Permit: T22CM02751
Permit Details
Apply Date:
04/14/2022
Applicant:
Description:
TI for Hospital
Permit Reviews
Permit Number - T22CM02751
Permit Status: Issued
Permit Description: TI for Hospital
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/14/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 05/17/2022 | COMPLETED |
06/24/2022 | RESUBMITTAL | 08/08/2022 | COMPLETED |
08/17/2022 | RESUBMITTAL | 08/29/2022 | COMPLETED |
10/12/2022 | REVISION - - 1ST | 10/12/2022 | ACTIVE |
01/02/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/03/2024 | APPROVED |
01/25/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 01/25/2024 | REQUIRES RESUBMIT |
01/29/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.4 | 01/29/2024 | REQUIRES RESUBMIT |
02/16/2023 | COMMERCIAL REVIEW - FULL v.3 | 03/14/2023 | APPROVED |
07/16/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.5 | 07/16/2024 | APPROVED |
12/12/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/14/2023 | APPROVED |
10/27/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/21/2022 | REQUIRES RESUBMIT |
01/09/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/11/2024 | REQUIRES RESUBMIT |
12/19/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/20/2023 | APPROVED |
02/16/2023 | COMMERCIAL REVIEW - FULL v.2 | 02/16/2023 | REQUIRES RESUBMIT |
01/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 01/22/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - T22CM02751
Permit Status: Issued
Permit Description: TI for Hospital
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
08/27/2024 | SHOP DRAWINGS REQUIRED FOR FIRE ALARM. |
08/27/2024 | SHOP DRAWINGS REQUIRED FOR RADIO COVERAGE. |
08/27/2024 | SHOP DRAWINGS REQUIRED FOR SPRINKLERS. |
08/27/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
08/27/2024 | SPECIAL INSPECTION IS REQUIRED FOR STRUCTURAL. |
Conditions
Permit Number - T22CM02751
Permit Status: Issued
Permit Description: TI for Hospital
Date | Description | Comments |
---|---|---|
08/27/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
08/27/2022 | SPECIAL INSPECTION FOR MEDICAL GASES IS REQUIRED. | |
08/27/2022 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
08/27/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
08/27/2022 | SHOP DRAWINGS REQUIRED FOR ELEVATOR. | |
08/27/2022 | SHOP DRAWINGS REQUIRED FOR COOLER. | |
08/27/2022 | SHOP DRAWINGS REQUIRED FOR SEISMIC BRACKING. | |
08/29/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required | |
01/11/2024 | ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM02751
Permite Description: TI for Hospital
Total Outstanding Inspections - 13
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
COT - FCON - Underground Pressure | N/A | Not Ready | Need plans and permit for the fire line | |
COT - FCON - Underground Flush | N/A | Not Ready | Need plans and permit for the fire line. | |
10/24/2023 | COT - HCBU - Building Above Ceiling | N/A | Partial Pass | 10/24/23: above ceiling firewall/fireblock sealing all penetrations in rooms 10705C,10705D,10705E |
10/13/2023 | COT - HCBU - Building Progress | N/A | Partial Pass | Building above ceiling on Level #2 corridors. |
10/31/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Partial Pass | Elevators (West) on levels #2 & #3. Ok to apply final layer of Sheetrock. |
08/02/2023 | COT - HCEL - Electrical Progress | N/A | Not Ready | Contractor cancelled |
10/26/2022 | FCON – OH Piping & Hydro | N/A | Partial Pass | 1a and 1b complete 200 lb for two hours no leaks. |
10/26/2022 | COT - FCON - Hood System - Final | N/A | Not Ready | |
10/26/2022 | COT - HCPL - Plumbing Final | N/A | Not Ready | |
12/21/2023 | COT - FCON - Alarm - Final | N/A | Partial Pass | Tested all flows and tampers. Tested all doors they all closed upon activation on fire alarm. Tested all horns and strobes on all floors. |
COT - FCON - Fire - Final | N/A | Not Ready | still need to finish testing fire alarm and preaction sprinklers. | |
12/21/2023 | COT - HCEL - Electrical Final | N/A | Partial Pass | Test of the emergency lighting system, interior and exterior. Emergency generators responded as required. |
01/26/2024 | SITE - Zoning Final | N/A | Not Applicable |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM02751
Permit Description: TI for Hospital
Total Completed Inspections - 41
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - HCBU - Sustainability | Passed | N/A | |
10/26/2022 | COT - HCPL - Backwater Valve | Passed | See permit number T22CM00621 | |
10/26/2022 | COT - HCPL - Medical Gas Preconstruction Mtg | Passed | See permit number T22CM00621 | |
10/26/2022 | COT - HCPL - Sewer | Passed | See permit number T22CM00621 | |
10/26/2022 | COT - HCPL - Rough Soil | Passed | See permit number T22CM00621 | |
