Inspection Status: Not Ready
Inspection History: COT - HCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - HCBU - Building Progress |
|
Not Ready |
|
| 07/16/2024 |
COT - HCBU - Building Progress |
|
Passed |
|
| 01/10/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Masonry pre-grout at loading dock area; North wall at second lift (4’ - 8’). Ok to place grout in progress areas. |
| 03/06/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Masonry pre-grout: North wall of CUP: three areas were required by engineer to be changed at 4’ wall height. Change were completed on 3 March. Rebar in place, ok to grout progress areas. |
| 03/13/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Sheetrock nailing in operating rooms : 10501, 10502, and corridor 10500F. Ok to tape progress areas. |
| 03/27/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Top out Sheetrock nailing at 8’ below deck level on Level #1 throughout. Progress areas have been taped. |
| 06/12/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Level #2, patient rooms #20118, 20119, 20120, 20121: domestic water lines at 3/4” - 1 1/4”. |
| 06/15/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Caisson footings for columns (4 ), at 30” x 10’6”. Ok to place concrete in progress areas |
| 06/21/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Mechanical above ceiling: Chilled water system tested at 118 psi. Fire barrier, Fire caulking at Level #2, 8 patient rooms caulking at south wall between levels 1 and 2. |
| 07/05/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Excavation/layout rebar: water retention basins Northwest and south west. Rebar is in place, Ok to place concrete in progress areas. |
| 09/20/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Level #4, in wall electric, above ceilings at rooms: 40101A, 40102A, 40103A, 40104A, 40105A, 40106A, 40107A, 40108A, 40109A, 40110A, 40001. Level #2 ceilings at 20113, 20117A, 20118A. |
| 10/13/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Building above ceiling on Level #2 corridors. |