Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
Permit Number - T22CM01378
Inspection Description - COT - LCBU - Excavation/Rebar/Zoning
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/17/2025 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved. 10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor 10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor 12/3/24: reinforcement per plan 2nd floor decking at pour #1 west side of building 1/17/25: (2) 4" schedule 40 conduit from future CT cabinet location to transformer. Ok to backfill. |
|
| 02/03/2025 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved. 10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor 10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor 12/3/24: reinforcement per plan 2nd floor decking at pour #1 west side of building 1/17/25: (2) 4" schedule 40 conduit from future CT cabinet location to transformer. Ok to backfill. 2/3/25: 2nd floor framing perimeter passed. |
|
| 02/04/2025 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 11/25/24: not ready 12/10/24; reinforcement at 2nd floor decking pour 2 passed ok to proceed with concrete placement. 2/4/25: needed DP inspection |
|
| 04/04/2025 | COT - LCBU - Excavation/Rebar/Zoning | Re-inspection required | 4/4/25: inspection called in for retaining wall at SE corner of site. This inspection is required to be called under your DP permit for engineering. | |
| 04/04/2025 | COT - LCBU - Excavation/Rebar/Zoning | Re-inspection required | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved. 10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor 10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor 12/3/24: reinforcement per plan 2nd floor decking at pour #1 west side of building 1/17/25: (2) 4" schedule 40 conduit from future CT cabinet location to transformer. Ok to backfill. 2/3/25: 2nd floor framing perimeter passed. |
|
| 08/08/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. | |
| 08/19/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. |
|
| 08/22/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 |
|
| 08/22/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 8-22-25: approved. | |
| 08/22/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 8-22-25: approved. | |
| 08/22/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 8-22-25: approved. | |
| 08/22/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 8-22-25: approved. | |
| 08/30/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. |
|
| 09/06/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. |
|
| 09/11/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. |
|
| 09/12/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V | |
| 09/20/2024 | COT - LCBU - Excavation/Rebar/Zoning | Not Ready | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday |
|
| 09/24/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. |
|
| 09/26/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. |
|
| 10/10/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. |
|
| 10/17/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 | |
| 10/23/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved. |
|
| 10/25/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved. 10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor |
|
| 10/29/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved. 10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor 10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor |
|
| 10/30/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved. 10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor 10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor 10/30/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 16'-20' Above finish floor. |
|
| 11/01/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved. 10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor 10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor 10/30/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 16'-20' Above finish floor. 11/1/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 20-24' Above finish floor. |
|
| 11/05/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | Both stairwells. 7th lift reinforcements per plan. Okay to grout progress areas. 11/5/2024 | |
| 11/07/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | Both Elevator shafts 7th lift okay to grout. West end stairwell at final height okay to fully grout progress area. 11/7/2024 | |
| 11/08/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | Final lift for both elevators. okay to grout. 11/8/2024 | |
| 11/25/2024 | COT - LCBU - Excavation/Rebar/Zoning | Not Ready | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved. 10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor 10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor |
|
| 11/26/2024 | COT - LCBU - Excavation/Rebar/Zoning | Not Applicable | ||
| 11/26/2024 | COT - LCBU - Excavation/Rebar/Zoning | Not Applicable | ||
| 11/26/2024 | COT - LCBU - Excavation/Rebar/Zoning | Not Ready | 11/25/24: not ready | |
| 11/26/2024 | COT - LCBU - Excavation/Rebar/Zoning | Not Ready | 11/25/24: not ready | |
| 12/03/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 8/8/24: perimeter footing reinforcement per plans. Ok to pour GL W/18-27, C-W/13-1, C/18-27, Stairwell footing at south west corner GL T-X/1-2 ok to proceed. 8/19/24: reinforcement at elevator slab per plans ok to proceed. Partial pass. #2 west end Elevator pit. (Sump pit) s3-00 typical elevator pit section. Screen wall south end from east to west. Okay for concrete placement in footings. 8/22/2024 8/30/24: West elevator pit reinforcement per plan ok to proceed. 9/6/24: East Elevator pit reinforcement per plans ok to proceed. 9/11/24: vapor barrier has been placed at west half of 8" slab on grade. F40 at GL 10/H ok to pour. 9/12/24: footing F40. COL 18,R AND T; COL 28, U AND V 9/20/24: not ready for first lift at elevator for CMU wall. Will recall Monday 9/24/24: elevator stem walls reinforcement per plan ok to proceed with grout. 9/26/24: west half GL A-X/ 1-14 reinforcement per plan ok to proceed. 10/10/24: east half GL A-V.6/14-32.6 reinforcement per plan ok to proceed. Stairwell north east end, elevator east end, stairwell south west end and elevator west end. Reinforcements per plan. 1st lift okay to grout. 10/17/2024 10/23/24: reinforcement per approved plans at NE and SW staircase walls at 4-8'6" Above finish floor, N and S Elevator walls 4-8'6" above finish floor approved. 10/25/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 8'-12' Above finish floor 10/29/24: reinforcement per approved plans at South West and North East staircase walls and North and South Elevator walls all at 12'-16' Above finish floor 12/3/24: reinforcement per plan 2nd floor decking at pour #1 west side of building |
|
| 12/05/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 11/25/24: not ready 12/5/24: reinforcement per plan at pour 1 west end |
|
| 12/10/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 11/25/24: not ready 12/10/24; reinforcement at 2nd floor decking pour 2 passed ok to proceed with concrete placement. |
|
| 12/16/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 11/25/24: not ready 12/5/24: reinforcement per plan at pour 1 west end 12/16/24: Reinforcement per plan at east 3rd pour ar 2nd floor decking. |
|
| 12/20/2024 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 11/25/24: not ready 12/5/24: reinforcement per plan at pour 1 west end 12/16/24: Reinforcement per plan at east 3rd pour ar 2nd floor decking. 12/20/24: roof decking fastened per plans ok to proceed |