Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
In Review
Type:
Commercial Building
Apply Date:
02/24/2022
Applicant:
William Shipley
Description:
New Storage Facility

Permit Reviews

Permit Number - T22CM01378
Permit Status: In review
Permit Description: New Storage Facility
Start Date Submittal Complete Date Status  
02/24/2022 3RD PARTY REVIEW - COMMERCIAL 07/15/2022 COMPLETED Review Details
03/04/2024 COMMERCIAL REVIEW - FULL v.2 04/09/2024 APPROVED Review Details
02/21/2024 COMMERCIAL REVIEW - FULL v.1 02/21/2024 REQUIRES RESUBMIT Review Details
07/12/2023 RESTAMP - COMMERCIAL v.1 07/13/2023 APPROVED Review Details
05/03/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/06/2024 APPROVED Review Details
01/23/2024 COMMERCIAL REVIEW - FULL v.1 02/13/2024 APPROVED Review Details
06/30/2023 COMMERCIAL REVIEW - FULL v.1 07/12/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - T22CM01378
Permit Status: In review
Permit Description: New Storage Facility
Total Outstanding Activity Conditions - 15
Date Name
04/10/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
04/10/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/10/2024 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
04/10/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
04/10/2024 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
04/10/2024 SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED.
07/15/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
07/15/2022 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
07/15/2022 SPECIAL INSPECTION IS REQUIRED FOR EFIS.
07/15/2022 SHOP DRAWINGS REQUIRED FOR METAL STAIRS.
07/15/2022 SHOP DRAWINGS REQUIRED FOR METAL STUD DESIGN.
07/15/2022 SHOP DRAWINGS REQUIRED FOR AUTOMTIC FIRE SPRINKLERS.
07/15/2022 SHOP DRAWINGS REQUIRED FOR FIRE ALARM.
07/15/2022 SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT.
07/15/2022 SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT.

Conditions

Permit Number - T22CM01378
Permit Status: In review
Permit Description: New Storage Facility
Date Description Comments
04/10/2024 The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account.
07/13/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
05/06/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: In Review
Permit Number: T22CM01378
Permite Description: New Storage Facility
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
COT - FCON - Fire - Final N/A Not Ready Ok to backfill Underground. Will Hydro test another day.
08/08/2024 COT - LCPL - Plumbing Progress N/A Partial Pass 5/13/24: not ready needed information on sewer connection
Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed.
6/7/24: partial approval from manhole to clean out at tie-in. Air pressure conducted and passed.
7/23/24: called Erich at 6:55am (no answer, left message stating I was in route for inspection), arrived on site at 7:03am called Erich (no answer), not ready.

Canceled per contractor. 7/26/2024
7/29/24: Canceled by Erich
8/1/24: domestic water tie in per plans ok to backfill. Shading required
Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed.
8/8/24: plumbing underground at rooms 102,103,106 passed. Ok to backfill.
08/08/2024 COT - BULD - SWG Clearance N/A Not Applicable
08/01/2024 COT - HCPL - Sewer N/A Partial Pass Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed.
6/7/24: partial approval from manhole to clean out at tie-in. Air pressure conducted and passed.
7/23/24: called Erich at 6:55am (no answer, left message stating I was in route for inspection), arrived on site at 7:03am called Erich (no answer), not ready.
7/29/24: Canceled by Erich
8/1/24: Domestic water tie in passed ok to backfill. Shading required
08/08/2024 COT - LCPL - Plumbing Final N/A Partial Pass Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed.
6/7/24: partial approval from manhole to clean out at tie-in. Air pressure conducted and passed.
7/23/24: called Erich at 6:55am (no answer, left message stating I was in route for inspection), arrived on site at 7:03am called Erich (no answer), not ready.
7/29/24: Canceled by Erich
8/1/24: Domestic water tie in passed ok to backfill. Shading required
8/8/24: plumbing underground at rooms 102,103,106 passed. Ok to backfill.
08/22/2024 BULD - Electrical Clearance N/A Not Ready
08/22/2024 COT - HCEL - Electrical Underground N/A Partial Pass X2 4” schedule 40 at 48” depth. From disconnect switch feeding panel “MDP”. Okay to backfill progress areas. 8/22/2024
09/12/2024 COT - LCPL - Rough Soil N/A Canceled
09/26/2024 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday
9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout.
9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-REV3_1_PLAN SET_V2.PDF DOCUMENTS VIEW
REV3_1_REVISION NARRATIVE_V2.PDF DOCUMENTS VIEW
CONS-REV2_1_REV PLAN SET_V1.PDF DOCUMENTS VIEW
REV2_1_REV NARRATIVE_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-STANTEC_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
CALCS_STRUCT1_V1.PDF DOCUMENTS VIEW
CALCS_STRUCT2_V1.PDF DOCUMENTS VIEW
SIC-2023-06-30_V1.PDF DOCUMENTS VIEW
ENERGY_ALL_V1.PDF DOCUMENTS VIEW
CALCS_STRUCT1_V1.PDF DOCUMENTS VIEW
SIC-2023-06-30_V1.PDF DOCUMENTS VIEW
ENERGY_ALL_V1.PDF DOCUMENTS VIEW
SPECS_V1.PDF DOCUMENTS VIEW
CALCS_STRUCT2_V1.PDF DOCUMENTS VIEW