Permit: T22CM06674

Parcel: 123100280


Addresses:

1625 N CAMPBELL AV

Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Progress 

Date Description Inspector Results Comments
04/27/2023 COT - HCPL - Plumbing Progress  Partial Pass in wall plumbing for sink five and sink six ok to cover
06/05/2024 COT - HCPL - Plumbing Progress  Partial Pass
08/06/2024 COT - HCPL - Plumbing Progress  Passed DI water lines and compressed air lines as per RFI #180 and #207.
08/22/2023 COT - HCPL - Plumbing Progress  Partial Pass
08/24/2023 COT - HCPL - Plumbing Progress  Partial Pass Partial approvals for 1st floor Tower 4 - rooms 14505, 14506, 14550, 14511, 14512, double doors at corridor 14554E, labs storage, mens and woman's restrooms * this completes framing at Tower 4
09/06/2023 COT - HCPL - Plumbing Progress  Partial Pass 8/24/23 - Partial approvals for 1st floor Tower 4 - rooms 14505, 14506, 14550, 14511, 14512, double doors at corridor 14554E, labs storage, mens and woman's restrooms * this completes framing at Tower 4
9/6/23: Tower 4- level 1- area B. CO2 tested at 150 psi. Compressed air tested at 150 psi. Domestic water tested at 120 psi. All areas tested and approved were high-lighted on page P301B.
09/26/2023 COT - HCPL - Plumbing Progress  Partial Pass 9/25/23 DWV SEE ATTACHED DRWG
10/12/2023 COT - HCPL - Plumbing Progress  Partial Pass see photos in attachments dated 10/12/23
11/02/2023 COT - HCPL - Plumbing Progress  Partial Pass 11/2/23 DWV basement see attached drawing photo this date
12/05/2023 COT - HCPL - Plumbing Progress  Partial Pass 12/5/23 potable water above ceiling see photo
12/18/2023 COT - HCPL - Plumbing Progress  Partial Pass 12/18/23 DWV slab on grade waste line area tower three from area penetrating basement to south side coring operation, ok to cover