Permit: T22CM01378
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
6430 S COMMERCE CT
Address NEW:
6430 S COMMERCE CT
Apply Date:
02/24/2022
Applicant:
Erich Olds
Description:
New Storage Facility
Permit Reviews
Permit Number - T22CM01378
Permit Status: Complete
Permit Description: New Storage Facility
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/24/2022 | 3RD PARTY REVIEW - COMMERCIAL | 07/15/2022 | COMPLETED |
| 03/04/2024 | COMMERCIAL REVIEW - FULL v.2 | 04/09/2024 | APPROVED |
| 02/21/2024 | COMMERCIAL REVIEW - FULL v.1 | 02/21/2024 | REQUIRES RESUBMIT |
| 07/12/2023 | RESTAMP - COMMERCIAL v.1 | 07/13/2023 | APPROVED |
| 05/03/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/06/2024 | APPROVED |
| 10/16/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/20/2025 | REQUIRES RESUBMIT |
| 07/01/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/01/2025 | APPROVED |
| 01/23/2024 | COMMERCIAL REVIEW - FULL v.1 | 02/13/2024 | APPROVED |
| 10/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/06/2025 | APPROVED |
| 06/30/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/12/2023 | APPROVED |
| 08/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/29/2025 | APPROVED |
| 11/04/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 11/05/2025 | APPROVED |
| 09/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/17/2025 | APPROVED |
Conditions
Permit Number - T22CM01378
Permit Status: Complete
Permit Description: New Storage Facility
| Date | Description | Comments |
|---|---|---|
| 07/15/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 07/15/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 07/15/2022 | SPECIAL INSPECTION IS REQUIRED FOR EFIS. | |
| 07/15/2022 | SHOP DRAWINGS REQUIRED FOR METAL STAIRS. | |
| 07/15/2022 | SHOP DRAWINGS REQUIRED FOR METAL STUD DESIGN. | |
| 07/15/2022 | SHOP DRAWINGS REQUIRED FOR AUTOMTIC FIRE SPRINKLERS. | |
| 07/15/2022 | SHOP DRAWINGS REQUIRED FOR FIRE ALARM. | |
| 07/15/2022 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT. | |
| 07/15/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT. | |
| 04/10/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 04/10/2024 | The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account. | |
| 07/13/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 04/10/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 08/22/2025 | All new permit documents such as, Plan set and ALL other supporting permit documents required to be submitted to reflect the permit address change. City of Tucson will not Final this permit without all documents being updated with the correct address. | |
| 09/17/2025 | EFIS Designs must be submitted and approved prior to ... | |
| 05/06/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 04/10/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM01378
Permite Description: New Storage Facility
Total Outstanding Inspections - 13
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/05/2025 | COT - LCEL - Electrical Final | N/A | Re-inspection required | Re inspect fuses for mini splits on roof. Raise seal tight off of roof. West end of driveway hall missing labeling on j boxes and ko seals. 8/5/2025 |
| 08/08/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 04/10/2025 | COT - HCBU - Framing | N/A | Partial Pass | 4/9/2025 partial pass. 1st floor nailing and type of gyp board approved per wall types page A9.1. Okay to proceed progress areas. |
| 09/26/2024 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. |
| 08/08/2024 | COT - LCPL - Plumbing Progress | N/A | Partial Pass | 5/13/24: not ready needed information on sewer connection Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed. 6/7/24: partial approval from manhole to clean out at tie-in. Air pressure conducted and passed. 7/23/24: called Erich at 6:55am (no answer, left message stating I was in route for inspection), arrived on site at 7:03am called Erich (no answer), not ready. Canceled per contractor. 7/26/2024 7/29/24: Canceled by Erich 8/1/24: domestic water tie in per plans ok to backfill. Shading required Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed. 8/8/24: plumbing underground at rooms 102,103,106 passed. Ok to backfill. |
| 08/22/2025 | BULD - Electrical Clearance | N/A | Not Applicable | 8-22-25: not applicable. |
| 08/01/2024 | COT - HCPL - Sewer | N/A | Partial Pass | Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed. 6/7/24: partial approval from manhole to clean out at tie-in. Air pressure conducted and passed. 7/23/24: called Erich at 6:55am (no answer, left message stating I was in route for inspection), arrived on site at 7:03am called Erich (no answer), not ready. 7/29/24: Canceled by Erich 8/1/24: Domestic water tie in passed ok to backfill. Shading required |
| 08/08/2024 | COT - LCPL - Plumbing Final | N/A | Partial Pass | Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed. 6/7/24: partial approval from manhole to clean out at tie-in. Air pressure conducted and passed. 7/23/24: called Erich at 6:55am (no answer, left message stating I was in route for inspection), arrived on site at 7:03am called Erich (no answer), not ready. 7/29/24: Canceled by Erich 8/1/24: Domestic water tie in passed ok to backfill. Shading required 8/8/24: plumbing underground at rooms 102,103,106 passed. Ok to backfill. |
| COT - FCON - Fire - Final | N/A | Not Ready | ||
| 09/12/2024 | COT - LCPL - Rough Soil | N/A | Canceled | |
| 08/25/2025 | COT - LCME - Mechanical Final | N/A | Re-inspection required (with fee) | 8-25-25: wrap hot water copper line with R3 insulation above ceiling at restroom, missing restroom fan covers, and paint all exterior PVC/ABS. |
| 08/28/2025 | COT - HCBU - TCO | N/A | Partial Pass | 8-28-25: approved for Level 1 TCO. Pending conditions and water sterilization report. |
| 10/07/2025 | COT - LCBU - Preslab | N/A | Deferred |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM01378
Permit Description: New Storage Facility
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/08/2025 | COT - LCEL - Electrical Final | Passed | 8-8-25: electrical final approved. | |
| 08/22/2025 | COT - HCBU - Framing | Passed | 8-22-25: approved. | |
| 08/22/2025 | COT - HCEL - Electrical Underground | Passed | 8-22-25: approved. | |
| 08/22/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 8-22-25: approved. | |
| 08/25/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 08/26/2025 | COT - LCPL - Plumbing Progress | Passed | 8-26-25: approved. | |
| 08/26/2025 | COT - HCPL - Sewer | Passed | 8-26-25: pressure test from sewer to manhole verified. Plumbing final approved. | |
| 08/26/2025 | COT - LCPL - Plumbing Final | Passed | 8-26-25: pressure test from sewer to manhole verified. Plumbing final approved. | |
| 08/27/2025 | COT - FCON - Fire - Final | Passed | ||
| 08/27/2025 | COT - LCPL - Rough Soil | Passed | 8-27-25: approved. | |
| 08/28/2025 | COT - LCME - Mechanical Final | Passed | 8-28-25: approved. | |
| 08/28/2025 | COT - LCBU - Building Final | Passed | 8-28-25: building final approved. Note: a water sterilization inspection/report is required. |
|
| 09/26/2025 | ENGR Engineering Final | Passed | ||
| 10/08/2025 | COT - HCBU - TCO | Passed |