Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Framing
Permit Number - T22CM02751
Inspection Description - COT - HCBU - Framing
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - HCBU - Framing | Not Ready | ||
10/06/2022 | COT - HCBU - Framing | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. Area A, GL: 1 - 6.4/B - C. |
01/12/2023 | COT - HCBU - Framing | Partial Pass | North portion of area A; offices, corridors, procedural rooms. | |
02/23/2023 | COT - HCBU - Framing | Partial Pass | Area D, south and southeast exterior walls. Ok to cover progress areas. | |
02/28/2023 | COT - HCBU - Framing | Partial Pass | North and East portion of Area B. | |
03/27/2023 | COT - HCBU - Framing | Partial Pass | Exterior framing for Level #2; North and South walls, Level #3 North exterior wall. | |
04/06/2023 | COT - HCBU - Framing | Partial Pass | Equipment pad in CUP area; column piers on South exterior side. Ok to place concrete in progress areas. | |
04/17/2023 | COT - HCBU - Framing | Partial Pass | Exterior wall framing on Northeast corner of Area D: Levels #1 - 4. Ok to cover progress areas. | |
05/23/2023 | COT - HCBU - Framing | Not Ready | Contractor cancelled. | |
07/17/2023 | COT - HCBU - Framing | Partial Pass | Framing in Area D, rest room ceilings in 30119, 30120, 30121, 30123, 30122, 30123, 30124. Fire caulking for shaft protection at Level #2 East and West walls of center shaft; West shaft walls. | |
08/07/2023 | COT - HCBU - Framing | Passed | South portion of structure, columns are framed with metal studs. Ok to cover progress areas. Patient rooms on Level #3, North side of level have been edge Fire caulked. `Level #3 East shaft has been Fire caulked. See permit number T22CM00621 |