Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Firewall/Fire Barrier/Firestop
Permit Number - T22CM02751
Inspection Description - COT - HCBU - Firewall/Fire Barrier/Firestop
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | ||
01/06/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | West wall of C.U.P. Ok to tape and Fire caulk. | |
01/11/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Sheetrock nailing for 2 hour rated walls and 1 hour rated smoke walls in Northwest area of section A: GL: 1 - 5/A - F. OK to tape progress areas. | |
01/31/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Section B North, Fire caulking for rooms and corridors. Ok to tape progress areas. | |
02/08/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Fire and smoke rated walls in South portion of Area B and Area A up to GL: #11. Ok to tape and Fire caulk progress areas. | |
02/21/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Area C, west stairwell area; Area A (Northwest), top out at 4’ below deck height, Ok to tape progress areas. | |
04/06/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Contractor cancelled. | |
04/07/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Area D South, Fire caulking along beams on live #1 | |
04/17/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Interior walls of elevator shaft. Fire rated sheathing in place. Need to firecaulk progress areas top and bottom. | |
04/18/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Exterior elevator shaft walls, Fire caulked and sealed. | |
04/19/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Interior sheathing of elevator shafts at levels #1 & #2. Complete proper Fire caulking | |
04/21/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Elevator shaft at Level #3; contractor cancelled. Will reschedule for 24 April | |
04/24/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Elevator shafts on Level # 2 and Level #3. Level #4 shaft is not ready, needs to be patched and Fire caulked. | |
04/26/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Elevator shaft on Level 4; not ready, contractor cancelled. | |
04/28/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Elevator shafts on Level #3 and Level #2 need to complete encapsulation of sheet rock with Fire caulking. | |
05/01/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Elevator shafts on Levels #3 & 4. Ok to tape and cover. | |
05/15/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | West elevator shaft fire caulked on Level #4. Exterior framing on South wall of Level #4, Ok to insulate and cover progress areas. Plumbing intermediate for waste and vent lines at 1 1/2” - 4” in North portion of Area C; Level #4. | |
05/19/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Contractor cancelled. | |
06/15/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Levels #1 & #2 shafts Fire caulked | |
06/16/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Elevator area of #1 & #2 facing. | |
06/20/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Contractor cancelled. | |
06/23/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Contractor cancelled. | |
06/27/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Contractor cancelled. | |
06/28/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Contractor cancelled. | |
06/29/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #2, East shaft from Level #2 to Level #3: fire stop caulked. | |
06/30/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Contractor cancelled. | |
07/05/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | East shaft and center shaft need to be Fire caulked. Will reschedule for 7 July. | |
07/10/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #3, East and West shafts. Level #1, Area D & Area C shafts. | |
07/12/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Not Ready | Contractor cancelled. | |
07/14/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #2, East and West shafts are Fire caulked | |
07/19/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #3 shafts (East and West | |
07/31/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #3, center shaft, Fire caulking is complete. | |
08/04/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #4, East shaft: ensure bottom of shaft at floor lever is,properly caulked. | |
08/09/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #4, East shaft; ensure second layer of Sheetrock is properly Fire caulked at,top and bottom of Sheetrock. | |
08/14/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Spray inhibitor with rock wall at floor edge for North and south patient rooms on level #2. | |
08/16/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #2, East portion (North and South rooms); ceiling edge Fire spray and rock wool placement. | |
08/18/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #2 patient rooms (12). Fire treatment at edge slab. | |
08/22/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #2, slab edge fire prevention system: rock wool and spray caulking in rooms: 20001, 20115, 20116, 20117, 20118, 20119, 20120, 20121, 20122, 20123, 20124, 20125. | |
08/25/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #1 slab edge Fire caulking at 10004, 10755, 10300N, 10300M, 10300E, 10300F. Level #4 slab edge Fire caulking at 40107, 40137, East Shaft, West shaft. Electric in walls, Level #2, 20134, 20128. |
|
09/07/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #3, edge of slab fire protection in rooms 300001 (west wall only), 30146, 30125A, 30201, 30100A corridor (East end). | |
09/28/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Slab edge fire protection in rooms: 20117, 20117A, 20118, 30118. Building above ceiling Level #1, rooms 10808, 10124, 10132, 10125, 10122, 10010, 10120, 10606, 10100A, 10100K, 10305. | |
10/13/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #4, Fire caulking in rooms: 40206, 40205, 40119, 40208, 40209, 40203, 40114, 40300A, 40127 | |
10/31/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Elevators (West) on levels #2 & #3. Ok to apply final layer of Sheetrock. | |
11/20/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Level #4, rooms: 40100, 40101, 40102, 40103, 40104, 40104, 40105, 40106, 40106, 40107, 40108, 40109, 40110, 40300A/B, 40301, 40302, 40303, 40304, 40305, 40306, 40121, 40122, 40123, 40124, 40125, 40129, 40130, 40308, | |
11/30/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | Fire riser lines on level #4 in East and West stairwells. See permit number T22CM00621 Electric above ceiling: Level #4, West elevator soffit at 40801. |
|
12/28/2022 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Electric rooms 10901, 10902, 10903 in Area E. |