Rezoning Cases
Date - 11/22/2024 10:07 a.m.
Total Number Of Rezone Cases - (1)
Case No. | Description | New Zone | Status | Status Date |
---|---|---|---|---|
C9-05-02 | Civano Master PAD - Houghton | PAD | Effectuated | 06/01/2006 |
Permits
Address: 5755 S HOUGHTON RD
Date - 11/22/2024 10:07 a.m.
Total Number Of Permits - (41)
Permit | Status | Apply Date | Expired Date | Unit | Type | Description |
---|---|---|---|---|---|---|
TF-FCP-1223-01453 | Complete | 12/27/2023 | 07/02/2024 | Fire Construction Permit | Installation of a Honeywell Hwf2v-com panel onto an existing fire alarm system. | |
T21CM09774 | Complete | 12/21/2021 | 06/30/2024 | Commercial Building | Foundation Only for Future Hospital | |
TF-FCP-1222-00197 | Complete | 12/08/2022 | 12/09/2023 | Fire Construction Permit | Clean agent suppression system for computer room | |
TR-ROW-1122-00072 | Complete | 11/17/2022 | 01/19/2023 | Right-of-Way (ROW) | Asphalt patching a trench running S across Drexel Rd. The trench was cut by a different contractor who crossed Drexel Rd with two 6" ducts for TEP under ROW permit T22RW03556. Traffic control will be the same as was used in T22RW03556. Trench has been backfilled to subgrade and is ready to be paved. Trench is currently plated. | |
DP21-0302 | Complete | 11/08/2021 | 01/24/2027 | Development Package | Site/Grading/Swppp - TMC Rincon Hospital. | |
TR-ROW-1123-01325 | Void | 11/06/2023 | N/A | Right-of-Way (ROW) | PHASE 1 -COX TO OVERLASH 15983' OF AERIAL TO INSTALL NEW CATV CONDUIT FOR SYSTEM TIE- | |
TR-UTL-1123-02868 | Complete | 11/06/2023 | 02/25/2024 | Right-of-Way (ROW) - Utility | COX PRJ258363-1B TO OVERLASH 4600' OF AERIAL TO INSTALL NEW CATV CONDUIT FOR SYSTEM TIE | |
TR-UTL-1123-02872 | Complete | 11/06/2023 | 03/06/2024 | Right-of-Way (ROW) - Utility | COX PRJ258363-1A TO OVERLASH 6,449' OF AERIAL TO INSTALL NEW CATV CONDUIT FOR SYSTEM TIE | |
TR-UTL-1023-02846 | Complete | 10/31/2023 | 03/06/2024 | Right-of-Way (ROW) - Utility | COX PRJ258363-1C TO OVERLASH 4600' OF AERIAL TO INSTALL NEW CATV CONDUIT FOR SYSTEM TIE (ALONG HARRISON RD) | |
TR-UTL-1023-02701 | Canceled | 10/13/2023 | N/A | Right-of-Way (ROW) - Utility | COX TO OVERLASH 15983' OF AERIAL TO INSTALL NEW CATV CONDUIT FOR SYSTEM TIE | |
TS-PRM-1023-00545 | Complete | 10/05/2023 | 07/14/2024 | Sign - Permanent | Install one lighted Integrated Architectural Sign, 3 lighted wall signs and letters for the monument sign. | |
TR-ROW-0923-01194 | Issued | 09/27/2023 | 11/24/2023 | Right-of-Way (ROW) | Quality Issues with previous permit (TR-ROW-1122-00072) so work must be redone. Resubmitting for TR-ROW-1122-00072 with Traffic Control. Previous Description of Work: Asphalt patching a trench running S across Drexel Rd. The trench was cut by a different contractor who crossed Drexel Rd with two 6' ducts for TEP under ROW permit T22RW03556. Taffic control will be the same as was used in T22RW0556. Trench has been backfilled to subgrade and is ready to be paved. Trench is currently plated. | |
T22FC00669 | Complete | 09/27/2022 | 06/22/2024 | Fire Construction Permit | EXPEDITE-Automatic Fire Extingshing Sys - NEW FIRE SPRINKLER SYSTEM THROUGHOUT NEW 4 STORY HOSPITAL. | |
TR-ROW-0923-01191 | Needs Resubmittal | 09/26/2023 | N/A | Right-of-Way (ROW) | **** Resubmittal Required - upload traffic control plan for work area. **** Quality Issues with previous permit (TR-TOW-112-00072) so work must be redone. Previous Description of Work: Asphalt patching a trench running S across Drexel Rd. The trench was cut by a different contractor who crossed Drexel Rd with two 6' ducts for TEP under ROW permit T22RW03556. Taffic control will be the same as was used in T22RW0556. Trench has been backfilled to subgrade and is ready to be paved. Trench is currently plated. | |
TF-FCP-0923-01129 | Complete | 09/22/2023 | 03/28/2024 | Fire Construction Permit | Above ground storage tank for generator fuel | |
TF-FOP-0923-01534 | Complete | 09/22/2023 | 09/27/2024 | Fire Operational Permit | Operational Permit for Above ground generator and storage tanks | |
TF-FOP-0924-01050 | Void | 09/13/2024 | N/A | Fire Operational Permit | Operational Permit for Above ground generator and storage tanks will be applied for when the SLF permit is applied for. | |
