Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
Permit Number - T22CM06674
Inspection Description - COT - HCPL - Plumbing Progress
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/27/2023 | COT - HCPL - Plumbing Progress | Partial Pass | in wall plumbing for sink five and sink six ok to cover | |
06/05/2024 | COT - HCPL - Plumbing Progress | Partial Pass | ||
08/06/2024 | COT - HCPL - Plumbing Progress | Passed | DI water lines and compressed air lines as per RFI #180 and #207. | |
08/22/2023 | COT - HCPL - Plumbing Progress | Partial Pass | ||
08/24/2023 | COT - HCPL - Plumbing Progress | Partial Pass | Partial approvals for 1st floor Tower 4 - rooms 14505, 14506, 14550, 14511, 14512, double doors at corridor 14554E, labs storage, mens and woman's restrooms * this completes framing at Tower 4 | |
09/06/2023 | COT - HCPL - Plumbing Progress | Partial Pass | 8/24/23 - Partial approvals for 1st floor Tower 4 - rooms 14505, 14506, 14550, 14511, 14512, double doors at corridor 14554E, labs storage, mens and woman's restrooms * this completes framing at Tower 4 9/6/23: Tower 4- level 1- area B. CO2 tested at 150 psi. Compressed air tested at 150 psi. Domestic water tested at 120 psi. All areas tested and approved were high-lighted on page P301B. |
|
09/26/2023 | COT - HCPL - Plumbing Progress | Partial Pass | 9/25/23 DWV SEE ATTACHED DRWG | |
10/12/2023 | COT - HCPL - Plumbing Progress | Partial Pass | see photos in attachments dated 10/12/23 | |
11/02/2023 | COT - HCPL - Plumbing Progress | Partial Pass | 11/2/23 DWV basement see attached drawing photo this date | |
12/05/2023 | COT - HCPL - Plumbing Progress | Partial Pass | 12/5/23 potable water above ceiling see photo | |
12/18/2023 | COT - HCPL - Plumbing Progress | Partial Pass | 12/18/23 DWV slab on grade waste line area tower three from area penetrating basement to south side coring operation, ok to cover |