Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM01378

Parcel: 13727991E

Inspection Status: Requested

Inspection History: COT - LCBU - Excavation/Rebar/Zoning 

Permit Number - T22CM01378

Inspection Description - COT - LCBU - Excavation/Rebar/Zoning 

Inspection Status - Requested

Date Description Inspector Results Comments
COT - LCBU - Excavation/Rebar/Zoning  Requested
08/08/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
08/19/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.
08/22/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
08/30/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
09/06/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
09/11/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
09/12/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
09/20/2024 COT - LCBU - Excavation/Rebar/Zoning  Not Ready 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday
09/24/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday
9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout.
09/26/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday
9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout.
9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed.
10/10/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday
9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout.
9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed.
10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed.
10/17/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024
10/23/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday
9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout.
9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed.
10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed.

Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024

10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved.
10/25/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday
9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout.
9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed.
10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed.

Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024

10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved.
10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor
10/29/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday
9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout.
9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed.
10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed.

Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024

10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved.
10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor
10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor
10/30/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday
9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout.
9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed.
10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed.

Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024

10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved.
10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor
10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor
10/30/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 16'-20' Above finish floor.
11/01/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed.
8/19/24: reinforcement at elevator slab per plans ok to proceed.

Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section.
Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024
8/30/24: West elevator pit reinforcement per plan ok to proceed.
9/6/24: East Elevator pit reinforcement per plans ok to proceed.
9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour.
9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V
9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday
9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout.
9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed.
10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed.

Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024

10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved.
10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor
10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor
10/30/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 16'-20' Above finish floor.
11/1/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 20-24' Above finish floor.
11/05/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Both stairwells. 7th lift reinforcements per plan. Okay to grout progress areas. 11/5/2024
11/07/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Both Elevator shafts 7th lift okay to grout. West end stairwell at final height okay to fully grout progress area. 11/7/2024
11/08/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Final lift for both elevators. okay to grout. 11/8/2024