Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Firewall/Fire Barrier/Firestop
Permit Number - T22CM06674
Inspection Description - COT - HCBU - Firewall/Fire Barrier/Firestop
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/27/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | corridor 1359N not ready, 5 penetrations on east wall need caulking ok to proceed with insulation and drywall | |
05/01/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | ||
05/02/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | partial approval for area B south and east wall 2hr perimeter wall and area A from sweat chloride room east to expansion joint | |
05/03/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | ||
05/06/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Area A interior walls, penetrations have been Fire caulked. | |
05/15/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 5-15-24: Tower three. | |
05/17/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | ||
05/22/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | screw inspection, from elevator shaft to north east corner tower 4, and framing for tower three elevator shaft ceiling close out. | |
08/14/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | ||
08/31/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Canceled | ||
09/13/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 5-15-24: Tower three. 8/14/23 Tower 4 partial approval framing on fire rated walls north, east and west 1 and 2 hr walls tape and caulking to go. 9/13/23: fire blanket rated 90 minutes installed at level 1 & 2 . |
|
10/10/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
11/15/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Tower #4. 2 hour rated walls Fire caulking | |
COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 5-15-24: Tower three. 8/14/23 Tower 4 partial approval framing on fire rated walls north, east and west 1 and 2 hr walls tape and caulking to go. 9/13/23: fire blanket rated 90 minutes installed at level 1 & 2 . 11/30/23: Area C shaft walls 1hr fire rated walls complete. Tower 4 |
||
12/14/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Area C. All MEP’S above ceiling approved. EVS ROOM #14550. Tower 4 Area B MEP’S all above ceiling approved. #14518 AREA B (GLASS WASHROOM) MEP’S all above ceiling approved. 12/14/2023 |