement and first floors of the exis
Date | Description | Comments |
---|---|---|
12/08/2022 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
05/15/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
10/28/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
10/28/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
05/15/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
10/28/2024 | FIREPROOFING THICKNESS INSPECTION | |
10/28/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
10/28/2024 | SPECIAL INSPECTION FOR STEEL FRAMES IS REQUIRED. | |
12/08/2022 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: T22CM06674
Permite Description: This project consists of replacing the main lab located on the basement and first floors of the exis
Total Outstanding Inspections - 20
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/21/2023 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | partial approval for curb attachments and 3rd party for curb anchors |
12/18/2023 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Approved tower 4 only. |
12/20/2023 | COT - FCON - Alarm - Final | N/A | Not Ready | |
05/31/2023 | COT - HCME - Mechanical Progress | N/A | Partial Pass | partial approval for supply air shaft to first floor from AH009 IN BASEMENT and relief duct, and outside air duct to air intake, ok to insulate |
08/31/2023 | COT - HCBU - Framing | N/A | Partial Pass | Tower 4, Rooms 14513, 14518, 14539. |
12/14/2023 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | Area C. All MEP’S above ceiling approved. EVS ROOM #14550. Tower 4 Area B MEP’S all above ceiling approved. #14518 AREA B (GLASS WASHROOM) MEP’S all above ceiling approved. 12/14/2023 |
11/30/2023 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | 10/18/23 preamp room 14513 ok to drywall ceiling 10/25/23: hydro pressure test at 150psi at HHW and CHW to AHU 009 Basement Tower 4. Ok to insulate 11/13/23: Above ceiling hydronic pipe Tower 3 Area A, HHW piped to VAV's throughout Tower 3 Area A(Pressure Test), CHW pipe to FCU's to IDF room and Freezer room Tower 3 Area A (Pressure Test). 11/15/23 duct pressure test tower 3 as reflected on attached photos this date 11/30/23: mechanical above ceiling in Area B passed (south of passage 13572S), pending Rooms 14518 and storage |
12/26/2023 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | Electric intermediate for Area C is completed. |
11/30/2023 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | 9/13/23: compressed air in tower 3 to exterior yard. Tested at 150 PSI 11/30/23: plumbing above ceiling in Area B passed (south of passage 13572S), pending Rooms 14518 and storage |
07/16/2024 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | Sinks and eye wash stations in Lab #13571. |
09/06/2023 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 8/24/23 - Partial approvals for 1st floor Tower 4 - rooms 14505, 14506, 14550, 14511, 14512, double doors at corridor 14554E, labs storage, mens and woman's restrooms * this completes framing at Tower 4 9/6/23: Tower 4- level 1- area B. CO2 tested at 150 psi. Compressed air tested at 150 psi. Domestic water tested at 120 psi. All areas tested and approved were high-lighted on page P301B. |
01/18/2024 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | |
08/31/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Canceled | |
05/03/2024 | COT - HCBU - Building Above Ceiling | N/A | Not Ready | |
12/21/2023 | COT - HCEL - Electrical Final | N/A | Partial Pass | Partial pass. Tower 4 approved. 12/21/2023 |
12/27/2023 | COT - HCME - Mechanical Final | N/A | Partial Pass | Partial Final Tower 4 - Area B and C |
12/27/2023 | COT - HCPL - Plumbing Final | N/A | Partial Pass | Partial Final Tower 4 - Area B and C Pending 14518 glass wash room (furniture tie in) 12/27/2023 |
10/14/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | ok for tco per tucson fire. still need to walk and check exit signs. |
12/29/2023 | COT - HCBU - Building Final | N/A | Partial Pass | Partial Final for TCO level 4 - For Tower 4 Area B and C of Project. 12/29/2023 |
12/29/2023 | COT - HCBU - Building Progress | N/A | Partial Pass | Partial Final for TCO level 4 - For Tower 4 Area B and C of Project. 12/29/2023 |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: T22CM06674
Permit Description: This project consists of replacing the main lab located on the basement and first floors of the exis
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/25/2023 | FCON – Fire – Intermediate | Passed | ||
09/09/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
09/18/2023 | COT - HCEL - Electrical Progress | Passed | ||
12/27/2023 | COT - FCON - Alarm - Final | Passed | ||
01/17/2024 | COT - HCME - Mechanical Progress | Passed | ||
03/21/2024 | COT - HCEL - Electrical Above Ceiling | Passed | Tower #3, Area A; circuits for lab furniture to be dropped when furniture is installed. | |
08/06/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | DI water lines and compressed air lines as per RFI #180 and #207. | |
08/06/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
08/06/2024 | COT - HCPL - Plumbing Progress | Passed | DI water lines and compressed air lines as per RFI #180 and #207. | |
10/10/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
10/10/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
10/10/2024 | COT - HCBU - Building Above Ceiling | Passed | Ok to set remaining ceiling tiles. | |
10/15/2024 | COT - HCEL - Electrical Final | Passed | ||
10/15/2024 | COT - HCPL - Rough Soil | Passed | ||
10/15/2024 | COT - HCME - Mechanical Final | Passed | ||
10/15/2024 | COT - HCPL - Plumbing Final | Passed | ||
11/07/2024 | COT - FCON - Fire - Final | Passed | ||
11/08/2024 | COT - HCBU - Building Final | Passed | signage to be completed by Banner | |
11/08/2024 | COT - HCBU - Building Progress | Passed |