Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCME - Mechanical Progress
Permit Number - T22CM06674
Inspection Description - COT - HCME - Mechanical Progress
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/17/2024 | COT - HCME - Mechanical Progress | Passed | ||
05/31/2023 | COT - HCME - Mechanical Progress | Partial Pass | partial approval for supply air shaft to first floor from AH009 IN BASEMENT and relief duct, and outside air duct to air intake, ok to insulate | |
08/17/2023 | COT - HCME - Mechanical Progress | Partial Pass | see attachments dated 8/17/23 | |
08/28/2023 | COT - HCME - Mechanical Progress | Partial Pass | see attachment | |
09/28/2023 | COT - HCME - Mechanical Progress | Partial Pass | see attached exhaust duct leak check | |
11/01/2023 | COT - HCME - Mechanical Progress | Partial Pass | Inspection for VAV circuit lines, area, one and venting, as reflected on drawings | |
12/01/2023 | COT - HCME - Mechanical Progress | Partial Pass | All HVAC for area C. Okay to proceed progress areas. 12/1/2023 | |
12/11/2023 | COT - HCME - Mechanical Progress | Partial Pass | Visual inspection of low pressure duct work to VAV 211 (1-10) Tower 3. Area A. Visual inspection low roof ductwork to ERU 201-202 (Supply) (okay to insulate) Visual inspection low roof return ductwork to AHU 211. (Okay to insulate) 12/11/2023 |
|
12/21/2023 | COT - HCME - Mechanical Progress | Canceled | Canceled per contractor. 12/21/2023 |