T22RW03311 | Complete | 09/12/2022 | 01/15/2023 | Right-of-Way (ROW) | TEP to replace UG cable approx 200ft . TEP trucks may be parked in Street; Work Order: T39908 ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. UNDER A PAVEMENT MORATORIUM, ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 50’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. | |
TF-FCP-0824-00709 | Void | 08/23/2024 | N/A | Fire Construction Permit | VOID-Submit under Permit#TF-FCP-0824-00695 - THIS IS A MODIFICATION OF THE EXISTING FIRE ALARM SYSTEM, ADDING A NUMBER OF SMOKE DETECTORS ADJACENT TO A SELECT NUMBER OF DOORS WITH MAGNETIC HOLDERS TO INITIATE DOOR RELEASE CONTROL. PLUS, THE ADDITION OF SMOKE DETECTORS AND AUDIOVISUAL DEVICES IN THE NEW PHYSICIAN'S SLEEPING AREAS. | |
TC-REG-0824-00010 | Needs Resubmittal | 08/22/2024 | 02/18/2025 | Registered Facility | 60 Bed Acute Care Hospital | |
TF-FCP-0824-00695 | Issued | 08/20/2024 | 03/11/2025 | Fire Construction Permit | THIS IS A MODIFICATION OF THE EXISTING FIRE ALARM SYSTEM, ADDING A NUMBER OF SMOKE DETECTORS ADJACENT TO A SELECT NUMBER OF DOORS WITH MAGNETIC HOLDERS TO INITIATE DOOR RELEASE CONTROL. PLUS, THE ADDITION OF TWO SMOKE DETECTORS AND TWO AUDIOVISUAL DEVICES IN THE NEW PHYSICIAN'S SLEEPING AREA. | |
TS-PRM-0824-00342 | Issued | 08/02/2024 | 01/29/2025 | Sign - Permanent | Install one lighted wall sign | |
TF-FCP-0723-00911 | Complete | 07/31/2023 | 02/29/2024 | Fire Construction Permit | new ERRCS for TMC Rincon Hospital. | |
TR-UTL-0623-01849 | Denied | 06/22/2023 | N/A | Right-of-Way (ROW) - Utility | (1) 3' x 6' bell hole in dirt to install new gas service. | |
T22TUP0010 | Approved | 05/31/2022 | N/A | Zoning Permit Annual | 24' x 60' construction trailer for the construction of the TMC Rincon project. | |
T22CM02751 | Issued | 04/14/2022 | 01/12/2025 | Commercial Building | TI for Hospital | |
DP22-0082 | Complete | 04/06/2022 | 01/10/2027 | Development Package | Grading - TMC Rincon Hospital. | |
TF-FOP-0324-00333 | Complete | 03/26/2024 | 03/27/2025 | Fire Operational Permit | Fire State Licensed Facility Operational Permit | |
T22CM02072 | Complete | 03/21/2022 | 08/15/2023 | Commercial Building | 24 x 60 construction trailer w generator and temp water/sewer tanks for project 21016400 | |
TF-FOP-0324-00301 | Complete | 03/15/2024 | 03/26/2025 | Fire Operational Permit | TMC Rincon Hospital Compressed Gas Permit | |
TF-FOP-0324-00302 | Complete | 03/15/2024 | 03/26/2025 | Fire Operational Permit | TMC Rincon | |
TF-FOP-0324-00303 | Void | 03/15/2024 | N/A | Fire Operational Permit | VOID-SUBMIT A FIRE STATE LICENSED FACILITY PERMIT - TMC Rincon | |
T22OT00151 | Complete | 03/03/2022 | 09/10/2022 | Floodplain Use | Construction of multi-story hospital building with ancillary access, parking, utilities, landscape, | |
TF-FCP-0323-00433 | Void | 03/02/2023 | N/A | Fire Construction Permit | VOID-Needs to be submitted under T22FC00669 per Trish-This permit consists of the upper floors of the Hospital that has already been submitted on Permit #T22FC00669 within this permit is the Two Standpipes that serve Levels 2-4, along with 618 SSP and 87 SSU sprinklers with 6 floor control assemblies within the 4 floors. | |
TF-FCP-0223-00352 | Complete | 02/01/2023 | N/A | Fire Construction Permit | Install and flush new U.G Fire water line that will service the new remote FDC that will be installed no less than 100'-0" from the new Hydrant that is on site. | |
TC-COM-0124-00216 | Issued | 01/31/2024 | 10/06/2024 | Commercial Building | New permit to resolve outstanding exhaust fans testing under T22CM02751 per Juan Garcia | |
T22CM00621 | Complete | 01/26/2022 | 07/08/2024 | Commercial Building | Shell & superstructure package for hospital | |
TF-FCP-0123-00326 | Complete | 01/24/2023 | 04/26/2024 | Fire Construction Permit | New Fire Alarm system with Voice Evacuation and Partial Evacuation | |
TS-PRM-0123-00125 | Needs Resubmittal | 01/12/2023 | 07/11/2023 | Sign - Permanent | (MSP case TS-MSP0323-00005) Install 4 lighted wall signs and lighted faces for the monument sign | |
TC-CFO-0124-00020 | Issued | 01/11/2024 | 02/18/2024 | Certificate of Occupancy | TI for Hospital | |
TC-COM-0123-00455 | In Review | 01/11/2023 | 04/10/2024 | Commercial Building | TMC Rincon Campus PV is 101.05kW DC (145 Silfab 490W & 60 Silfab 500W modules). Grid-tied inverters will supply TEP service. 60 modules are roof-mounted with a ballasted system. 145 modules are mounted on a new custom steel canopy. |
Plans
Address: 5755 S HOUGHTON RD
Date - 11/22/2024 10:07 a.m.
