Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM06674

Parcel: 123100280


Addresses:

1625 N CAMPBELL AV


Inspection Status: Passed

Inspection History: COT - HCME - Mechanical Progress 

Permit Number - T22CM06674

Inspection Description - COT - HCME - Mechanical Progress 

Inspection Status - Passed

Date Description Inspector Results Comments
01/17/2024 COT - HCME - Mechanical Progress  Passed
05/31/2023 COT - HCME - Mechanical Progress  Partial Pass partial approval for supply air shaft to first floor from AH009 IN BASEMENT and relief duct, and outside air duct to air intake, ok to insulate
08/17/2023 COT - HCME - Mechanical Progress  Partial Pass see attachments dated 8/17/23
08/28/2023 COT - HCME - Mechanical Progress  Partial Pass see attachment
09/28/2023 COT - HCME - Mechanical Progress  Partial Pass see attached exhaust duct leak check
11/01/2023 COT - HCME - Mechanical Progress  Partial Pass Inspection for VAV circuit lines, area, one and venting, as reflected on drawings
12/01/2023 COT - HCME - Mechanical Progress  Partial Pass All HVAC for area C. Okay to proceed progress areas. 12/1/2023
12/11/2023 COT - HCME - Mechanical Progress  Partial Pass Visual inspection of low pressure duct work to VAV 211 (1-10) Tower 3. Area A.
Visual inspection low roof ductwork to ERU 201-202 (Supply) (okay to insulate)
Visual inspection low roof return ductwork to AHU 211. (Okay to insulate) 12/11/2023
12/21/2023 COT - HCME - Mechanical Progress  Canceled Canceled per contractor. 12/21/2023