Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
Permit Number - T22CM06674
Inspection Description - COT - HCBU - Framing
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/22/2024 | COT - HCBU - Framing | Partial Pass | 10/19/23 pre amp room 14513 hard lid framing ok for drywall 11/2/23 drywall first and second layer and framing for hard lid as reflected in attached photos this date 11/9/2023 area C tower 4. Reflecting on highlighted areas on photos. Okay to proceed progress areas. 11/22/23 partial for area C framing in offices and corridor walls, ok to 2 side in offices only 11/30/23: Area C tower 4 framing per plan ok to cover. 12/20/2023 Tower 3 area A All of North wall. Area A all of West wall Soffit Two doors IDF #13593 #13594 1/22/24: All area A complete pending corridor 13594N |
|
04/27/2023 | COT - HCBU - Framing | Partial Pass | partial approval for two hr perimeter wall ok to drywall | |
05/15/2023 | COT - HCBU - Framing | Partial Pass | 5-15-23: Infill of duct openings. | |
05/22/2023 | COT - HCBU - Framing | Partial Pass | for small ceiling area at shaft tower three | |
08/04/2023 | COT - HCBU - Framing | Partial Pass | ||
08/24/2023 | COT - HCBU - Framing | Partial Pass | Partial approvals for 1st floor Tower 4 - rooms 14505, 14506, 14550, 14511, 14512, double doors at corridor 14554E, labs storage, mens and woman's restrooms * this completes framing at Tower 4 | |
08/31/2023 | COT - HCBU - Framing | Partial Pass | Tower 4, Rooms 14513, 14518, 14539. | |
09/18/2023 | COT - HCBU - Framing | Passed | ||
10/19/2023 | COT - HCBU - Framing | Partial Pass | 10/19/23 pre amp room 14513 hard lid framing ok for drywall | |
10/31/2023 | COT - HCBU - Framing | Partial Pass | 10/31/23 Framing inspection as indicated on attached photo | |
11/02/2023 | COT - HCBU - Framing | Partial Pass | 11/2/23 drywall first and second layer and framing for hard lid as reflected in attached photos this date | |
11/09/2023 | COT - HCBU - Framing | Partial Pass | 11/9/2023 area C tower 4. Reflecting on highlighted areas on photos. Okay to proceed progress areas. | |
11/15/2023 | COT - HCBU - Framing | Partial Pass | see photo | |
11/22/2023 | COT - HCBU - Framing | Partial Pass | 11/22/23 partial for area C framing in offices and corridor walls, ok to 2 side in offices only | |
11/30/2023 | COT - HCBU - Framing | Partial Pass | 10/19/23 pre amp room 14513 hard lid framing ok for drywall 11/2/23 drywall first and second layer and framing for hard lid as reflected in attached photos this date 11/9/2023 area C tower 4. Reflecting on highlighted areas on photos. Okay to proceed progress areas. 11/22/23 partial for area C framing in offices and corridor walls, ok to 2 side in offices only 11/30/23: Area C tower 4 framing per plan ok to cover. |
|
12/20/2023 | COT - HCBU - Framing | Partial Pass | Tower 3 area A All of North wall. Area A all of West wall Soffit Two doors IDF #13593 #13594 |