10/26/2022 | COT - HCBU - Roof Nailing | Passed | See permit number T22CM00621 | |
10/26/2022 | COT - HCPL - Gas Reconnect | Passed | See permit number T22CM00621 | |
10/26/2022 | COT - HCBU - Interior Shear Bracing | Passed | See permit number T22CM00621 | |
12/28/2022 | COT - HCPL - Plumbing Progress | Passed | Domestic water lines at 3/4” - 1 1/2” in rooms 10115, 10100L. Domestic water vent lines in Area B North at GL; B - D/ 8 - 12.5 | |
02/02/2023 | COT - FCON - Underground Pressure | Passed | ||
02/02/2023 | COT - FCON - Underground Flush | Passed | ||
05/16/2023 | COT - HCPL - Plumbing Intermediate | Passed | Domestic waste and vent lines at 1 1/2” - 4” lines in North portion of area C - D See permit number T22CM00621 | |
06/02/2023 | COT - HCPL - Plumbing Roof Drains | Passed | Contractor cancelled. | |
06/27/2023 | BULD - Electrical Clearance | Passed | Level #1, South electric rooms; panel boards and transformers at Room 10505: P1D-HEB1, P1D-HNB1, P1D-LCB1, P1D-LCB2, P1D-LEB1, P1D-LCB2, P1D-LEB1, P1D-LLS1, P1D-LNB1, P1D-LNB2, P1D-LNB3, P1D-LNB4, DP1D-LCB1, DP1D-LNB1, DP1DHNB1, TX1D-CB1, TX1D-EB1, TX1D-LS1, TX1D-NB1. Room 10501; P1OR1-LBC1, Room 10502, P1OR2-LBC1. See permit number T22CM00621 | |
07/21/2023 | COT - BULD - SWG Clearance | Passed | Request meter sets (2) for natural gas service and propane service at North side of building, Request meter set for natural gas service at kitchen area of South side of building. | |
07/21/2023 | COT - HCPL - Gas Pressure Test | Passed | Request meter sets for North side of building for natural gas and propane service for CUP area (2 meters required). Request meter set for South side building for kitchen areas | |
07/27/2023 | COT - HCEL - Electrical Underground | Passed | Doctors’ entry gate at Southwest area of building: 4 each 3/4” conduits, 1 each 2” conduit, 2 each spare conduits. Pk to cover progress areas. See permit number T22CM00621 | |
08/03/2023 | COT - HCME - Mechanical Progress | Passed | Kitchen hood; grease interceptors (3) in place. Ok to wrap remaining duct work. See permit number T22CM00621 | |
08/03/2023 | COT - HCME - Mechanical Intermediate | Passed | Hydronic chilled water system pressure tested at 100 psi, for levels #1 - #4. See permit number T22CM00621 | |
08/03/2023 | COT - HCME - Kitchen Hood | Passed | Three grease interceptors on kitchen hood. Ok to complete duct wrap. See permit number T22CM00621 | |
08/07/2023 | COT - HCBU - Framing | Passed | South portion of structure, columns are framed with metal studs. Ok to cover progress areas. Patient rooms on Level #3, North side of level have been edge Fire caulked. `Level #3 East shaft has been Fire caulked. See permit number T22CM00621 | |
09/15/2023 | COT - HCBU - Preslab | Passed | Loading dock area and South ramp. Ok to place concrete in progress areas. | |
11/09/2023 | COT - HCEL - Electrical Above Ceiling | Passed | Level #2 corridors: 20200, 20200G, 20200C, 20100, 20100M, 20100A, 20100H, 20100D, 20200A, 20118, 20117, 20132. West elevators on levels,#2 & #3 | |
11/09/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | Level #2 corridors: 200200, 20200G, 20200C, 20100, 20100M, 20100A, 20100H, 20100D, 20200A, 20118, 20117, 20132. Elevators “B” at levels #2 & #3 | |
07/16/2024 | COT - HCBU - Building Above Ceiling | Passed | See permit number T22CM00621 | |
07/16/2024 | COT - HCBU - Building Progress | Passed | ||
11/22/2023 | COT - HCME - Mechanical Above Ceiling | Passed | Inspection is for Building above ceiling wall penetrations; 40208A, 40208, 40118, 40117, 40116, 40112, 40132, 40111, 40114; corridors and alcoves: 40100, 40100A< 40100B, 40100C, 40100D, 40100E, 40100K, 40100J, 40200. See permit number T22CM00621 | |
11/29/2023 | COT - HCEL - Electrical Intermediate | Passed | Levels #1 and #4 soffits and in wall electric at elevator areas. Ok to cover progress areas. | |
11/30/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | Fire riser lines on level #4 in East and West stairwells. See permit number T22CM00621 Electric above ceiling: Level #4, West elevator soffit at 40801. |
|
12/04/2023 | COT - HCEL - Electrical Progress | Passed | ||
12/13/2023 | FCON – OH Piping & Hydro | Passed | ||
12/13/2023 | COT - FCON - Hood System - Final | Passed | ||
01/02/2024 | COT - HCPL - Plumbing Final | Passed | ||
01/04/2024 | COT - HCPL - Medical Gas/Test | Passed | ||
01/04/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
01/09/2024 | COT - FCON - Alarm - Final | Passed | ||
01/09/2024 | COT - FCON - Sprinkler - Final | Passed | ||
01/09/2024 | COT - HCME - Mechanical Final | Passed | ||
01/09/2024 | COT - HCBU - Building Final | Passed | Ok to make application for Certificate of Occupancy. | |
01/16/2024 | COT - FCON - Fire - Final | Passed | ||
01/18/2024 | COT - HCEL - Electrical Final | Passed |