Total Number Of Plans - (3)
Plan Number | Status | Application Date | Exp Date | Unit | Type | Description |
---|---|---|---|---|---|---|
CWH-22-0082 | Active | 04/06/2022 | 12/12/2022 | -- Commercial Water Harvesting Ordinance | Grading - TMC Rincon Hospital. | |
TS-MSP0323-00005 | Approved | 03/01/2023 | N/A | -- Master Sign Program | Increase allowable max square footage from 250sf in the scenic corridor to 452sf to install 4 lighted wall signs and the lighted faces of the monument sign. | |
TS-MSP0823-00011 | Complete | 08/24/2023 | N/A | -- Master Sign Program | (Approved 09/19/23 - appeal ends 10/3/23) Increase allowable max square footage from 250sf in the scenic corridor to approx 650sf to install 4 lighted wall signs and the lighted faces of the monument sign. To also add an Integrated Architectural Feature as the main sign at this location. |
Record Requests
Address: 5755 S HOUGHTON RD
Date - 11/22/2024 10:07 a.m.
Total Number Of Requests - (11)
Request Number | Status | Request Date | Completed Date | Type | Description |
---|---|---|---|---|---|
REQ-0124-00783 | Complete | 01/26/2024 | 01/29/2024 | Requests | Shell & superstructure package for hospital |
REQ-0124-00784 | Complete | 01/26/2024 | 01/29/2024 | Requests | Foundation Only for Future Hospital |
REQ-0623-03535 | Denied | 06/27/2023 | N/A | Requests | *** Work is not in City ROW *** BUILDING PERMIT REQUEST - Not needed, work area is within a parcel. |
REQ-0724-04917 | Approved | 07/16/2024 | 07/16/2024 | Requests | TI for Hospital |
REQ-0724-04920 | Denied | 07/16/2024 | N/A | Requests | This Project is not complete, all related permits need to be in completed status (TF-FCP-0824-00695), and conditions need to be satisfied. Please re-request once all items are in completed/approved status. TI for Hospital |
REQ-0724-04962 | Void | 07/17/2024 | N/A | Requests | Duplicate request- TI for Hospital |
REQ-1122-00055 | Complete | 11/08/2022 | 12/20/2022 | Requests | *(PLEASE RENEW FOR 30 DAYS)* TEP to replace UG cable approx 200ft . TEP trucks may be parked in Street ** PROOF OF NOTIFICAT; Work Order: T39908 |
REQ-1123-06259 | Canceled | 11/15/2023 | N/A | Requests | ** Permit has been cancelled per applicant** THIS HAS BEEN BROKEN UP INTO 3 SEPERATE DRAWINGS AND THE AGENT SUBMITTED SEQUENCE 1A VIA TR-UTL-1123-02872 SO THIS ONE CAN BE CANCELLED. |
REQ-1123-06260 | Withdrawn | 11/15/2023 | N/A | Requests | WAS INCORRECTLY SUBMITTED VIA GENERAL INSTEAD OF UTILITY. WITHDRAWING AND HAVE ALREADY RESUBMITTED |
REQ-1123-06428 | Complete | 11/27/2023 | 11/29/2023 | Requests | Quality Issues with previous permit (TR-ROW-1122-00072) so work must be redone. Resubmitting for TR-ROW-1122-00072 with Traffic Control. Previous Description of Work: Asphalt patching a trench running S across Drexel Rd. The trench was cut by a different contractor who crossed Drexel Rd with two 6' ducts for TEP under ROW permit T22RW03556. Taffic control will be the same as was used in T22RW0556. Trench has been backfilled to subgrade and is ready to be paved. Trench is currently plated. |
REQ-1223-06706 | Approved | 12/08/2023 | 12/28/2023 | Requests | GC has extended Project beyond expiration date. |