Permit: T22CM02751

Parcel: 14101925B


Addresses:

5755 S HOUGHTON RD


Inspection Status: Not Ready

Inspection History: COT - HCBU - Building Progress

Permit Number - T22CM02751

Inspection Description - COT - HCBU - Building Progress

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/26/2022 COT - HCBU - Building Progress Not Ready
07/16/2024 COT - HCBU - Building Progress Passed
01/10/2023 COT - HCBU - Building Progress Partial Pass Masonry pre-grout at loading dock area; North wall at second lift (4’ - 8’). Ok to place grout in progress areas.
03/06/2023 COT - HCBU - Building Progress Partial Pass Masonry pre-grout: North wall of CUP: three areas were required by engineer to be changed at 4’ wall height. Change were completed on 3 March. Rebar in place, ok to grout progress areas.
03/13/2023 COT - HCBU - Building Progress Partial Pass Sheetrock nailing in operating rooms : 10501, 10502, and corridor 10500F. Ok to tape progress areas.
03/27/2023 COT - HCBU - Building Progress Partial Pass Top out Sheetrock nailing at 8’ below deck level on Level #1 throughout. Progress areas have been taped.
06/12/2023 COT - HCBU - Building Progress Partial Pass Level #2, patient rooms #20118, 20119, 20120, 20121: domestic water lines at 3/4” - 1 1/4”.
06/15/2023 COT - HCBU - Building Progress Partial Pass Caisson footings for columns (4 ), at 30” x 10’6”. Ok to place concrete in progress areas
06/21/2023 COT - HCBU - Building Progress Partial Pass Mechanical above ceiling: Chilled water system tested at 118 psi. Fire barrier, Fire caulking at Level #2, 8 patient rooms caulking at south wall between levels 1 and 2.
07/05/2023 COT - HCBU - Building Progress Partial Pass Excavation/layout rebar: water retention basins Northwest and south west. Rebar is in place, Ok to place concrete in progress areas.
09/20/2023 COT - HCBU - Building Progress Partial Pass Level #4, in wall electric, above ceilings at rooms: 40101A, 40102A, 40103A, 40104A, 40105A, 40106A, 40107A, 40108A, 40109A, 40110A, 40001. Level #2 ceilings at 20113, 20117A, 20118A.
10/13/2023 COT - HCBU - Building Progress Partial Pass Building above ceiling on Level #2 corridors.