Permit: T22CM06674

Parcel: 123100280


Addresses:

1625 N CAMPBELL AV

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Date Description Inspector Results Comments
01/22/2024 COT - HCBU - Framing Partial Pass 10/19/23 pre amp room 14513 hard lid framing ok for drywall
11/2/23 drywall first and second layer and framing for hard lid as reflected in attached photos this date

11/9/2023 area C tower 4. Reflecting on highlighted areas on photos. Okay to proceed progress areas.
11/22/23 partial for area C framing in offices and corridor walls, ok to 2 side in offices only
11/30/23: Area C tower 4 framing per plan ok to cover.
12/20/2023 Tower 3 area A
All of North wall.
Area A all of West wall Soffit
Two doors IDF #13593
#13594
1/22/24: All area A complete pending corridor 13594N
04/27/2023 COT - HCBU - Framing Partial Pass partial approval for two hr perimeter wall ok to drywall
05/15/2023 COT - HCBU - Framing Partial Pass 5-15-23: Infill of duct openings.
05/22/2023 COT - HCBU - Framing Partial Pass for small ceiling area at shaft tower three
08/04/2023 COT - HCBU - Framing Partial Pass
08/24/2023 COT - HCBU - Framing Partial Pass Partial approvals for 1st floor Tower 4 - rooms 14505, 14506, 14550, 14511, 14512, double doors at corridor 14554E, labs storage, mens and woman's restrooms * this completes framing at Tower 4
08/31/2023 COT - HCBU - Framing Partial Pass Tower 4, Rooms 14513, 14518, 14539.
09/18/2023 COT - HCBU - Framing Passed
10/19/2023 COT - HCBU - Framing Partial Pass 10/19/23 pre amp room 14513 hard lid framing ok for drywall
10/31/2023 COT - HCBU - Framing Partial Pass 10/31/23 Framing inspection as indicated on attached photo
11/02/2023 COT - HCBU - Framing Partial Pass 11/2/23 drywall first and second layer and framing for hard lid as reflected in attached photos this date
11/09/2023 COT - HCBU - Framing Partial Pass 11/9/2023 area C tower 4. Reflecting on highlighted areas on photos. Okay to proceed progress areas.
11/15/2023 COT - HCBU - Framing Partial Pass see photo
11/22/2023 COT - HCBU - Framing Partial Pass 11/22/23 partial for area C framing in offices and corridor walls, ok to 2 side in offices only
11/30/2023 COT - HCBU - Framing Partial Pass 10/19/23 pre amp room 14513 hard lid framing ok for drywall
11/2/23 drywall first and second layer and framing for hard lid as reflected in attached photos this date

11/9/2023 area C tower 4. Reflecting on highlighted areas on photos. Okay to proceed progress areas.
11/22/23 partial for area C framing in offices and corridor walls, ok to 2 side in offices only
11/30/23: Area C tower 4 framing per plan ok to cover.
12/20/2023 COT - HCBU - Framing Partial Pass Tower 3 area A
All of North wall.
Area A all of West wall Soffit

Two doors IDF #13593
#13594