Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
Permit Number - T22CM01378
Inspection Description - COT - HCBU - Framing
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/29/2025 | COT - HCBU - Framing | Partial Pass | 1/29/25: partial pass for first floor perimeter framing. Ok to proceed with sheathing | |
| 02/03/2025 | COT - HCBU - Framing | Partial Pass | 1/29/25: partial pass for first floor perimeter framing. Ok to proceed with sheathing 2/3/25: 2nd floor exterior framing complete ok to proceed. |
|
| 02/19/2025 | COT - HCBU - Framing | Partial Pass | 1/29/25: partial pass for first floor perimeter framing. Ok to proceed with sheathing 2/3/25: 2nd floor exterior framing complete ok to proceed. 2/19/25: sheathing fastened per schedule. First and second floor |
|
| 03/25/2025 | COT - HCBU - Framing | Partial Pass | 3-25-25, partial pass interior framing for restrooms, break room, office area, equipment room, sprinkler & electrical room. Okay to continue with construction at progress areas. | |
| 04/02/2025 | COT - HCBU - Framing | Partial Pass | 4-2-25, in wall rough electrical in 1st floor for sales, break room, janitorial closet, sink, woman's restroom, men's restroom, electrical & riser room, elevator 2 mechanical room, elevator 1-okay to drywall progress areas. | |
| 04/10/2025 | COT - HCBU - Framing | Partial Pass | 4/9/2025 partial pass. 1st floor nailing and type of gyp board approved per wall types page A9.1. Okay to proceed progress areas. | |
| 05/16/2025 | COT - HCBU - Framing | Re-inspection required | 5-16-25, called point of contact and left voicemail advising contractor that I was on site at 6:23 hours. I asked several employees if they knew what needed to be inspected but could not assist. Left job site at 6:39am. | |
| 05/19/2025 | COT - HCBU - Framing | Partial Pass | 5-19-25, ground level shaft framing approved. Okay to continue construction at progress areas. | |
| 05/21/2025 | COT - HCBU - Framing | Partial Pass | 5-21-25, hard lid framing & seismic wiring for men's/woman's restroom, break room and sales area verified per plans. Also, inspected the framing around 2nd floor shaft, insulated, drywall nailing approved. Okay to continue with construction at progress areas | |
| 06/04/2025 | COT - HCBU - Framing | Partial Pass | 6-4-25: framing at mechanical rooms approved-okay to continue with construction at progress areas. | |
| 06/10/2025 | COT - HCBU - Framing | Partial Pass | Elevator #1 and #2 (Equipment rooms approved. Okay to proceed progress areas. 6/10/2025 | |
| 08/22/2025 | COT - HCBU - Framing | Passed | 8-22-25: approved. |